title: 'AI pile takeoff in Piper: manual, assisted and agentic workflow'
url: 'https://piper-ai.com/resources/ai-deep-foundations-takeoff-in-piper'
description: 'Build a reviewable pile takeoff in Piper: count caps by mark, split lengths by tip zone, calculate concrete, and keep testing separate from production quantities.'
contentTypes: [guide]
publishedAt: '2026-11-25T15:48:41.493Z'
author: 'Ido Gedanken, CEO'
readingTime: 11
---

# AI pile takeoff in Piper: manual, assisted and agentic workflow

1. Count locations first, then apply the correct cap schedule and elevation zone.
2. Manual, assisted and agentic measurements belong in one reviewable takeoff.
3. Installed length, procurement length and payable length need separate bases.
4. Test piles and test events are not interchangeable quantities.

For a GC estimator checking a deep-foundation package at bid-stage CDs, the useful output is not one pile count. It is a chain you can inspect: **cap location → cap mark → piles per cap → pile type → elevation zone → installed length**. Keep drilled-shaft geometry, cap concrete and the testing program beside that chain, not hidden inside a single assembly total.

Piper supports manual, assisted and agentic takeoff from PDF drawings in one editable takeoff file. Use manual measurement for ambiguous geometry, assisted tools for repeated candidates, and an agentic task for a defined set of measurements. The estimator still checks sheet coverage, scale, selection and the assumptions behind the quantities. Those are the [publicly described takeoff workflows](https://piper-ai.com/use-cases/takeoff), not a promise of an unreviewed foundation estimate.

This walkthrough is for quantity review, not foundation design or determination of driving criteria. If tip elevations, shaft dimensions or the test program remain unresolved, retain a question and a pricing basis rather than turning missing information into a measured quantity.

## 1. Set up the sheets around the foundation chain

Bring the drawing PDFs into a Piper takeoff, select the sheets, and set or calibrate their scale. Each measurement stays attached to its source page. Start with the foundation plans, cap schedules, pile or shaft schedules, sections and details needed for this package. Keep the specifications and geotechnical information available in the same project context, but distinguish drawing measurements from requirements read in text.

Use a known dimension to check calibration on each sheet you will measure. Check an enlarged cap detail separately from its parent plan. A correctly calibrated plan does not establish the scale of a detail on another page. Piper's setup and source-sheet measurement behavior are described on its [Takeoff page](https://piper-ai.com/use-cases/takeoff).

Before measuring, prepare a small basis register. These are suggested estimator fields, not Piper interface labels:

- Source sheet and revision.
- Cap mark or shaft type.
- Plan locations covered.
- Schedule row used.
- Diameter or section size.
- Cut-off or shaft-top elevation.
- Tip or shaft-bottom elevation and its source.
- Elevation zone and quantity status: indicated, assumed or unresolved.
- Testing status: production element, test element or undecided.

That register prevents a geometric count from silently becoming a geotechnical assumption. The federal guide specification for drilled piers asks designers to show top and bottom elevations, diameter, quantities by size, casing and reinforcement details, plus testing locations where required. Its basis-of-bid option uses number, total length and diameter together, not count alone. See [UFGS 31 63 29, November 2019, current posted text](https://www.wbdg.org/FFC/DOD/UFGS/UFGS%2031%2063%2029.pdf), drawing notes and §1.1.1.

These UFGS documents are editable guide specifications. Their bracketed choices are not requirements on every project. Use them here as technical examples; the issued contract documents establish the actual basis.

For the general product workflow outside this trade, use the [manual, assisted and agentic takeoff hub](https://piper-ai.com/resources/ai-takeoff-in-piper).

## 2. Choose the measurement mode by item, not by sheet

One foundation sheet can contain work suited to all three modes. There is no benefit in making every cap manual because one is irregular, or making every item agentic because the plan contains repetition.

