---
title: 'Build a custom site concrete scope and gap register in Piper'
url: 'https://piper-ai.com/resources/custom-site-concrete-scope-app-piper'
description: 'Build a site concrete register that connects curb profiles, sidewalk thickness, ramps and pole bases to sources, bidder coverage and addendum review in Piper.'
contentTypes: [guide]
publishedAt: '2026-11-30T11:48:46.883Z'
author: 'Ido Gedanken, CEO'
readingTime: 11
---

# Build a custom site concrete scope and gap register in Piper

1. Keep physical requirements, trade assignments and bidder coverage separate.
2. A thickness revision can change the carry without changing sidewalk area.
3. Reopen connected scope decisions after an addendum, not just the revised drawing row.
4. Review the custom tool on a small fixture before adding it to company templates.

A useful site concrete tool should answer three different questions: **What must be built, which package carries it, and does the current bidder actually include it?** Do not collapse those into one “included” field.

For a GC estimator preparing a commercial sitework package at bid-stage CDs or a GMP, the tool should hold curb profiles, sidewalk thickness zones, ramps, pads and their interfaces as source-backed records. Each record needs an assignment, an open-question treatment and a connection to bidder clarifications. Otherwise a clean scope sheet can conceal an unresolved carry.

Piper lets teams describe custom registers and workflows in plain language on the same project data its other workflows read. The team reviews the result like any workspace file. The construction decisions still belong to the estimator. This guide defines what to request and how to test it, not a completed product demonstration. [Build with Piper](https://piper-ai.com/use-cases/construction-app-builder) describes the supported building workflow.

## Define the record before asking Piper to build the tool

Start with a small register, not a dashboard. A dashboard can summarize bad assignments as neatly as good ones.

Use one record for each **location and construction basis** that could produce a different scope decision. “Sidewalks” is too broad if the service crossing has a different thickness from the pedestrian walk. “Curbs” is too broad if the driveway return uses a different section from the parking islands.

The following is a proposed register structure, not a claim about a prebuilt Piper screen:

- **Identity:** item ID, location, element type and package.
- **Construction basis:** curb profile or slab thickness, reinforcing, finish, base, joints and relevant detail references.
- **Evidence:** drawing sheet and detail, specification paragraph, revision or addendum, and the requirement each source establishes.
- **Measurement:** quantity, unit, source and whether the quantity includes ramp runs, landings or pad footprints.
- **Boundary:** proposed furnishing and installing parties, adjacent package, and the physical handoff.
- **Coverage:** bidder, proposal revision, inclusion, exclusion or silence, plus the supporting proposal passage.
- **Decision:** open question, person responsible for resolution, clarification response, approved treatment and estimate reference.
- **Change:** previous basis, current basis, affected records and outstanding review.

Keep requirement status separate from coverage status. A drawing requirement can be confirmed while bidder coverage remains unknown. A trade assignment can be approved while the price is still provisional.

For the language of the issued package itself, use the site concrete scope-of-work guide; this article is about maintaining the relationships behind that language.

### Preserve the bidder's unit without letting it define the work

The current posted [UFGS 32 16 19, Concrete Curbs, Gutters and Sidewalks](https://www.wbdg.org/FFC/DOD/UFGS/UFGS%2032%2016%2019.pdf), dated May 2018, distinguishes sidewalk measurement by depth from curb and gutter measurement by cross section. Its unit-price provisions use square yards or square meters for sidewalks and linear feet or meters for curbs. The guide instructs specifiers to delete those provisions for lump-sum work.

That is a useful model for record design, not a universal payment rule. Your project specification and bid instructions control. A subcontractor may quote sidewalks in SF even when the owner schedule uses SY. Hold both units and document the conversion rather than replacing the original basis.

More importantly, hold thickness and profile independently of quantity. The difference between two sidewalk prices may be a different construction basis, not a different measured area. A register that stores only “4,500 SF included” cannot expose that distinction.

## Build boundary checks from connected sources

The following checks combine official documents into practical estimating rules. They are recommendations for reviewing your project, not substitutes for its edited specifications or designer decisions.

UFGS documents are guide specifications with editable choices. Research for this guide checked the current posted May 2018 sidewalk section, August 2021 exterior-lighting section and November 2026 cast-in-place concrete section. The fetched PDFs reference the October 2026 Unified Master Reference List. Do not overwrite an issued project's older contract edition merely because a newer guide is available.

