---
title: 'Build a custom HVAC bid leveling tool in Piper'
url: 'https://piper-ai.com/resources/custom-hvac-bid-leveling-app-piper'
description: 'Build an HVAC leveling tool that separates equipment, controls, TAB and commissioning, traces adjustments to sources, and reopens decisions when bids change.'
contentTypes: [guide]
publishedAt: '2026-11-30T06:32:08.869Z'
author: 'Ido Gedanken, CEO'
readingTime: 10
---

# Build a custom HVAC bid leveling tool in Piper

1. Build around HVAC systems and scope ownership, not one checkbox for each specification section.
2. Keep bidder adjustments separate from costs carried in other trade packages.
3. A controls exclusion can leave TAB support uncovered even when a separate controls quote exists.
4. Test revised bids against earlier decisions before adding the tool to company templates.

An HVAC leveling tool should answer two questions separately: **what does this bidder carry, and what will the GC spend to cover the complete HVAC package?** If it merges those questions into one adjusted total, it can hide controls costs in another package, duplicate insulation, or treat equipment startup as complete commissioning support.

For a GC estimator comparing commercial HVAC proposals at bid-stage CDs or a GMP checkpoint, build the ownership rules before the dashboard. Piper can build a custom tracker, workbook or register from a plain-language request, using the same project documents, quantities, scopes, bids and decisions as its other workflows. The result is reviewed like any other workspace file. That is the useful starting point described in [Build with Piper](https://piper-ai.com/use-cases/construction-app-builder), not a promise that the first draft is ready to carry.

This guide defines the tool's review logic, then gives a request and test exercise. It does not replace design approval, determine whether a substitution is acceptable, or make the final carry decision. For the underlying leveling process, use the [construction bid leveling guide](https://piper-ai.com/resources/construction-bid-leveling-guide).

## Build HVAC rows around systems and obligations

Use equipment tags and systems as the spine of the comparison. Attach obligations to them. A row labeled “controls included” is not enough if the equipment quote covers factory controllers but leaves field devices, building integration and testing support unresolved.

The official guide specifications illustrate why the rows need more detail. UFGS 23 09 00 separates building-level DDC from the front end and integration covered in Section 25 10 10, and references separate controls-device and sequence sections. Its proprietary-system provisions also require an interface to the open building control network with the functionality shown on the points schedule. Equipment controls and building integration are therefore different review questions under that specification. See [UFGS 23 09 00, August 2024, Change 1 August 2025, paragraphs 1.1 and 1.1.2.2](https://legacy.wbdg.org/FFC/DOD/UFGS/UFGS%2023%2009%2000.pdf).

These are guide specifications for military construction, not universal commercial requirements. The editions used here were checked against the [public UFGS listing](https://legacy.wbdg.org/dod/ufgs?page=2) on November 24, 2026. Use the project's issued and edited sections as the actual pricing basis. Do not load every option in an unedited guide into a commercial scope.

For a rooftop-unit and VAV package, start with the following proposed row structure. It is an estimating design, not a prescribed trade split.

| Scope group | Rows to distinguish | Evidence the reviewer needs |
| --- | --- | --- |
| Equipment | Scheduled unit, proposed unit, accessories, factory controls, startup | Equipment schedule, specification, proposal and substitution status |
| Air distribution | Duct system, pressure basis, dampers, access, leakage testing | Duct plans, details, testing schedule and proposal limits |
| Piping | System, valves, specialties, condensate destination and connections | Piping plans, risers, equipment details and package boundaries |
| Insulation | Duct, pipe and equipment; factory versus field; jackets and accessories | Insulation schedule, details, equipment scope and insulation quote |
| Controls | Factory devices, field devices, wiring, programming, integration and test support | Points schedule, sequences, controls scope and proposal exclusions |
| TAB | Balancing, leakage testing, prerequisite work, technician support and repeat attendance | TAB section, commissioning section and each bidder's attendance basis |
| Completion support | Startup, functional testing assistance, seasonal work, training and closeout | Commissioning requirements, equipment requirements and bidder qualifications |
| Interfaces | Power, curbs, louvers, roof work, permits and furnished-by/install-by splits | Mechanical, electrical and architectural details plus adjacent scopes |

Give each row a system or equipment tag, required scope source, proposed owner, bidder response, quote source, unresolved question and cost treatment. Permit “not addressed” as an answer. Silence is not an inclusion and it is not automatically an exclusion.