Piper lets the estimator draw areas, lengths and counts manually; assisted tools propose boundaries, trace connected lines or find similar symbols; agentic takeoff builds editable measurements from a described task. All require review on the drawing. The distinctions below apply those [documented capabilities](https://piper-ai.com/use-cases/takeoff) to deep foundations.

| Foundation item | Manual starting point | Assisted starting point | Agentic starting point |
| --- | --- | --- | --- |
| Repeated pile or cap symbols | Place counts at confirmed locations | Select an example and inspect similar-symbol candidates | Request counts grouped by mark and source sheet |
| Irregular cap footprint | Draw the concrete outline and deductions | Trace connected outline segments where usable | Request editable cap areas with uncertain boundaries flagged |
| Drilled-shaft location and diameter | Count locations and verify dimensioned concrete size | Find repeated shaft symbols without treating symbol size as diameter | Request counts by scheduled shaft type with diameter basis stated |
| Pile length by zone | Review elevation inputs and apply the formula | Candidate counts support the calculation but do not establish tip elevations | Request grouped counts and lengths using only identified elevation inputs |
| Cage and testing basis | Review details and specification requirements directly | Do not treat symbol matching as a cage or test-program calculation | Keep unresolved reinforcement and testing outside accepted drawing totals |

### Draw manually where the concrete boundary needs judgment

Draw the area of an irregular cap from its actual concrete outline. Add deductions where the documents and your quantity convention require them. Use the section depth as a reviewed input for the volume calculation. A surrounding excavation line, grade beam or reinforcement envelope is not automatically the cap footprint.

For a round drilled shaft, verify the dimensioned concrete diameter before calculating cylinder volume. Do not use the outside diameter of the reinforcement cage as the shaft diameter. The drilled-pier guide lists shaft diameters and reinforcement as distinct drawing information; FHWA's drilled-shaft manual explains the concrete space around the cage in its discussion of temporary casing. See [UFGS 31 63 29, drawing notes](https://www.wbdg.org/FFC/DOD/UFGS/UFGS%2031%2063%2029.pdf) and [FHWA GEC 10, 2018, Chapter 3](https://www.fhwa.dot.gov/engineering/geotech/nhi18024.pdf).

Manual measurement is also the sensible fallback for a partly obscured pile location or a one-off cap whose outline is interrupted by notes. It resolves the specific ambiguity without changing the method for the rest of the plan.

### Use assistance for repetition, then clean the selection

For repeated pile or cap symbols, select a confirmed example and inspect the similar-symbol candidates. Separate unlike cap marks even when their outlines look alike. Remove legend samples, detail illustrations, duplicate background representations and unrelated matches. Add missed locations manually before accepting the count.

Use tracing where connected lines actually define the cap outline. Room-boundary assistance proposes an enclosed boundary, but a foundation drawing is not necessarily a room plan. If a proposed boundary follows adjacent linework rather than the concrete face, correct it or draw the area yourself.

Piper describes assistance as a starting point affected by dense linework, open boundaries, symbol variants and drawing quality, not a completeness check. Its [Takeoff documentation](https://piper-ai.com/use-cases/takeoff) requires inspection and correction of candidates. The dedicated AI pile takeoff pitfalls guide addresses automated-selection and reading failures in more detail.

## 3. Give the agent a bounded foundation task

Agentic takeoff is different from accepting individual assisted candidates. You describe the task; Piper reads the drawing, uses measurement and assistance tools, and creates editable measurements grouped into items. You then review that set in the same takeoff viewer used for manual measurements. This is the behavior described on the [Takeoff page](https://piper-ai.com/use-cases/takeoff).

Supply the relevant sheets and a clear boundary. Do not ask for a complete priced pile package while leaving cap schedules or elevation assignments undefined.

**Illustrative agentic request, not a transcript or demonstrated result:**

> "Count the pile caps on the selected foundation plans by cap mark, excluding schedule illustrations and duplicate details. Create editable count measurements at each cap location, grouped by mark and elevation zone. Use the identified cap schedule to report piles per cap and pile type, then calculate pile counts by group. Using only the cut-off and tip elevations explicitly assigned to each group in the supplied drawings, calculate vertical installed length as cut-off elevation minus tip elevation. Show the input basis for each group. Do not apply one tip elevation across unassigned zones. Measure cap concrete footprints separately from pile counts. Flag conflicting schedule rows, missing elevations, batter piles and unclear boundaries for review. Do not invent cage lengths or testing quantities."

This request defines the intended review artifact. It does not guarantee that every requested association will be resolved correctly. If the agent cannot establish the schedule or zone relationship, complete that portion manually and keep the assumption visible.

