# Build a custom AI site concrete takeoff app in Piper

1. Build the quantity sheet around detail assignments, not just area totals.
2. Keep concrete thickness, base depth and reinforcing as separate rules.
3. Count ramp locations separately from warning panels and concrete quantities.
4. Test a detail-only revision before adding the tool to company templates.

For a GC estimator checking a commercial site package at bid or GMP, the useful custom tool is not a calculator that turns all sidewalk square feet into concrete yards. It is a **flatwork and curb quantity sheet that keeps each measured extent connected to the detail governing its construction**.

Build it to answer a harder question: if the plan area stays the same but a driveway detail changes, which concrete, base, reinforcing and carry decisions need another review?

Piper lets teams describe a tool in plain language and build it on the project's takeoff quantities, drawings, specifications and addenda. The result is reviewed like another workspace file, not accepted as an independently checked estimate. That is the relevant distinction in [Build with Piper](https://piper-ai.com/use-cases/construction-app-builder).

Start by defining the trade logic. Then ask Piper to build it.

## Make the detail assignment the center of the quantity sheet

For this tool, treat a measured region or run as an input, not a complete assembly. Give it a location, a source sheet and a governing detail. Attach concrete thickness, base depth, reinforcing and other requirements separately.

That structure matters because those requirements do not necessarily change together.

For example, the City of Davison's posted concrete specification distinguishes ordinary sidewalk, sidewalk through residential driveways and sidewalk through commercial driveways. Section 2.03 assigns different thicknesses and requires welded wire fabric through driveways. Section 3.04 also splits ramp thickness by distance behind the curb. These are jurisdiction-specific examples, not defaults for a general commercial project. They illustrate why one label such as “sidewalk” is insufficient for a calculator. See the [Davison concrete specification, sections 2.03 and 3.04](https://www.cityofdavisonmi.gov/DocumentCenter/View/606).

Base needs its own rule. Albert Lea's posted 2021 replacement specification calls for a minimum two-inch aggregate base under ordinary sidewalk but six inches at driveway locations. Copying the concrete thickness classification into the base calculation would not preserve that requirement. See [Albert Lea's specification, section 2.3A](https://www.cityofalbertlea.org/wp-content/uploads/Curb-Gutter-Sidewalk-Driveway-Specs-2021.pdf).

The estimating implication is broader than either local specification: **a constant area does not mean a constant scope**. A detail reassignment can change several quantity outputs without changing the polygon on the plan.

Do not use this flatwork tool as the design basis for retaining walls, foundations or structural equipment pads. Give those items separate reviewed detail assignments. If their dimensions or reinforcement are unresolved, keep them in an open-question register rather than applying an ordinary sidewalk assembly.

## Define the inputs before asking for outputs

A useful first version should read reviewed takeoff quantities and retain enough information to reconstruct each result. Specify these input groups in the request.

### Curb and gutter runs

Require a run identifier, location, curb type, measured LF, source sheet and detail reference. State which edge represents the measurement basis. For this tool, use one designated edge per run and retain transitions as separate segments.

Keep curb-only and integral curb-and-gutter items distinct. If the team wants concrete CY, use a reviewed cross-sectional area for each type, not a nominal curb height multiplied by an assumed width. The formula should expose the section area and its basis.

For the measurement process itself, use the separate guide to AI site concrete takeoff.

### Sidewalks, driveway crossings and aprons

Require net SF by region, concrete thickness in inches, base depth in inches, finish, reinforcing basis and source detail. Keep driveway-crossing sidewalk separate from the adjoining apron unless the documents and the team's measurement convention explicitly combine them.

Do not store only a blended thickness for all flatwork. Preserve the individual regions so a changed detail can update one region without rebuilding the entire quantity sheet.

Set ordinary sidewalk, ramps, driveway crossings and pads up as separately identifiable families. They may roll into a summary, but the underlying quantities should remain visible. The companion site concrete takeoff tips covers measurement and item organization rather than the calculator logic developed here.

### Ramps and detectable warnings

Record each ramp location and type. Give it its own concrete-area allocation, detail reference and detectable-warning requirement. Then record warning surfaces by location, dimensions and selected panel arrangement.

A ramp count is not necessarily a procurement panel count. Under the Access Board's public right-of-way accessibility guidelines, R305.1.4 describes warning-surface coverage as at least 24 inches in the direction of travel and the full width of the ramp run, excluding flares, or the applicable transition or landing. It does not prescribe one manufactured panel per ramp. See [PROWAG R305.1.4](https://www.access-board.gov/prowag/technical.html#r305-detectable-warning-surfaces).

Confirm the applicable accessibility standard and project detail before applying that rule. This tool is a quantity aid, not an accessibility approval.

### Pads, enclosures, walls and companion work

For an equipment pad, retain count, length, width, thickness and any separate thickened-edge or footing geometry. Record the governing detail and trade assignment. Include relevant electrical and other discipline sheets in the source review rather than restricting the input list to civil plans.

For a dumpster enclosure, separate the slab from walls, footings, gates and bollards. For retaining walls, separate concrete geometry from reinforcement and footing quantities. An enclosure count or wall LF can be a summary reference, but it should not silently supply missing design dimensions.

