title: 'Boston’s 100-foot park review: carry the separate approval gate into the schedule'
url: 'https://piper-ai.com/resources/boston-parks-100-foot-permit-gate'
description: 'Check protected open space and Parks Commission review early enough to protect a Boston building-permit milestone.'
contentTypes: [guide]
publishedAt: '2026-11-21T12:18:12.371Z'
updatedAt: '2026-11-21T12:18:12.379Z'
author: 'Ido Gedanken, CEO'
readingTime: 1
---

# Boston’s 100-foot park review: carry the separate approval gate into the schedule

An otherwise ready Boston building permit can still depend on a separate Parks Commission decision. The [City's 100-foot review page](https://content.boston.gov/departments/parks-and-recreation/development-approval-near-public-parks-and-parkways) says construction or alteration within 100 feet of a park or parkway requires Commission approval before a building permit. Check the protected-space evidence and review route with the City rather than assuming proximity alone resolves the project-specific decision.

## Record the late gate before fixing the start

| Decision | Record | Schedule implication |
| --- | --- | --- |
| Protected space | Parcel and protected-space map; designer confirms relationship | Identify the review question early |
| Other approvals | Agency decisions and current design package | Review generally follows other agency reviews |
| Parks route | Administrative review or hearing, as confirmed by Parks | Carry the actual route and complete-submission dependency |
| Permit | Commission decision and building-permit status | Keep issuance and trade mobilization as separate milestones |

The City says small renovations or additions may receive administrative review. Published timing depends on complete information and should not be treated as a guaranteed approval date. A design change after other agency review may require the applicant to revisit the Parks submission, so identify the design owner and current drawing revision.

Parks design approval is separate from permission to occupy or use park land. If a crane or staging plan assumes that access, identify its separate permission and cost. [Separate access assumptions from permissions](https://piper-ai.com/resources/construction-logistics-plan-estimate-review) and check the [Boston decision guide](https://piper-ai.com/resources/boston-preconstruction-obligation-decision-guide).