Review the result from location toward formula:

1. Open the source sheet and inspect the count locations and cap areas.
2. Confirm sheet coverage, revision and scale.
3. Match the grouped cap mark to the actual schedule row.
4. Confirm pile type and piles per cap before accepting multiplication.
5. Check each location's zone assignment against the elevation source.
6. Review formula inputs and units separately from geometry.
7. Correct, remove or supplement measurements and item assignments as needed.

The important check is the relationship, not merely the arithmetic. A correct count multiplied by the wrong schedule row produces a clean-looking wrong total. Repeating that multiplication will not expose the row error.

For the method-independent sequence rather than this product walkthrough, see how to do AI deep-foundation takeoff.

## 4. Roll up counts, lengths and concrete without losing the basis

Piper can roll measurements up by item, classify them through catalogs, and apply price-book references and formulas. The team supplies and reviews the pricing basis. Use those [documented quantity tools](https://piper-ai.com/use-cases/takeoff) to preserve the foundation relationships, not to conceal them inside one total.

Suggested item descriptions include cap mark, pile or shaft type, diameter where applicable, and zone. Keep count, installed length, concrete volume and reinforcement quantities distinct. A cage count is not a reinforcing-steel weight; a cap count is not a pile count.

### Worked cap-to-pile example

**Illustrative inputs only:** assume vertical piles, with 12 C1 caps carrying four piles each. Eight C1 caps are in Zone A and four are in Zone B. Another six C2 caps carry six piles each, all in Zone B. The indicated cut-off elevation is +100 ft. The indicated tips are +60 ft in Zone A and +48 ft in Zone B.

- C1, Zone A: 8 × 4 = 32 piles; length = 100 − 60 = 40 ft; total = 1,280 LF.
- C1, Zone B: 4 × 4 = 16 piles; length = 100 − 48 = 52 ft; total = 832 LF.
- C2, Zone B: 6 × 6 = 36 piles; length = 52 ft; total = 1,872 LF.
- Production total: 84 piles and 3,984 LF.

Applying the Zone A length to every pile gives 84 × 40 = 3,360 LF, understating this illustrative quantity by **624 LF**. The count is unchanged. The correction is to split the item by zone, not to recount all 84 locations.

Now assume the illustrative C1 caps are 8 × 8 × 3 ft and C2 caps are 10 × 10 × 4 ft, with no deductions or overlaps:

- C1 concrete: 12 × 8 × 8 × 3 ÷ 27 = 85.33 CY.
- C2 concrete: 6 × 10 × 10 × 4 ÷ 27 = 88.89 CY.
- Total cap concrete: 174.22 CY.

These are geometric quantities, not order quantities or a price. Reinforcement, excavation, working room and installation assumptions still need their own basis.

### Keep shaft diameter separate from cage diameter

**Second illustrative calculation:** a straight 3 ft diameter shaft, 40 ft long, contains π × 3² ÷ 4 × 40 ÷ 27 = **10.47 CY** of theoretical concrete. Using a 2.5 ft cage diameter instead gives **7.27 CY**, a 3.20 CY understatement per shaft. Across ten identical shafts, that is 32.00 CY using unrounded values.

The right correction is the concrete diameter input, not a general waste factor. Conversely, theoretical geometry does not establish actual concrete consumption. FHWA describes how cavities around casing can increase concrete demand in its [2018 drilled-shaft manual, §3 construction methods](https://www.fhwa.dot.gov/engineering/geotech/nhi18024.pdf). Keep any estimator allowance for additional consumption separate, with its ground-condition and installation basis. The manual addresses transportation foundations; it is not a universal building-foundation allowance.

For broader organization choices, use deep-foundation takeoff setup and formula tips; a repeatable calculator is the subject of the custom pile takeoff app guide.

## 5. Separate bid length, procurement length and testing

The illustrative elevation calculation above applies to vertical piles with assigned elevations. It does not determine final driving acceptance, ordered pile length or payment on every contract.

That distinction matters because the official examples use different structures. [UFGS 31 62 23.13, February 2021, §1.1](https://www.wbdg.org/FFC/DOD/UFGS/UFGS%2031%2062%2023.13.pdf) bases bids on indicated tip-to-cutoff lengths, then uses test data to establish calculated tips and driving resistances. It excludes additional payment for cutting off piles and portions above cutoff. [UFGS 31 62 16.13, November 2020, Change 2 February 2024, §§1.5.1 and 1.5.2](https://www.wbdg.org/FFC/DOD/UFGS/UFGS%2031%2062%2016.13.pdf) provides separate furnishing and driving provisions, with driving measured along the pile axis below cutoff.

