# Albany West Community Center: trace pool scope across prime contracts and revised phases

An estimator reviewing the archived Albany West Community Center bid would have made a consequential mistake by assigning the pool and outdoor-shower piping solely from the plumbing trade label. The city's January 2025 addendum placed the pool, associated site piping and showers in general construction (GC), while assigning light-pole base installation to the electrical contractor (EC). The practical decision is to carry each issued instruction into the affected prime estimate and its interfaces, not to allocate all site work to one trade.

This is a completed-project case at 520 Livingston Avenue, not a live bid opportunity. The [January 2025 addendum](https://www.albanyny.gov/DocumentCenter/View/12166/AWCC-Phase-2--Main-Project-FULL-ADD-3-gc-m-e-and-5-p?bidId=) is a snapshot of the bid basis, not proof of the final contract. Its cover and inner pages carry different January dates, so this discussion identifies it by month. Obtain the complete issued set and any later changes before applying the lesson to a contract.

## Pool, excavation and electrical boundaries

The addendum says all pool scope, associated piping and the surrounding site area belong to GC, as do the outdoor showers and associated piping. It also directs GC to perform excavation required for plumbing contractor (PC) work, coordinating locations with PC. That does not transfer all site excavation to GC: the same addendum assigns EC all associated light-pole base installation work. Identify the limits and backfill or restoration responsibilities in the actual drawings and specifications before pricing the interface.

The food-service sheets are GC work unless the drawings say otherwise. Podcast furniture is by others and not in contract. These are different treatments: the first has a drawing-based exception, while the second should not quietly become a GC furniture carry. Each still merits an interface check for connections, access and installation boundaries where the issued documents require them.

## A filled scope-change register

This register translates the archived instruction into estimating actions. The old basis is the issue requiring review, not an assertion that every item had previously been assigned to another prime.

| Issue | Old basis to revisit | January addendum instruction and prime | Estimate consequence | Interface evidence needed |
| --- | --- | --- | --- | --- |
| Pool and outdoor showers | Plumbing-looking piping could be assumed to sit with PC | Pool, site piping and showers are GC | Carry the pool system and associated piping in GC scope | Pool drawings, connection limits and trade proposals |
| PC excavation | Excavation may be buried in a plumbing quote | GC excavates for PC work and coordinates locations with PC | Carry excavation in GC and check PC exclusions | Coordinated locations, depths and restoration limits |
| Light-pole bases | General site-work language could suggest GC | EC performs associated light-pole base installation work | Verify EC carry; avoid duplicating in GC | Base details and interfaces with surrounding site work |
| Food service | Equipment sheets could be treated as a separate package | GC unless drawings note otherwise | Reconcile drawing exceptions and trade coverage | Food-service sheets and equipment connections |
| Podcast furniture | Furniture might be assumed included | By others, not in contract | Exclude the furniture itself from GC carry | Delivery, placement and connections if shown |

## Separate allowances from informational pricing

The addendum replaces the earlier general requirements statement that allowances were none. It lists specific allowances: GC moisture mitigation of $50,000, EC data and telecommunications without equipment of $55,000, GC snow removal of $30,000, and GC perforated graphic metal panel of $113,500 for 1,135 square feet. It separately lists general prime allowances of $400,000 GC, $60,000 EC, $55,000 mechanical, and $50,000 plumbing and fire protection. See the [archived GC manual](https://www.albanyny.gov/DocumentCenter/View/11725/Project-Manual---GENERAL-CONSTRUCTION?bidId=) and the addendum together: the replaced manual language is not the operative basis for these items in that addendum.

Record the specific and general categories separately against the applicable bid form and instructions. An allowance is a pricing provision, not evidence of an extra award amount or final expenditure. Do not simply add the listed allowances to an unknown contract price. The addendum also says GC informational pricing for AC1 is included in the base bid, while GC alternates are excluded from the base bid. A separate AC1 figure is informational, so adding it again would double count it. Confirm the bid form and any later revisions before calculating a carry.

## A phase ledger is not an acceptance record

The addendum revised the schedule to target substantial completion of existing renovations, the gym addition and full facade on December 1, 2025, with a planned December 2 ribbon cutting. It targeted clinic interior and pool/site work for June 1, 2026. The earlier manual's pool and clinic target was March 2, 2026. The practical estimating question is what protection, access, temporary services and remobilization the revised handoffs require, not whether all work ends on the first date. Use this case alongside a method to [review phased turnovers and remobilization](https://piper-ai.com/resources/preconstruction-phasing-estimate-review).

| Phase basis | Archived target | Estimate review |
| --- | --- | --- |
| Existing renovation, gym and full facade | Substantial completion December 1, 2025; ribbon cutting planned December 2 | Price separation and turnover of usable areas from continuing work |
| Clinic interior | June 1, 2026 | Confirm access, services and acceptance requirements for later work |
| Pool and site | June 1, 2026 | Review seasonal site access, protection and return visits against actual issued schedule |

The city [reported the outdoor pool completed](https://www.albanyny.gov/m/newsflash/home/detail/699) as the final phase in an announcement dated July 1 and posted July 6, 2026. That is owner-reported completion of the pool phase, not proof of every contractual punch-list or warranty condition, clinic acceptance or a precise construction completion date. Later addenda, executed award and final cost are not established by these sources.

Before relying on this historical register, retrieve the full addenda sequence, bid form and prime drawings, executed agreement and changes, the accepted phase schedule, and turnover records. Mark each row with its controlling revision and unresolved interface. That makes a later price review traceable without treating an opening announcement as a contract closeout.