# Buffalo city construction bids: verify apprenticeship agreements before pricing labor-hour commitments

On an applicable City of Buffalo construction bid, check the contractor and subcontractor apprenticeship arrangements before relying on a labor-hour forecast. A promise to hire apprentices later does not establish that the appropriate agreement was in place at bid. The issued solicitation, contract and responsible City officer determine the project's requirements and evidence.

[Buffalo Code section 96-13](https://ecode360.com/13580897) defines a construction contract for its apprenticeship provisions by reference to specified construction work with a value over $100,000. It calls for appropriate NYS Commissioner of Labor-approved apprenticeship agreements at bid for covered contractors and subcontractors. It also states a minimum 10% of the total construction workforce labor hours of all contractors and subcontractors performing the covered contract, with only hours in the trade in which an apprentice is registered counting toward that requirement. Confirm applicability and definitions for the issued procurement; this is not a rule for every project with a Buffalo address.

## Separate bid readiness from execution evidence

Use a row per participating entity and trade. This example is a planning tool, not an official submission or legal determination.

| Review item | At bid | During execution |
| --- | --- | --- |
| Entity and trade scope | List bidder and proposed subcontractor scope; check whether each falls within the clause | Reopen review when an entity or scope changes |
| Agreement or program | Identify appropriate approved program and agreement for the actual work | Retain current program and participation evidence |
| Employer participation | Obtain proof that each relevant employer participates in the applicable arrangement | Confirm any replacement employer and trade before its release |
| Bid submission | Match required statements and supporting documents to the invitation | Preserve accepted submission and subsequent decisions |
| Eligible apprentice hours | Forecast total construction workforce hours and eligible hours by registered trade | Reconcile hours worked in the registered trade to payroll and registration evidence |
| Supervision and ratios | Qualified lead checks applicable program standards and staffing assumptions | Verify current supervision and ratio conditions before scheduling work |
| Monthly evidence | Assign collection and review responsibilities | Collect contract-required census and records; reconcile denominator and exceptions |

Section 96-13 also describes bid-submission statements and monthly workforce census and payroll evidence. Read the exact required forms and timing for the contract rather than assuming the register replaces them.

## Test the forecast against the work packages

Illustratively, suppose a team forecasts 20,000 total construction workforce hours across the covered contract. Ten percent is 2,000 hours, but the useful question is whether the proposed packages can supply those hours through people registered in the trades in which they work. Allocate the forecast by trade and phase; ask the participating employers to support their capacity and identify supervision constraints. The figures are hypothetical, not a project benchmark or an official determination of the denominator.

If the electrical scope moves to a different firm, check that firm's relevant program evidence and update both the apprentice-hour forecast and bid or change documentation. A general training course or OSHA class does not by itself establish registration in an approved apprenticeship program. Buffalo training/apprenticeship routes can help identify pathways; the issued contract and program records establish what evidence is needed for this bid.

## Keep the two handoffs visible

At bid, preserve the program, employer participation, trade scope and submission. During work, collect the eligible hours, total hours, registration and workforce reports needed for the actual contract. Assign one person to reconcile the trade records and another to resolve missing evidence before the reporting deadline. Coordinate with the separate workforce and business-utilization records, but do not add their different percentages together.

### Can an employer plan to join an apprenticeship program after bid?

Do not assume that meets the requirement. The cited City provision calls for appropriate agreements established at the time of bid for covered work. Confirm the solicitation and the employer's actual evidence with the responsible officer.

### Do all apprentice hours count toward the stated 10%?

The provision limits counted hours to work in the trade in which the person is registered. Confirm program status, trade and the contract's total workforce-hour denominator.