For more interface examples, use the existing [HVAC scope-gap and double-up review](https://piper-ai.com/resources/hvac-scope-gaps-and-double-ups-bid-leveling); this tool's job is to preserve the ownership and pricing decision for each interface.

## Normalize the basis before computing an adjustment

Write the rules in language a second estimator can audit. Recommended rules are:

1. **Compare the same equipment basis.** Record scheduled and proposed equipment separately. Keep an unapproved substitution as an open question, not an accepted savings line.
2. **Separate allowances from complete scope.** If a controls allowance is replaced with a separate controls proposal, show both the allowance removed and the replacement scope added. Check that their boundaries match first.
3. **Use unit prices only within their stated basis.** A rate for additional terminal units should not become a universal controls rate unless the devices, programming, integration and attendance are demonstrably comparable.
4. **Do not deduct an overlap without a priced removal.** An equipment package and insulation quote may both mention insulation, but the tool should ask whether they cover the same physical work before suggesting a deduction.
5. **Keep base scope, alternates and unresolved substitutions separate.** A cheaper equipment alternative does not repair an incomplete base bid.

The insulation check deserves its own rule. [UFGS 23 07 00, August 2024, paragraph 1.2.1](https://legacy.wbdg.org/FFC/DOD/UFGS/UFGS%2023%2007%2000.pdf) assigns field-applied insulation and accessories to that section while factory-applied insulation is specified under the piping, duct or equipment being insulated. Its drawing notes also call for identifying areas of internal duct insulation and special jackets.

Read those provisions together and the cost consequence is sharper than “check insulation.” A proposal saying “insulated equipment included” cannot establish that the field duct, piping and jackets are covered. Conversely, an insulation subcontractor's exclusion of factory work is not necessarily a gap. The tool needs a physical-work boundary, not a keyword match.

Use the same approach for curbs and louvers: distinguish furnishing, setting, supports, flashing, connections and adjacent work according to this project's documents. For the wider ownership decision, link the row to the team's [MEP interface review](https://piper-ai.com/resources/mep-coordination-preconstruction-scope), rather than assigning everything to mechanical by default.

## Make the exclusion library identify questions, not invent prices

An HVAC exclusion library should contain review prompts and their evidence requirements. It should not contain automatic dollar penalties.

For example, a “controls excluded” entry should ask:

- Are factory controls still included with the equipment?
- Who provides field devices, control wiring and device power?
- Who programs and integrates the system?
- Who attends TAB and functional testing?
- Is a separate controls proposal priced on the current equipment and points schedule?

A “TAB excluded” entry should distinguish balancing from duct air leakage testing, prerequisite corrections, technician support and any specified seasonal attendance. [UFGS 23 05 93, May 2025, paragraphs 1.3.1 and 1.3.2](https://legacy.wbdg.org/FFC/DOD/UFGS/UFGS%2023%2005%2093.pdf) requires technical personnel, including factory representatives and controls technicians, to enable the testing work and calls for coordination of their attendance.

Meanwhile, [UFGS 23 08 00, May 2023, Change 1 August 2024, paragraphs 1.3, 1.6 and 2.1.1](https://legacy.wbdg.org/FFC/DOD/UFGS/UFGS%2023%2008%2000.pdf) addresses commissioning access assistance, readiness documentation and proprietary equipment and software for startup and testing. Startup, TAB and commissioning support are not interchangeable obligations in these documents.

**The important interaction:** buying TAB and buying controls does not, by itself, buy the controls technician's attendance for TAB. The installation scope may be covered while the support event remains uncovered. If the issued specification has these requirements, the library should generate an attendance question attached to both rows, not simply mark both packages complete.

Include similar prompts for insulation, power wiring, curbs, louvers, commissioning and permits. Store the bidder's exact wording beside the interpreted effect. The [exclusion and qualification review guide](https://piper-ai.com/resources/review-subcontractor-exclusions-and-qualifications) covers how to resolve that wording; the custom tool should retain the result and its source.

## Show two totals and one unresolved-exposure register

Keep the arithmetic simple and the ownership explicit.

