# Lender draw inspections: prepare funding evidence alongside the payment application

A lender draw inspection is a funding-control step whose evidence and timing come from the actual financing process. The GC should map its payment application to the borrower's draw package, identify who provides each record, and forecast the effect of any gap. A lender's release decision does not itself change the GC's payment terms or replace permit and special inspections.

The FDIC's October 2025 [construction and land-development lending examination module](https://www.fdic.gov/risk-management-manual-examination-policies/construction-and-land-development-lending) describes supervisory considerations including independent, qualified inspection, written progress reports, disbursement authority, remaining budget and lien or title controls. Those are lender examination considerations, not universal terms imposed on a particular GC contract. Ask the borrower and lender for the actual process and document requirements, and compare them with the [contractual billing basis](https://piper-ai.com/resources/construction-payment-application-prebid-review).

## Build a draw handoff register

| Field | Record for each application line or material item |
| --- | --- |
| Payment application | Schedule-of-values line, period, claimed progress and contractual submission date. |
| Progress evidence | Current observations, dated photographs, stored-material records or other documents the actual process requests; identify preparer and location. |
| Inspection | Requested and actual inspection dates, access contact, scope and report status. A scheduled inspection is not a completed inspection. |
| Budget to finish | Current forecast and source, pending changes and responsible borrower or cost reviewer. Reconcile differences rather than silently changing a GC invoice. |
| Lien or title documents | The specific forms and periods required by the relevant agreement, responsible party and status. Obtain legal advice on their effect. |
| Approval and release | Borrower, inspector and lender decision owners, conditions outstanding, approved amount and actual release status. |

The register is a coordination tool, not a substitute for the loan documents or a determination that an item is fundable. Establish the evidence basis for stored materials and changes with the actual decision makers; do not assume a particular invoice automatically qualifies.

## Fictional example: invoice and inspection do not align

Suppose a contract calls for a GC application on the last day of the month. The borrower schedules the lender's inspection several days earlier, before a major equipment delivery. The application can reflect the contract's permitted billing basis while the draw package may need another observation or document under the lender's process. The estimator and finance team should show both dates, the amount potentially affected, who will obtain the missing evidence and the cash-flow assumption pending a decision. Neither the earlier inspection nor an unapproved draw changes the contract by itself.

For bid purposes, ask who pays for requested reports and repeat visits, provides site access, maintains supporting records and coordinates subcontractor documentation. Carry an explicit timing assumption for financing review instead of inserting an invented standard number of days. Confirm payment and lien questions with the responsible commercial and legal advisers.

## Keep construction acceptance on its own track

A lender's progress observation serves disbursement decisions. It does not establish code acceptance, and [construction inspections](https://piper-ai.com/resources/construction-special-inspection-prebid-matrix) do not automatically satisfy the lender's evidence requirements. Maintain separate status and responsible sign-off for each, even where a report can be shared. At handoff, preserve the submitted application, inspection report, outstanding questions and actual funding decision so the next forecast can distinguish billed, approved and received amounts.