# Construction contract notices: build a deadline and recipient register before award

A construction contract notice is a communication required or contemplated by the agreement when a specified event occurs. An internal issue log can alert the team, but it is not necessarily the written notice delivered to the designated recipient by the required method. Before award, extract the trigger, clock, recipient and delivery rule for each notice and assign an owner.

A federal example illustrates why the details matter: when incorporated, [FAR 52.236-2](https://www.acquisition.gov/far/52.236-2) calls for prompt written notice to the contracting officer before disturbing specified differing site conditions. [FAR 52.249-10](https://www.acquisition.gov/far/52.249-10) addresses delay notice under its own terms. Neither provision supplies a universal deadline for other contracts. Have counsel interpret the actual agreement and law.

## Extract an obligation, not just a clause number

For each provision record the triggering event, when the clock starts, deadline and calendar, content required, named recipient and address, permitted delivery method, follow-up submissions and proof of receipt. Link the exact clause and revision. Separate notice of an event from any later detailed claim or cost submission if the contract distinguishes them. Assign a primary owner and backup with an internal reminder ahead of the contractual deadline.

Compare prime terms with the subcontract. A trade's internal report must reach the GC early enough for the GC to evaluate and deliver any prime notice. Review subcontract flow-down against the actual obligations and avoid assuming the subcontract automatically mirrors the prime agreement.

## Work a differing-condition record

In this illustrative project, excavation exposes a buried obstruction not shown in the issued documents. The subcontractor photographs it and alerts the superintendent. The prime contract must be checked immediately for preservation, notice and investigation requirements; the example does not establish that the condition qualifies for relief.

| Register field | Illustrative entry | Control |
| --- | --- | --- |
| Trigger and evidence | Obstruction found at grid C4 on May 6; dated photo and drawing reference | Preserve condition and ask counsel or project lead how to proceed |
| Recipient and method | Contract-designated recipient and method to be verified | Do not substitute an informal site conversation |
| Deadline and content | Extract exact clock and required description | Assign owner and earlier internal reminder |
| Delivery | Notice sent using the required channel | Retain copy and proof of transmission or receipt as applicable |
| Follow-up | Log inspection, direction, cost and schedule records | Track response and any separate submission deadline |

The superintendent's log and photo support the notice; they do not prove that it was properly delivered. Record the actual submission and response independently. Do not disturb or proceed on the strength of this example; follow the signed contract and obtain project-specific direction.

## Reconcile the register before award

[Ask contract questions before bidding](https://piper-ai.com/resources/survey-pre-bid-questionnaire) where the recipient, method, time calculation or required contents are ambiguous. Review notice provisions for changes, delay, concealed conditions and claims, then transfer the register to the project manager at handoff. Counsel should resolve conflicts and advise on consequences rather than relying on an informal assumption that late notice is harmless.