**Bidder contract position = raw bid + agreed additions - agreed deductions.**

**Evaluated package position = bidder contract position + separately carried completion scope + estimator-approved provisional plugs.**

These are proposed estimating definitions for the tool, not contractual formulas. A provisional plug belongs in the GC's evaluated position until its treatment is resolved. It is not an agreed addition to the subcontractor's price.

Every adjustment should identify its scope row, amount, pricing basis, owner, status and whether the cost is already carried elsewhere. Keep unpriced issues in a separate register. A blank price should remain unresolved rather than turn into zero through a formula.

### Illustrative comparison: the higher mechanical quote is the lower complete package

Assume a commercial project with four rooftop units and 24 VAV terminals. These quantities, proposals and dollar amounts are hypothetical. Both equipment offers have been reviewed on the same acceptable basis for this exercise.

- Bid A is **$780,000**, excluding controls, TAB and field insulation.
- Bid B is **$852,000**, including controls and field insulation but excluding TAB.
- A separate controls quote for Bid A's basis is **$58,000**. It excludes TAB attendance.
- TAB is **$14,000** for either option.
- Field insulation for Bid A is **$32,000**.
- For Bid A, the estimator approves an illustrative provisional attendance plug of two mobilizations at $1,800 each, or **$3,600**. Bid B confirms this support is included.

| Illustrative cost component | Bid A basis | Bid B basis |
| --- | --- | --- |
| Mechanical raw bid | $780,000 | $852,000 |
| Separate controls carry | $58,000 | $0; included in mechanical bid |
| Separate TAB carry | $14,000 | $14,000 |
| Separate field insulation carry | $32,000 | $0; included in mechanical bid |
| Provisional controls attendance plug | $3,600 | $0; confirmed included |
| Evaluated HVAC package position | $887,600 | $866,000 |

Bid A starts $72,000 below Bid B. After scope normalization, Bid B's evaluated package is **$21,600 lower**: $887,600 minus $866,000.

The ranking change is arithmetic, not a research finding. The useful decision is the separation of commercial price from package completion. If controls, TAB and insulation stay in separate contracts, Bid A's mechanical contract position remains $780,000. Its evaluated HVAC package position is $887,600. Do not call the latter a revised mechanical quote.

Also do not add the $58,000 controls amount to HVAC and leave the same amount in a separate controls estimate line. Give each cost one carry location and show it in the comparison without duplicating it in the project total.

Competent estimators may disagree about the attendance plug. On a single-turnover project with confirmed support included, the plug should be removed. On a phased project with an unanswered attendance limit, retain an explicit provisional basis or seek a firm price. The deciding evidence is the required test events and quote coverage, not a standard percentage applied to every HVAC bid.

## Ask Piper to build the register on the project's data

Piper's [Bid Leveling workflow](https://piper-ai.com/use-cases/bid-leveling) compares proposals against intended scope, extracts bid terms and surfaces missing or overlapping work with sources. Build with Piper lets teams describe a custom workbook, tracker or register that reads that same project context, including takeoff quantities. It also supports automations triggered by a new bid or addendum.

A spreadsheet maintained on the side can support the same reasoning. The difference is where the source connections and update work are maintained.

| Review concern | Spreadsheet maintained on the side | Tool built on project data in Piper |
| --- | --- | --- |
| Project basis | Team maintains links to drawings, specifications, quantities and quote versions | Built work reads the same project documents, quantities, scopes, bids and decisions |
| Scope comparison | Team structures inclusions, exclusions and source references | Piper's leveling workflow extracts terms and checks proposals against intended scope |
| Change handling | Team reconciles new files and updates affected rows and decisions | Team can request an automation when a bid or addendum arrives |
| Company method | Team distributes and maintains the workbook structure | Working tools can be added to company project templates |
| Carry authority | Estimator reviews the comparison and decides | Estimator reviews the comparison and decides |

The Piper column reflects its [public app-builder description](https://piper-ai.com/use-cases/construction-app-builder), not an independently tested comparison. A connected tool still needs correct ownership rules and estimator review.