Add joint types, reinforcing, dowels and base as explicit quantity lines where required. Leave a requirement unresolved when its basis is missing. The discussion of [pricing design intent when drawings are incomplete](https://piper-ai.com/resources/design-intent-estimating-incomplete-drawings) is the better place to decide how that uncertainty becomes an allowance or qualification.

## Write formulas that preserve the measurement basis

The first version should produce a quantity sheet, a detail-rule register and an open-question register. Pricing can come later, with a team-supplied basis.

Use explicit units:

- **Flatwork concrete CY:** net SF × concrete thickness in inches ÷ 324.
- **Base in-place CY:** base footprint SF × base depth in inches ÷ 324.
- **Curb concrete CY:** run LF × reviewed cross-sectional area in square feet ÷ 27.
- **Rectangular pad concrete CY:** count × length in feet × width in feet × thickness in inches ÷ 324, with separate geometry for any thickened portion.
- **Warning-surface SF:** required coverage width in feet × coverage depth in feet, by location.

These are geometric conversions, not ordering quantities. Keep concrete waste, base purchasing conversions and other procurement allowances separate and labeled. Do not apply a hidden percentage to every output.

For base, allow an independently measured footprint. Do not assume it always ends at the concrete edge. For warning panels, require a selected panel size and layout before reporting procurement counts. For reinforcing, show the specified type and reviewed quantity basis; do not substitute an area allowance for a detailed bar takeoff without labeling the substitution.

Joint LF deserves a separate input or an explicitly defined layout rule. Area alone does not identify joint length or joint type. Albert Lea's posted specification distinguishes sidewalk contraction joints from curb-and-gutter contraction joints and gives them different maximum spacings. That is another reason to keep joint rules outside the concrete-volume formula. See [sections 2.3B and 3.3B](https://www.cityofalbertlea.org/wp-content/uploads/Curb-Gutter-Sidewalk-Driveway-Specs-2021.pdf).

Avoid universal spacing defaults. Even the archived Los Angeles permit guide, labeled Version 1.0, July 2001, describes control-joint locations at returns and tree wells as well as intervals. It is useful as an example of location-based logic, not as a current requirement for another project. See [the archived guide, page 3](https://permitmanual.engineering.lacity.gov/sites/permit/files/documents/BOE%20Standard%20Specifications%C2%A0Quick%20Reference%20Guide.pdf).

## Test a revision that changes no measured area

Use a synthetic fixture before connecting the tool to a live bid. The following quantities and rules are **illustrative**, not a project result or standard assembly.

Assume the reviewed takeoff contains 2,400 SF of ordinary sidewalk and 600 SF of sidewalk through a driveway crossing. The ordinary sidewalk rule is four-inch concrete over four-inch base. The original crossing rule is six-inch concrete over six-inch base.

The original outputs are:

- Ordinary sidewalk concrete: 2,400 × 4 ÷ 324 = 29.63 CY.
- Crossing concrete: 600 × 6 ÷ 324 = 11.11 CY.
- Crossing base: 600 × 6 ÷ 324 = 11.11 in-place CY.

Now introduce an **illustrative detail revision**: the crossing becomes eight-inch concrete, retains six-inch base and adds a stated reinforcing requirement. The plan geometry remains unchanged.

The revised crossing concrete is 600 × 8 ÷ 324 = 14.81 CY. The base remains 11.11 in-place CY. The reinforcing line becomes a review item until its quantity basis is resolved.

The arithmetic is not the test's main value. The test asks whether the tool can preserve three different treatments of the same region:

1. Concrete quantity changes because the assigned thickness changes.
2. Base quantity stays unchanged because its rule does not change.
3. Reinforcing needs a new basis rather than an invented quantity.

Ask for an affected-item register showing the original rule, revised rule, source revision and resulting treatment. Reject a version that reports “no quantity change” merely because total SF is unchanged. Also reject a version that changes base depth just because concrete thickness changed.

This is a proposed acceptance test, not a claim that Piper has already built or passed this particular site concrete app.

## Compare a side workbook with a tool on project data

A separate spreadsheet can implement the same formulas, references and review controls. The decision is how the team maintains the connections when project information changes, not whether spreadsheets can calculate concrete volume.

| Review concern | Spreadsheet on the side | Tool built on project data in Piper |
| --- | --- | --- |
| Quantity inputs | Team maintains imported or entered quantities and their source references | Reads the same project quantities and documents used by other Piper workflows |
| Detail rules | Team maintains a rule register and links each region to it | Request a rule register tied to the project's drawings, specs and addenda |
| Revision handling | Team updates the workbook and identifies dependent lines | Request an automation when project information changes, followed by estimator review |
| Source checking | Can retain source links if the team establishes and maintains them | Numbers link back to source pages in the workspace |
| Repeat use | Reuse the workbook while checking inherited project assumptions | Add the tested tool to company templates, then check each new project's rules |
| Responsibility | Estimator reviews formulas, source basis and carried quantities | Estimator still reviews formulas, source basis and carried quantities |

Piper's [construction app builder description](https://piper-ai.com/use-cases/construction-app-builder) supports the project-data, source-tracing, automation and template capabilities in this comparison. It does not establish a performance benchmark against a workbook.

