# Boston permanent drainage: reconcile infiltration, UIC and maintenance scope

For a Boston site subject to BWSC’s permanent stormwater requirements, compare civil bids against the engineer’s approved infiltration design and its evidence requirements. Do not use a rainfall factor alone as a construction design or assume every renovation needs the same site-plan approval.

[BWSC’s storm drain requirements](https://www.bwsc.org/builders-contractors/site-plan-requirements/storm-drain-requirements) describe a criterion of one inch of rainfall times impervious area for projects below 100,000 square feet of floor area, and 1.25 inches at or above 100,000 square feet. Floor area selects the criterion; the impervious area is the surface used in the calculation. The engineer must determine applicability and prepare the project-specific analysis.

## Civil scope and evidence checklist

| Item | Project input to obtain | Bid and handover question |
| --- | --- | --- |
| Design basis | Floor area, impervious catchment and drainage analysis | Are all contributing surfaces and connections included? |
| Subsurface | Soil infiltration testing and engineer’s assumptions | Who pays for testing and changes if conditions differ? |
| Infiltration system | Approved location, excavation, media and protection | Who installs and protects it during construction? |
| UIC | Determine whether the new system requires an approval number | Who obtains and supplies the number to BWSC? |
| Operations | O&M plan and assigned maintenance responsibility | Are access and turnover documents included? |
| As-built | Green infrastructure documentation and survey | Which contractor collects records before concealment? |

BWSC describes testing, drainage analysis, O&M and as-built green-infrastructure documentation, and requires UIC approval numbers for applicable new infiltration systems. It also states that GCOD infiltration systems may not use underdrains or stormwater capture and reuse. [BWSC requirements](https://www.bwsc.org/builders-contractors/site-plan-requirements/storm-drain-requirements)

## Resolve construction interfaces before leveling

For an illustrative underground chamber, compare excavation limits, bedding, connection elevations, protection from construction sediment and survey responsibilities across civil and plumbing bids. A low installation price can leave testing or reinstatement unassigned. [Reconcile plumbing and site utilities](https://piper-ai.com/resources/plumbing-underground-scope-boundary), and keep permanent drainage separate from temporary SWPPP and dewatering decisions in the [Boston obligation guide](https://piper-ai.com/resources/boston-preconstruction-obligation-decision-guide).