# Buffalo construction stormwater: separate local review from state permit coverage

For a City of Buffalo redevelopment, a disturbance below one acre does not by itself dispose of stormwater review. The city's September 2023 [Unified Development Ordinance, section 7.3](https://www.buffalony.gov/DocumentCenter/View/12313/Unified-Development-Ordinance-Updated-092023?bidId=), and [Buffalo Sewer Authority's 2019 guidance](https://buffalosewer.org/app/uploads/2020/01/191015-Plan-Review-SW-Guidance-Final.pdf) describe a quarter-acre local threshold, including smaller work within a larger qualifying plan. State coverage is a separate determination. Ask the designer and authorities to confirm current applicability and project conditions before fixing the bid basis.

## Measure both the work and the larger plan

Record the area disturbed by this contract, the boundaries and total disturbance of the larger common plan, and the evidence behind each number. Include staging, utility trenches and other proposed ground disturbance in the designer's review rather than assuming the building footprint is the whole job. A smaller phase may be part of a larger plan. The local threshold is one-quarter acre, or 10,890 square feet; the dated UDO also addresses runoff from below-threshold activity.

Consider a **hypothetical** 0.6-acre redevelopment in the city. It exceeds the local quarter-acre threshold even if it is the whole plan. It is below one acre, but that fact alone does not determine state coverage: the designer must check the larger common plan and other applicable state conditions. [DEC's construction permit page](https://dec.ny.gov/environmental-protection/water/water-quality/stormwater/construction-activity-permit) identifies GP-0-25-001, effective January 29, 2025 through January 28, 2030, and describes the one-acre rule and special geographic cases. Do not substitute the obsolete permit number cited in the 2019 BSA guidance for the current permit.

## Use a two-axis applicability and scope register

Populate this register from the actual drawings and agency correspondence. The entries below are questions to resolve, not a determination for the hypothetical project.

| Decision or handoff | Evidence to record | Bid consequence if open |
| --- | --- | --- |
| Disturbance and common plan | Contract acreage, total plan boundary, phases and designer determination | Carry a stated assumption and request the missing boundary |
| Local BSA review | Applicable SWPPP, submission, comments and approved revision | Identify design and review dependencies before earthwork |
| State coverage | Current permit applicability, common-plan analysis and coverage evidence if required | Do not infer a state release from local review |
| Receiving system | Storm-only, storm overflow, storm relief or combined sewer and confirmed outfall | Check which documented design basis applies |
| Approved BMP and designer | Accepted practice, location, drawing revision and limiting-factor evidence | Price the approved system and identify an unresolved alternative separately |
| Construction controls | Installer, inspection and maintenance responsibilities and frequency from the issued plan | Include temporary measures and access in trade scopes |
| Permanent turnover | Owner, O&M documents, training and accepted completion evidence | Carry closeout and access obligations into the handoff |

## Compare the drawings before pricing an alternative

The BSA guidance calls for site/utility, grading, landscape and erosion-control plans. Compare the BMP footprint, elevations, access and construction sequence across all four. A planter on the landscape plan may conflict with a utility route or grading detail; ask the designer to reconcile it rather than estimating an unapproved relocation. The guidance describes a green-infrastructure preference and documentation of limiting factors for certain alternatives. Contaminated soil or groundwater, for example, is a reason to request the designer's evidence and BSA determination, not for the GC to select a different practice unilaterally.

Receiving-system type matters to the dated guidance's review paths. Confirm the actual connection and proposed discharges with BSA. Its [sewer permit page](https://buffalosewer.org/how-we-can-help-you/apply-for-a-sewer-connection-or-permit/) distinguishes sewer-tap review and a temporary-discharge application. An approved stormwater design does not itself authorize a temporary construction discharge.

## Assign the work through turnover

Separate the contractor who installs temporary controls from the party responsible for inspecting and maintaining them under the issued plan. Price repairs, access and sequencing on that basis. For permanent facilities, obtain the accepted O&M requirements and identify the owner receiving them; the dated UDO addresses professional preparation and ongoing owner maintenance. Track these dependencies alongside the wider [Buffalo approvals](https://piper-ai.com/resources/buffalo-construction-permit-sequence-prebid), and update the register when an issued plan or condition changes.

### Does 0.6 acre automatically require the state construction general permit?

No determination follows from that figure alone. Check the total common plan, applicable geographic conditions and current DEC permit with the designer and authority. The same project can have a separate Buffalo review obligation.

### Can the estimator choose a less expensive BMP?

Price an alternative as a proposal, not as the approved base. Obtain the designer's limiting-factor support and the applicable BSA review before changing the accepted design.