## Give Piper an actual construction request

Piper supports plain-language requests for workbooks, registers and workflow automations. What teams build reads the same project information Piper reads, including quantities from takeoff, drawings, specifications, revisions and addenda. No coding is needed, and Piper asks where a request is unclear. See [Build with Piper](https://piper-ai.com/use-cases/construction-app-builder).

Here is an example request a team could type. It specifies the desired tool, not an existing preset or promised finished result:

> Build a flatwork and curb quantity workbook for this project using our reviewed site concrete takeoff quantities and the current drawings, specifications and addenda. >Report curb and gutter LF by type, sidewalk SF by concrete thickness, concrete CY, base footprint and in-place CY, ramp counts, detectable-warning surface dimensions and panel counts, and separate equipment-pad quantities. Keep retaining walls and structural pads separate from ordinary flatwork. >Keep each region or run connected to its source sheet, location and governing detail. Use one designated measurement edge per curb run. Store concrete thickness, base depth and reinforcing as independent rules with their source references. Do not use a project-wide average thickness. >Use net SF times thickness in inches divided by 324 for slab concrete CY. Use a separate base footprint and depth for base CY. For curb volume, use the reviewed cross-sectional area by curb type. Keep procurement allowances separate from geometric quantities. >Include a detail-rule register and an open-question register. Ask me when a detail, dimension, scope assignment or quantity basis is unclear. Do not treat missing information as zero. Show ramp and warning-surface locations separately, and ask for panel size and layout before calculating panel procurement counts. >When an addendum arrives, review its effect on the assigned site concrete rules and prepare an affected-item register for my review. Show changed source references and proposed quantity effects. Keep the previous reviewed basis visible in the register so I can compare it with the proposal.

The cross-trade guide to building a custom takeoff app in Piper covers the broader approach; this request adds the site concrete dependencies that a generic calculator would miss.

## Review the built file, then test the change automation

Review the result like any other workspace file. Start with source treatment, then formulas, then presentation. A neat summary is not proof that the underlying assignments are right.

Use the synthetic revision above to inspect the actual built result:

- Open the source behind a crossing quantity and confirm the assigned detail.
- Verify units and formula treatment, including deductions and thickened portions.
- Confirm base and reinforcing rules are independent of concrete thickness.
- Check that missing panel layouts and structural dimensions remain questions.
- Introduce the test addendum and inspect the affected-item register.
- Confirm the proposed change has not been confused with the estimator's reviewed carry decision.

Piper supports automations that run when something changes, such as an addendum arriving, and one step can hand work to the next. The site concrete automation described here is a requested configuration to build and test, not an assertion of a universal built-in revision rule. See [the app builder workflow](https://piper-ai.com/use-cases/construction-app-builder).

An automation that reviews new information does not by itself validate existing measurement geometry. Reopen the relevant takeoff when the revision changes extent, item assignment or measurement basis. Piper's [takeoff workflow](https://piper-ai.com/use-cases/takeoff) provides editable manual, assisted and agent-created measurements on source sheets; the estimator still checks scale, geometry and coverage.

Keep the app's calculation checks separate from the automated-selection review covered in AI site concrete takeoff pitfalls.

## Template the logic, not the last project's assumptions

Once the tool passes the team's acceptance tests, add it to company templates so future projects start with the same structure. Piper supports this reuse, with workspace permissions and history retained. See [Build with Piper](https://piper-ai.com/use-cases/construction-app-builder).

Carry forward field definitions, unit conventions, formula structure and review tests. Require confirmation of each new project's concrete thicknesses, base depths, curb sections, reinforcing, warning-surface details and trade assignments.

The template should make unanswered questions conspicuous, not disguise them as company-standard quantities. The result worth standardizing is a reviewable chain from measured extent to construction requirement to quantity and carry decision.

### Does this app replace site concrete takeoff?

No. The proposed app calculates and organizes quantities from takeoff inputs and reviewed construction rules. Piper's takeoff workflow measures PDF drawings through manual, assisted and agentic methods. The estimator still checks source sheets, scale, geometry, coverage and scope before using the quantities.

### Can the tool calculate concrete and base from the same area?

Yes, when their footprints are confirmed to match. Keep thickness and base depth independent, and allow a separate base footprint where the detail requires it. Report geometric concrete CY and in-place base CY separately from purchasing allowances or conversion factors.

### Should a ramp count produce one detectable-warning panel per ramp?

No. Keep ramp locations, required warning-surface coverage and procurement panel counts separate. Confirm the applicable project detail, panel dimensions and layout before converting coverage into a panel count. The PROWAG coverage provision describes surface extent, not one manufactured panel for every ramp.

### What should happen when an addendum changes a detail but not the plan area?

Request an affected-item review, not a geometry-only check. The tool should identify which assigned concrete, base or reinforcing rules changed and present proposed effects for review. Test that behavior on a synthetic detail-only revision before relying on the automation for a bid.