# Boston construction stormwater: assign SWPPP implementation and BWSC records

Price temporary stormwater work against a confirmed disturbance and operator basis. For a Boston project, the bid needs the party responsible for permit coverage, a workable SWPPP, installation and upkeep of controls, inspections and the records required for site closeout. Filing a notice is not the same as receiving authorization.

[BWSC’s storm drain requirements](https://www.bwsc.org/builders-contractors/site-plan-requirements/storm-drain-requirements) describe construction permit and SWPPP requirements for disturbance of one acre or more, including a smaller site that is part of a larger planned disturbance of that scale. BWSC identifies NOI tracking and SWPPP documents as site-approval inputs. [EPA’s New England permit program](https://www.epa.gov/npdes-permits/npdes-stormwater-permit-program-new-england) identifies the construction general permit for qualifying construction stormwater. Confirm the applicable permit and authorization with the environmental lead before starting regulated work.

## Allocate work by phase and operator

| Phase | Responsible party to name | Estimate and evidence to carry |
| --- | --- | --- |
| Before disturbance | Owner and environmental permit lead | Total planned disturbance, operator determination, SWPPP and notice preparation, authorization date |
| Mobilization | Site contractor | Install and protect controls in the project SWPPP and applicable permit conditions; coordinate access and staging |
| Active earthwork | Named operator and field lead | Inspections, maintenance, repairs, sediment handling and documented changes |
| Phased stabilization | Civil contractor and operator | Controls retained until the relevant areas meet the applicable closeout conditions |
| Closeout | Operator and owner | Final records and termination process under the applicable permit |

In an illustrative phased excavation, a control at the first entrance may need relocation as a second workface opens. The estimate should include that relocation, inspection access and the party who updates the plan, not just the initial installation. [Connect temporary controls with logistics](https://piper-ai.com/resources/construction-logistics-plan-estimate-review).

## Set the start and finish assumptions

Obtain the site boundary, phase plan and operator assignments before comparing site bids. Ask the permit specialist which inspection schedule and termination conditions apply to the actual authorization; do not assume every site uses the same frequency. Permanent infiltration and dewatering discharge are separate decisions in the [Boston obligation guide](https://piper-ai.com/resources/boston-preconstruction-obligation-decision-guide).