# Austin fire-system review: track FIRR approvals beyond the building permit

Treat Austin fire-system review as a set of linked submissions, not a single building-permit milestone. Before awarding sprinkler, alarm or low-voltage work, assign each system's preparation, intake, fees, comments, approval and field testing to a named party. An approved building plan does not establish that every separate system submittal is approved.

[Austin Fire Plan Review](https://www.austintexas.gov/fire/austin-fire-plan-review) describes reviews of site, building and fire-protection-system plans and provides separate resources for fire systems, electrical access control and emergency responder communications. The City directs applicants to check a related FIRR system case through the associated building permit and to use the current fire-system plan review form for intake. Confirm project-specific requirements and applicable code edition with the design team.

## Make each system a separate row

This proposed register is a bid and handoff tool. Complete only the rows that apply, and enter actual case numbers and dates as they become available.

| System | Submission owner to confirm | Dependencies and evidence |
| --- | --- | --- |
| Sprinkler | Fire protection contractor and designer | Hazard basis, water supply, calculations, FIRR status and approved plans |
| Fire alarm | Alarm contractor and engineer | Device and sequence coordination, electrical power and system approval |
| Access control | Security and electrical team | Door hardware, release sequence and fire-alarm interface |
| Emergency responder communications | Specialty contractor and design team | Coverage basis, system design and applicable acceptance evidence |
| Shared closeout | GC and each system contractor | Inspection, integrated tests, corrections and turnover records |

Ask each bidder to name the preparer, submission and resubmission work, applicable fees and excluded interfaces. Include electrical connections, monitoring, controls, ceiling coordination and testing attendance where the issued design requires them. Do not assume the party providing hardware also owns programming or a separate submittal.

## Link approvals to the construction sequence

**Illustrative example:** The building permit is issued while the alarm contractor's system review remains open. The GC register should show the building permit and alarm FIRR as separate statuses, identify outstanding comments, and ask the project team what procurement or installation can proceed under the actual approvals. Do not promise a standard review duration or assume permit issuance authorizes fabrication of every system.

Log revisions and responses against the related case, then distribute approved details to the field. Schedule contractor testing, City inspections and any integrated testing according to the approved documents and project requirements. Preserve evidence of corrected deficiencies before relying on an occupancy milestone.

For the broader method, see [the sprinkler-scope assumptions review](https://piper-ai.com/resources/fire-sprinkler-scope-assumptions).