### Example plain-language build request

The following is a proposed request, not a description of an already built or tested HVAC app:

> Build an HVAC bid leveling workbook and clarification register for this project. Use the current trade scope, subcontractor proposals and attachments, mechanical and related drawings, specifications, addenda, and takeoff quantities. >Organize equipment and system rows for air distribution, piping and condensate, insulation, controls, TAB, startup and commissioning support. Include power, curbs and louvers as interface checks. Use our issued package boundaries; ask where ownership is unclear. >For each bidder, show raw price, quoted inclusions and exclusions, source references, addenda acknowledgments, equipment basis, alternates, allowances and unit prices. Distinguish included, excluded, not addressed and unresolved wording. Separate the bidder contract position from the evaluated HVAC package position and identify the estimate location of each separately carried cost. >Keep a clarification register with the affected scope row, question, responsible reviewer, response source, status and proposed cost treatment. Do not close an issue merely because a revised total arrives. Leave unsupported prices unresolved and keep provisional plugs separate from agreed quote changes. >When a new or revised HVAC bid arrives, draft an updated comparison and a review list of changed scope, price, exclusions, equipment basis and addenda acknowledgments. Identify earlier adjustments and clarifications that need another look. Do not select a bidder or approve the carry.

Piper asks when a request is unclear. Use that exchange to specify the company's cost locations, treatment of separate contracts and reviewer responsibilities. Do not ask for a generic “HVAC completeness score” when the team needs named unresolved obligations.

## Test revision handling before making it the company template

Review the built result like any other workspace file. Start with a small, manually prepared fixture so the expected decisions are known. This is an acceptance exercise for your requested tool, not evidence of completed product testing.

Return to the illustrative comparison. Bid A submits a revision at **$804,000** that now includes field insulation. Keep controls, TAB and the attendance question unchanged.

The new evaluated position is:

**$804,000 + $58,000 + $14,000 + $3,600 = $879,600.**

The evaluated position drops **$8,000**, even though the raw quote rises $24,000. The $32,000 separate insulation carry is no longer needed on this assumed confirmed scope. If the tool preserves the old insulation adjustment, it produces $911,600 and overstates this comparison by $32,000.

Use that error as a revision test. The reviewer should be able to locate the new inclusion, connect it to the earlier insulation carry, and decide whether the separate cost can actually be removed. A revised price alone is not sufficient evidence.

Then test three harder conditions:

- **New equipment basis:** change a proposed unit while leaving the total unchanged. The review must reopen equipment, controls, power and support assumptions rather than report “no price change.”
- **Partial inclusion:** replace “insulation included” with “factory insulation included.” The field-insulation issue must remain unresolved unless other evidence covers it.
- **Unchanged controls total:** add a project requirement for another test event. The earlier controls quote may remain the same, but its attendance coverage needs review.

Trace several source references back to the actual proposal and issued documents. Check every arithmetic line by hand. Confirm that unanswered questions remain visible and that a separate package carry is counted once in the project estimate.

Once the fixture and a real package review work, add the useful structure and automation to company templates. Retain the row definitions, evidence requirements, normalization rules and review responsibilities. Reset project-specific quantities, prices, substitution statuses and open questions on each new job. The reusable asset is the decision method, not yesterday's plugs.

For the wider build pattern beyond HVAC, see the custom bid leveling tool guide.

## Questions before using the HVAC tool on a live bid

### Should controls be a separate bid column or an HVAC add-back?

Show controls as separately carried completion scope when the GC plans a separate contract. Keep it visible in the evaluated HVAC package position, but count it only once in the project estimate. Use an agreed HVAC addition only when that subcontractor has actually priced and accepted the matching scope.

### Can the tool use takeoff quantities to price missing HVAC work?

Use quantities as one input, not as proof of a complete price. Confirm system, equipment basis, accessories, installation conditions, testing and the rate's coverage before applying it. The example build request asks the tool to leave unsupported prices unresolved instead of inventing a plug.

### Does a controls quote close the TAB support question?

Not by itself. Check whether the controls proposal covers the attendance required by the project's TAB and commissioning documents. Keep installation, programming, integration and testing support as separate review obligations so a complete controls installation quote does not silently close an uncovered support event.

### What should happen when a revised HVAC proposal arrives?

Request an updated comparison and review of earlier adjustments and clarifications against the new proposal. A changed inclusion may retire an old carry; an unchanged price may conceal a changed equipment basis. The estimator must confirm those treatments before accepting the evaluated position or choosing the carry.

### Does building the tool in Piper automate the carry decision?

No. Piper builds and changes the requested artifact, and its leveling workflow supports source-backed comparison and adjustments. The team reviews the result, resolves ambiguous ownership and pricing, and decides the bidder and number to carry. A reusable template does not change that responsibility.
