# Construction RFIs: connect the answer to the scope and number it changes

A request for information, or RFI, asks for clarification of project information. For an estimating team, receiving an answer is only one step. The useful closeout is showing what the answer changes in trade scope, quotation coverage, the estimate and any decision already made from the earlier information.

A clarification is also different from contractual authorization to change the work or price. The executed agreement and procurement instructions determine the applicable process.

## Ask a question that can change a decision

Identify the conflicting or missing requirement, cite its document location, explain the affected package and state what the team needs clarified. Avoid asking a broad question without showing why its answer matters to pricing or scope.

[AIA's construction-administration guidance](https://learn.aiacontracts.com/articles/6467196-managing-construction-administration-on-your-project/) describes RFIs as a way to obtain clarification from the design team. Its discussion of changes also makes clear that the clarification process and formal change instruments have different roles.

## Separate the question from the pricing assumption

Before an answer arrives, record what the estimate currently carries and who approved that provisional basis. Do not let a question marked “open” coexist with an undocumented plug that later appears to be a firm price.

An illustrative equipment-support detail might leave the structural and mechanical bidders each assuming support work is by others. The RFI needs to clarify the requirement, while the scope review needs to identify who carries the resulting work.

## Route the answer to the affected packages

List the recipients and downstream records that must be revisited. The answer may change an installation detail, quantity, access need, testing requirement or responsibility boundary. It can affect more packages than the one that originally raised the question.

Use the [drawing-revision method](https://piper-ai.com/resources/drawing-revisions-cascade-scope-bids-estimate) to trace those consequences. Do not assume that copying every bidder on an email proves the quoted work was updated.

## Verify the treatment in the proposal and estimate

Record the revised proposal or other pricing support, the selected carry and any remaining qualification. Distinguish “answer received,” “scope reconciled” and “price reviewed” as different statuses.

The [addenda-management guide](https://piper-ai.com/resources/construction-addenda-management-for-gc-estimators) addresses the same gap between document distribution and completed estimating work. Acknowledgment is useful evidence of receipt, not proof of substantive coverage.

## Preserve the contract-administration boundary

If the answer appears to change the contracted work, follow the applicable procedure and review the [difference between directives and change orders](https://piper-ai.com/resources/construction-change-directive-vs-change-order). Do not infer authority or entitlement from the title “RFI response.”

Piper's [Survey workflow](https://piper-ai.com/use-cases/survey) can help apply company questions to source documents and identify unanswered items. Its [Scope Generation](https://piper-ai.com/use-cases/scope-generation) workflow helps turn confirmed requirements into reviewable packages. The project team still issues the RFI through the required process and approves the resulting scope and pricing treatment.

For [Summit Playground reconstruction review](https://piper-ai.com/resources/summit-playground-reconstruction-parks-9972-contractor-guide), turn missing design and package information into specific bid questions rather than assuming the tracker supplies a construction scope.

For the related project-specific decision, [see how to review OGS construction bid requirements](https://piper-ai.com/resources/ogs-construction-bid-questions-addenda) and carry the result into bid review.

For an Albany designated property, the [historic exterior scope review](https://piper-ai.com/resources/albany-historic-exterior-alteration-scope-review) tests the approved material against a proposed substitute before procurement.