# AUS Central Utility Plant: separate plant, storage and campus distribution scope

The AUS Central Utility Plant is in design, with construction estimated to start in 2027. The airport describes the plant, chilled-water thermal storage, heating and cooling piping, equipment and controls. [AUS expansion](https://www.flyaustin.com/expansion-development-program) Source status checked November 17, 2026. Level the plant and distribution proposals at physical connection points, then assign the work needed to make the combined system testable. A plant boundary drawn only at the building wall can leave flushing, controls or the final field connection unpriced.

## Separate thermal plant from distribution and storage

The following register is estimating analysis, not a statement of the owner’s contract assignments. The owner overview establishes the project context; the current drawings, specifications and package documents determine what a bidder must carry.

| Interface | Review boundary | Decision to resolve |
| --- | --- | --- |
| Plant equipment | Chillers, pumps and cooling-tower equipment | Who receives, rigs, sets and connects equipment? |
| Thermal storage | Tank and connections to the plant | Who provides tank interfaces, controls and integrated testing? |
| Power and controls | Electrical supply, instrumentation and control integration | Who terminates each cable and proves signals across package limits? |
| Hydronic distribution | Plant-side and campus-side piping | Where is the tie-in, and who supplies valves and final closures? |
| Flushing and commissioning | Cleaning, pressure tests and system startup | Who supplies temporary equipment and leads each combined test? |

The airport lists JE Dunn as prime. Its package listing marks long-lead/mechanical/electrical/storage and site/campus listings complete, while forecasting the plant buildings and cooling-tower package. The label describes the listing, not completion of the entire plant. [AUS planned subcontracting](https://www.flyaustin.com/journey-aus-business-opportunities)

## Define the condition delivered at each tie-in

Create one line per supply and return connection. Capture pipe size and elevation only from issued documents, then assign isolation, cleaning, test boundaries and turnover records. Resolve whether each bidder prices a standalone test or an integrated system test before leveling the bids.

The airport forecasts the plant buildings and cooling-tower package for Q1 2027. Earlier equipment, thermal storage and campus-utility listings are marked complete, but that label does not establish that equipment is installed or the combined plant is commissioned. Request a package-status register showing procurement, installation and accepted turnover separately.

## Documents to request before committing

Obtain the plant and campus distribution boundaries, thermal-storage interface drawings, control points list and integrated startup plan. Confirm which package brings each line to a testable condition and which supplies temporary flushing arrangements. Keep owner acceptance, vendor startup and contractor completion as separate milestones.

The [MEP interface review](https://piper-ai.com/resources/mep-coordination-preconstruction-scope) provides a broader method for documenting these boundaries and carrying unresolved assumptions through bid review.