---
title: 'AUS Concourse B and Tunnel: review the terminal, airside and tunnel boundaries'
url: 'https://piper-ai.com/resources/aus-concourse-b-tunnel-contractor-scope-guide'
description: 'Review AUS Concourse B and Tunnel boundaries across terminal shell, apron utilities, fueling and passenger conveyance, including provisions for future capacity.'
contentTypes: [guide]
publishedAt: '2026-11-24T06:38:58.368Z'
author: 'Ido Gedanken, CEO'
readingTime: 2
---

# AUS Concourse B and Tunnel: review the terminal, airside and tunnel boundaries

Concourse B and Tunnel is in design, with an early-2030s opening estimated by the airport. The owner describes a concourse with baggage and apron utilities, hydrant fueling, and a passenger tunnel with capacity for a future people mover. [Concourse B and Tunnel](https://www.flyaustin.com/expansion-development-program) Source status checked November 17, 2026. Separate the terminal shell from the apron and tunnel before comparing trade proposals. A price that reaches the concourse wall may still omit the crossing, termination or testing needed to make the adjoining system usable.

## Keep current tunnel work separate from future capacity

The following register is estimating analysis, not a statement of the owner’s contract assignments. The owner overview establishes the project context; the current drawings, specifications and package documents determine what a bidder must carry.

| Interface | Review boundary | Decision to resolve |
| --- | --- | --- |
| Terminal shell and baggage | Structure, openings and building-side connections | Which package provides sleeves, supports and final baggage-system interfaces? |
| Apron civil and utilities | Pavement, underground services and reinstatement | Where do pavement limits end at the building and tunnel? |
| Hydrant fueling | Fueling infrastructure and apron interfaces | Who provides excavation, isolation, testing and pavement restoration at each connection? |
| Passenger tunnel and conveyance | Tunnel structure, access and installed passenger conveyance | Who carries openings, power, controls and the transition into each terminal? |
| Future capacity | Space and provisions for a future people mover | Which provisions are in the current drawings, and which remain future work? |

The airport lists Hensel Phelps as prime and forecasts civil/apron, core-shell and finishes releases in separate future periods. Those forecasts are planning signals, not an invitation to bid or a final division of work. [AUS planned subcontracting](https://www.flyaustin.com/journey-aus-business-opportunities)

## Trace the concourse-to-apron handoffs

Start with an interface drawing around the concourse face and tunnel portals. Record elevation and location, each side’s assumed limit, shared penetrations and a named owner for closure. If the civil quote excludes the last connection and the shell quote starts inside the wall, carry the gap explicitly until the documents or an RFI resolve it.

The owner forecasts additional apron civil and utility work in Q2 2027, long-lead and core-shell work in Q4 2027, and finish-out in Q2 2028. Use those separate releases to ask when interface drawings must be fixed. In particular, future people-mover capacity does not establish that a people mover is included in the current tunnel package.

## Documents to request before committing

Request the tunnel and terminal interface drawings, apron and hydrant-fueling limits, baggage-system connection requirements and package-specific conveyance scope. For every future provision, mark whether the issued set requires space only, structural allowance, sleeves, power or installed equipment. Preserve an unresolved item rather than silently including a future system.

The [airport phasing review](https://piper-ai.com/resources/airport-construction-phasing-scope-review) provides a broader method for documenting these boundaries and carrying unresolved assumptions through bid review.
