# Albany lead-service replacement: align inventory, full replacements and paving

Price a lead-service street as a set of verified locations and unresolved decisions, not as the number in an inventory grant or a citywide program goal. For a GC, the key handoff is from material confirmation to an authorized full-service scope, resident access and a restoration sequence that fits the paving work.

Albany's [December 2025 Water capital improvement plan](https://www.albanyny.gov/DocumentCenter/View/14038/Albany-Capital-Improvement-Program---CIP---Five-Year-2026-2030-PDF) distinguishes inventory grant work, which excavates curb-box locations to confirm material and replaces lead found, from a repair grant for more systematic replacement of identified lead services (printed page 2-35, physical PDF page 45). The plan reports approximately 725 replacements in 2025, describes coordination with city paving, and gives a goal of 1,000 replacements in 2026 if funding is received (printed 2-39, physical page 49). Neither number defines the quantity in a particular contract.

## A street-level handoff register

The following is an illustrative estimating register. Each row should be tied to an address, map revision or bid item in the actual package. The named parties are proposed decision owners, subject to the contract.

| Decision | Evidence to request | Bid treatment until resolved |
| --- | --- | --- |
| Service material | Inventory record, field confirmation and location | Separate known lead, known non-lead and unknown locations; do not assume every investigation becomes a replacement |
| Replacement limits | Drawings and owner direction identifying public and private portions | Identify continuous work limits and who provides each portion; qualify gaps between packages |
| Resident access | Owner access process, appointments and interior work requirements | Record who obtains access and what happens when an appointment fails |
| Street and pavement | Paving limits, restoration details and city schedule | Show temporary and final restoration, ownership and sequencing as separate scope interfaces |
| Quantities | Address schedule, bid items and allowances | Carry contract quantities and stated assumptions, not citywide goals or grant totals |

Suppose an inventory location is unknown and the paving contractor has a scheduled street operation. An estimator can carry investigation under the applicable bid item and flag a conditional replacement, but should not silently count it as a confirmed lead service. If lead is found, the team needs direction on the replacement limits, resident access and the point at which restoration passes to the paving contractor. That is a hypothetical workflow, not a report of an Albany address.

## Close the gaps before leveling

Ask the owner for the latest service inventory, location-by-location design and access responsibilities, restoration specifications and coordination dates. Confirm whether the contract requires full replacement and how an inaccessible or unverified private portion is handled. The plan describes a city prohibition on partial repair, but the current code and its applicability need verification before relying on that statement. Separate legal requirements from the contract's actual work limits.

Compare utility and paving proposals at their shared edge: trench limits, temporary surface, final pavement, markings and acceptance. An exclusion in both bids is a GC scope gap; overlapping inclusions require a deliberate adjustment, not an automatic credit. Use the [Albany Water capital-plan decision guide](https://piper-ai.com/resources/albany-water-capital-program-preconstruction-decisions) to establish the current project stage and the [bid coverage guide](https://piper-ai.com/resources/construction-bid-coverage-guide) to record open boundaries.