---
title: 'AUS Arrivals and Departures Hall: review enabling works before the building package'
url: 'https://piper-ai.com/resources/aus-arrivals-departures-hall-enabling-scope-guide'
description: 'Review AUS hall enabling work: Red Garage removal, passenger access, utility continuity and the handoffs that precede foundations and terminal construction.'
contentTypes: [guide]
publishedAt: '2026-11-24T05:48:49.491Z'
author: 'Ido Gedanken, CEO'
readingTime: 2
---

# AUS Arrivals and Departures Hall: review enabling works before the building package

The AUS Arrivals and Departures Hall is in design. The airport places the new hall at the Red Garage and existing curbside area, with garage, roadway and utility enabling work, plus a pedestrian bridge. [AUS expansion](https://www.flyaustin.com/expansion-development-program) Source status checked November 17, 2026. Price the sequence that makes the hall site available before pricing the permanent building. The handoff is not just a vacant footprint: passenger routes, vehicle access and utility service must be accounted for at each change.

## Release the Red Garage site without losing access

The following register is estimating analysis, not a statement of the owner’s contract assignments. The owner overview establishes the project context; the current drawings, specifications and package documents determine what a bidder must carry.

| Interface | Review boundary | Decision to resolve |
| --- | --- | --- |
| Garage removal | Survey, disconnection, demolition and clearance | Who delivers the footprint and removes buried remnants? |
| Passenger and vehicle access | Wayfinding, temporary routes and curb changes | Who installs, maintains and changes each route? |
| Utility continuity | Temporary service, cutovers and permanent diversions | What must remain operating before demolition and who authorizes outages? |
| New hall | Foundations, shell, processing and baggage interfaces | What site condition and utility connection points does the building package receive? |
| Pedestrian bridge | Approaches, supports and interfaces with parking facilities | Which contractor provides supports, closures and handback? |

The airport lists Austin Commercial as prime and forecasts enabling, underground and later building packages. The anticipated release dates are preliminary, not evidence of an open solicitation. [AUS planned subcontracting](https://www.flyaustin.com/journey-aus-business-opportunities)

## Price the enabling sequence

Build a dependency line for each phase: replacement access available, services transferred, garage released, demolition completed, then foundations started. Ask for the owner-approved transition sequence before accepting a proposal that assumes unrestricted access. The order is an estimating hypothesis until the issued phasing documents confirm it.

The airport's forecast separates early enabling work in Q4 2026, demolition and underground MEP in Q2 2027, and foundations, core, shell and finishes in Q4 2027. Its expansion overview makes the Yellow Garage a predecessor to Red Garage closure. Track that dependency separately from the building contractor's own mobilization; the forecast dates do not reserve access or establish a live bid.

## Documents to request before committing

Obtain the garage-release milestones, utility isolation and reconnection drawings, temporary curb and passenger-route plan, and the exact enabling-package limits. The priced handoff should state which services remain live and what condition the demolition team must deliver to foundations. Compare the current package dates with the airport's preliminary forecast before committing to a sequence.

The [airport phasing review](https://piper-ai.com/resources/airport-construction-phasing-scope-review) provides a broader method for documenting these boundaries and carrying unresolved assumptions through bid review.
