# Boston wetlands permits: carry the Order of Conditions into construction scope

Before accepting a Boston site budget near a resource area, establish the Conservation Commission's jurisdiction decision and obtain the actual approval conditions. A mapped boundary is a prompt for professional review, not proof that identical controls apply to every site.

The [Commission's 2026 filing guide](https://www.boston.gov/sites/default/files/file/2026/01/2026.01.09%20Filing%20Guide_Conservation%20Commission.pdf) distinguishes a Request for Determination of Applicability (RDA), a Notice of Intent (NOI), boundary confirmation (ANRAD), and amendment, extension and completion routes. This Conservation NOI is distinct from a construction stormwater NOI.

## Convert the decision into a priced record

| Gate | Evidence and owner | Bid or schedule effect |
| --- | --- | --- |
| Jurisdiction | Environmental consultant's resource and buffer assessment; RDA if appropriate | Resolve which approval path applies |
| Boundary | Delineation and any ANRAD decision | Align site limits with grading and access |
| Authorization | NOI and actual Order of Conditions where applicable | Assign each condition to a trade and work period |
| Changed work | Designer and consultant compare revisions to Order | Ask Commission whether amendment is required before pricing a changed sequence |
| Expiry and completion | Order dates, extension decision and completion evidence | Carry monitoring and closeout through required period |

The guide states that an extension request must be submitted at least 30 days before an existing Order expires. The consultant should confirm current requirements and the specific order's dates. If an alternate moves grading toward a resource area, hold the saving conditional until the consultant and Commission address its effect on the approval. Identify the decision owner and any added field work or schedule exposure in the bid. [Record the approval basis](https://piper-ai.com/resources/construction-code-requirements-scope-review) and [check other Boston obligations](https://piper-ai.com/resources/boston-preconstruction-obligation-decision-guide).