title: 'Country Club Creek wastewater: separate utility, drainage and trail scope'
url: 'https://piper-ai.com/resources/country-club-creek-wastewater-multiagency-scope-guide'
description: 'Review Country Club Creek utility, drainage and trail boundaries, preserving differences between the owner overview and the dated engineering-services scope.'
contentTypes: [guide]
publishedAt: '2026-11-25T18:53:51.075Z'
author: 'Ido Gedanken, CEO'
readingTime: 2
---

# Country Club Creek wastewater: separate utility, drainage and trail scope

For a civil GC evaluating Country Club Creek, build the estimate around physical limits and agency interfaces, not a single assumed utility package. The city describes water and wastewater improvements alongside drainage and two distinct trail components. The public overview does not establish how construction contracts will be divided.

## What the owner describes

[Austin Water’s project page](https://www.austintexas.gov/water/country-club-creek-wastewater) describes planning along Country Club Creek between Metcalfe Road and Oltorf Street, with construction anticipated within the next few years rather than on a firm date. It identifies 5,000 linear feet of new wastewater pipe, 480 feet of replacement water line and 500 feet of new water line. City partners describe creek stabilization and detention, 1,100 feet of parks trail, and a separate 550-foot lit Safe Routes to School trail. These lengths describe different work, not an established single-contract takeoff.

The city’s [March 2025 engineering-services recommendation](https://services.austintexas.gov/edims/document.cfm?id=446953) describes a different water-line summary and adds a 600-foot concrete trail alongside the greenbelt and school-route trails. Keep those observations separate from the current overview; neither summary establishes the final construction package. Ask for the latest water limits and a crosswalk of all trail components before combining quantities or treating an omitted item as deleted.

## Create a shared physical-limit register

This table is a preconstruction review tool. The questions are not established contract obligations or assignments.

| City program or work | Publicly described scope | Questions to resolve in issued documents |
| --- | --- | --- |
| Austin Water | Wastewater and water line replacement or extension | Where are tie-ins, bypass limits, testing and restoration, and who carries each? |
| Watershed Protection | Creek stabilization and detention between Metcalfe and Burleson | Where do earthwork and grading overlap utility access, and who restores disturbed stabilization? |
| Parks and Recreation | Greenbelt trail between Burleson and Metcalfe | What are trail limits, surface, subgrade and acceptance boundaries? |
| Transportation and Public Works Safe Routes to School | Lit concrete trail toward Linder Elementary | Who carries lighting power, crossings, path connections and acceptance? |

Plot each limit on the same current plan, including temporary access and the final surface. A utility trench crossing a future path is an example of a possible overlap, not an identified project condition. Ask whether utility restoration stops at rough grade or includes the finished path, and whether the path contractor accepts that substrate. Record both bidders’ answers and a priced resolution before carry.

## Request the documents that settle the boundary

Obtain the actual solicitation, drawings, specifications, schedule, permits, addenda and agency coordination documents for the package being priced. Check temporary creek protection, access, dewatering, existing utilities, testing and sequencing against those documents. Identify who controls approvals and who bears restoration after a later trade disturbs completed work. If a scope is outside the package, record the external predecessor and its assumed completion date instead of quietly pricing it as included.

Use the [plumbing and underground boundary guide](https://piper-ai.com/resources/plumbing-underground-scope-boundary) for comparing tie-in descriptions and exclusions. Recheck the city’s current project and procurement information before making a pursuit decision.