Read together, these examples suggest a practical rule: **never use one unlabeled length field for installation, ordering and payment**. For a battered pile, vertical elevation difference is not axial length. For procurement, head allowance or other required excess may differ from a payable quantity. Populate those quantities only from the project's applicable basis.

### List test elements and test events independently

Read the issued test program directly. Record test piles, load-test events, required capacities, locations, reaction-system scope and whether test elements may remain in the finished work. Do not interpret a production plan with no test symbols as a zero testing requirement.

The concrete-filled steel pile guide allows properly located test piles with adequate driving resistance to be incorporated in finished work and separately provides for load tests. The drilled-shaft guide has distinct provisions for load tests, penetration tests and proof test holes. See [UFGS 31 62 23.13, §§1.1.3 and 3.2.1](https://www.wbdg.org/FFC/DOD/UFGS/UFGS%2031%2062%2023.13.pdf) and [UFGS 31 63 29, §1.1.2](https://www.wbdg.org/FFC/DOD/UFGS/UFGS%2031%2063%2029.pdf).

**Illustrative judgment call:** if three specified test piles occupy three of the 84 production locations and are accepted for permanent use, the physical total remains 84, not 87. If they are sacrificial and additional, it becomes 87 before considering reaction piles. Neither treatment determines the number of load-test events. Confirm the disposition rather than adding every test reference to production count.

Handle obstructions similarly. The drilled-shaft guide offers separate unit-price provisions for rock and other obstructions by diameter and length. That is a payment mechanism, not evidence of a measured obstruction quantity. Carry a contract-specific allowance or question where extent is unknown, rather than inventing footage from a plan count.

## 6. Carry the reviewed quantities into the trade-scope decision

Keep the accepted takeoff alongside the drawings, specifications, trade scopes and bid review in Piper. Its takeoff measures how much work is shown; [Scope Generation](https://piper-ai.com/use-cases/scope-generation) defines what each trade carries. These are separate workflows, not two names for a quantity total.

Before carrying a subcontractor number, compare its basis against the reviewed takeoff:

- Does the proposal use the same cap marks, pile types and zone lengths?
- Are test piles already included in production quantities or additional?
- Who carries cap concrete and reinforcement, cage fabrication, testing and cut-off work?
- Are uncertain lengths or obstructions addressed by an allowance, unit rate, qualification or unresolved question?

The GC's decision is whether that proposal covers the intended package on the agreed quantity and risk basis. A difference is not automatically a subcontractor error. It may be a different length convention, testing disposition or scope boundary.

Where the documents cannot settle the extent, use the distinction in [pricing design intent on incomplete drawings](https://piper-ai.com/resources/design-intent-estimating-incomplete-drawings) rather than presenting an assumption as measured work.

The finished artifact should let the next reviewer move backward from the carried quantity to the item, the schedule or formula inputs, and the source-sheet measurements. Piper's editable takeoff supports that review; the estimator owns the final geometry, coverage, scope and pricing decisions.

### Can Piper count piles from repeated foundation symbols?

Piper can find symbols similar to a selected example, or an agent can build editable counts from a defined drawing task. Review the candidate locations and item assignments before accepting them. For cap-based counts, separately verify the schedule row and piles per cap.

### Should pile length be measured on the plan?

Not for vertical depth established by elevations. Use the assigned cut-off and tip elevations as reviewed calculation inputs. A plan count establishes locations, not installed depth. Batter piles need an axial-length basis, and procurement or payable length must follow the applicable project requirements.

### Can an agent-created cap area be changed manually?

Yes. Piper's agent-created measurements are editable in the same takeoff viewer as manual measurements. Review the source sheet, scale, geometry and item assignment, then correct or remove the area as needed. Check the cap depth input separately before accepting concrete volume.

### Does a complete pile count include the testing program?

No. Production locations do not establish test events, reaction-system scope or the disposition of test piles. Read the issued specifications and testing details separately, then reconcile whether test elements overlap production locations or add physical work. Keep testing requirements beside the drawing quantities for trade-scope review.