# Atlantic Avenue BED778A: the 2020–2021 utility-to-street sequence

The archived [DDC presentation for BED778A](https://www.nyc.gov/assets/ddc/downloads/presentations/Project_BED778A-Presentation_for_CB2_3.3.21.pdf), whose cover says March 2020 and whose filename is indexed March 2021, describes a planned sequence for Atlantic Avenue from Carlton Avenue to South Oxford Street. Its value to a GC is the relationship between underground utility work and street reconstruction, not a current work permit or a verified completion date. DDC records a March 30, 2020 notice to proceed and anticipated completion in winter 2021.

## Read the utility-to-street sequence

The presentation describes one-block-at-a-time work. Its sequence separates preliminary work, DEP underground work and DOT above-ground work. [DDC presentation, pages 4–6](https://www.nyc.gov/assets/ddc/downloads/presentations/Project_BED778A-Presentation_for_CB2_3.3.21.pdf)

| Sequence | Activities in the historical presentation | Question for a new estimate |
| --- | --- | --- |
| Preliminary | Scheduling, outreach, tree protection, test pits and staging | Who owns each setup and how often does it recur? |
| DEP underground | Street cutting, excavation, watermain, hydrants, sewer and catch basins | What testing and handoff release the street phase? |
| DOT above ground | Curbs, roadway and sidewalks | What temporary surfaces and final restoration are included? |

The sequence is an analysis aid. It does not establish that each block actually followed the plan or that the project finished on the anticipated date. For a new bid, trace the limits and acceptance of each underground segment before carrying final pavement. An apparently complete pipe installation can still leave testing, temporary protection and a later return for surface work; the issued contract determines which of those activities applies.

## Price the operating cycle, not only the pipe

The historical schedule listed noisy work from 7 a.m. to 6 p.m. weekdays and pipe installation and necessary shutdowns from 9 p.m. to 5 a.m. weekdays, subject to event embargoes. It also described maintaining pedestrian and roadway access and coordinating temporary driveway restrictions case by case. These are project-specific historical arrangements, not current permission or a general NYC rule. [DDC presentation, pages 9–10](https://www.nyc.gov/assets/ddc/downloads/presentations/Project_BED778A-Presentation_for_CB2_3.3.21.pdf)

For a new package, put the permitted window, setup, traffic maintenance, shutdown approval, temporary surface and restoration in the same schedule row. A night crew may have less installation time than its nominal window once setup and reopening are accounted for; price the actual documents and production assumptions. The [night-work estimating guide](https://piper-ai.com/resources/night-work-construction-estimating) develops that operating-cycle review.

Obtain the current contract, access conditions and addenda before applying any historical sequence. The [NYC public bid review checklist](https://piper-ai.com/resources/nyc-public-construction-bid-review-checklist) helps separate the source presentation from the bidder's obligations. This is independent historical analysis.