# Asser Levy Recreation Center: HVAC, pool plant and flood-mitigation boundaries

A GC/CM estimator should carry Asser Levy as an interconnected plant and protection review, not a standalone HVAC equipment allowance. The difficult question is who owns the shutdown, temporary service, flood-protection interfaces and restart when the electrical, pool and mechanical packages meet.

[NYC Parks tracker 9384](https://data.cityofnewyork.us/resource/4hcv-tc5r.json?$where=trackerid%3D%279384%27) describes HVAC reconstruction, an electrical service upgrade, replacement of pool equipment including filtration, and flood mitigation at the boiler and pool equipment rooms. Its November 13, 2026 update lists procurement. That snapshot is not an issued bid package or proof of an award.

## Four systems, one plant boundary

The following is estimator analysis, not a description of issued trade packages.

| Interface | Carry question | Evidence needed |
| --- | --- | --- |
| HVAC and electrical service | Who provides service cutover, equipment feeds and temporary power? | Single-line diagram, utility coordination and outage plan |
| Pool filtration and plant | Who isolates and reconnects piping, power and controls? | Existing and proposed schematics, equipment schedule and operating constraints |
| Flood mitigation and equipment rooms | Where does protective work meet doors, penetrations and equipment access? | Protection details, elevations and room surveys |
| Restart | Who tests each system and demonstrates operation together? | Commissioning plan, acceptance criteria and assigned witnesses |

A mechanical bidder's equipment price may not include electrical cutover or protection around a new penetration. Record each boundary against a document and identify the other package that accepts it. If drawings are incomplete, distinguish a priced assumption from an unpriced design question.

## Keep adjacent work in its own register

The [CB6 FY2027 district-needs report](https://cbsix.org/wp-content/uploads/2026/03/Statement-of-District-Needs-and-CB-Budget-Requests.pdf) says windows and HVAC are funded while other requested center improvements need additional funding. That funding statement does not define tracker 9384’s issued scope. Ask for the window-work boundary and any adjacent ESCR access or floodwall interface before adding them to this plant estimate.

## Ask before pricing the shutdown

1. Establish available access, operating restrictions and which services must remain available.
2. Mark isolation points and temporary arrangements, including who installs, maintains and removes them.
3. Sequence service cutover, filtration work and room protection with the owner and affected trades.
4. Define flushing, functional tests, training and restoration evidence in the issued requirements; carry an explicit assumption until then.

If a flood-protection detail changes equipment removal or access, revisit both the rigging and protection carries rather than treating the detail as an isolated architectural item.

For the broader package review, use the [MEP coordination review](https://piper-ai.com/resources/mep-coordination-preconstruction-scope) and the [logistics estimate review](https://piper-ai.com/resources/construction-logistics-plan-estimate-review).