### Base preparation needs an acceptance boundary, not just a trade name

UFGS 32 16 19 links subgrade preparation to earthwork or aggregate-base sections. Its editing note distinguishes major grading generally handled elsewhere from work that may be assigned within the concrete section. It also addresses maintaining subgrade until concrete placement. [See paragraphs 3.1 through 3.1.3](https://www.wbdg.org/FFC/DOD/UFGS/UFGS%2032%2016%2019.pdf).

Our proposed check is to connect the concrete thickness record to the base and grading records. Record who delivers the prepared surface, the required elevation, who checks it before placement, and who carries any identified rework. “Base by earthwork” does not answer those questions.

Competent estimators may assign fine grading and base installation differently. On a hard-bid package, the deciding issue should be the issued allocation and compatible bidder qualifications. At a negotiated GMP, the team may choose the handoff that best matches the planned construction sequence, then obtain matching scope and price confirmations. In either case, do not treat the proposed assignment as accepted coverage.

### A pole base needs linked electrical and concrete responsibilities

[UFGS 26 56 00, Exterior Lighting, paragraph 2.6.7](https://www.wbdg.org/FFC/DOD/UFGS/UFGS%2026%2056%2000.pdf) places pole-foundation requirements in the electrical section while referring concrete requirements to Section 03 30 00 and underground electrical distribution. The current [UFGS 03 30 00](https://www.wbdg.org/FFC/DOD/UFGS/UFGS%2003%2030%2000.pdf) separately addresses concrete mix design, reinforcing shop drawings, joint-layout plans and field quality control.

Read together, these documents show why the section containing the foundation requirement should not be the tool's sole assignment rule. Specification location and subcontract responsibility are different things.

For each pole-base type, request a linked review of excavation, reinforcing, concrete, anchor bolts, bolt positioning, conduits, grounding and any specified grout. Keep the actual foundation detail attached. If the electrical bidder excludes foundations and the concrete bidder excludes electrical items, a single “pole bases by concrete” note is not adequate closure.

The review should identify a physical handoff: for example, who provides the anchor assembly and conduits before the concrete placement, and who accepts their positioning. That proposed handoff must be confirmed by the affected bidders, not inferred from the division number.

### Detectable warnings need two independent tests

The [Access Board's guide to ramps and curb ramps](https://www.access-board.gov/ada/guides/chapter-4-ramps-and-curb-ramps/) distinguishes detectable-warning requirements under DOT standards from non-transit facilities subject to DOJ standards. The Board's [ADA standards page](https://www.access-board.gov/ada/) identifies DOJ's 2010 standards and DOT's transportation-facility standards separately. Public right-of-way work requires its own applicable-basis review and is outside this private-site example.

Separately, UFGS 32 16 19 contains a detectable-warning system requirement for systems shown on the contract plans. A conclusion about the federal accessibility minimum therefore does not establish whether a panel shown in the bid documents can be removed from the scope.

Build two fields: **applicable requirement basis** and **contract-document requirement**. Then a third question asks who furnishes and installs the panel. If an addendum changes the ramp detail, reopen all three. The estimator should request clarification of a conflict, not let the tool delete the panel because the project was classified as non-transit.

For a broader review of the trade interfaces, see site concrete scope gaps.

## Test the register with an addendum that changes no total area

**Illustrative fixture only:** assume a commercial site package contains 4,500 SF of sidewalk at 4 inches thick. A later addendum changes a 900 SF service crossing to 6 inches while keeping its finished elevation unchanged. For this fixture, the issued detail retains the same 4-inch base thickness. The concrete bidder prices 4-inch work at $9/SF and confirms 6-inch work at $12/SF. These are invented test rates, not market benchmarks.

The old sidewalk carry is:

**4,500 SF × $9/SF = $40,500.**

The revised carry is:

- Remaining 4-inch walk: 3,600 SF × $9/SF = $32,400.
- Revised 6-inch crossing: 900 SF × $12/SF = $10,800.
- Revised sidewalk total: **$43,200**, an increase of **$2,700**.

The total area is still 4,500 SF. A change check based only on area would report no movement.

The theoretical additional concrete volume is **900 SF × (2/12) feet ÷ 27 = 5.56 CY**, before waste or ordering adjustments. That volume is a reasonableness check, not another cost to add to the revised SF price, which already includes the thicker slab in this fixture.

There is a second consequence. Because finished elevation and base thickness remain fixed, the bottom of the slab and the bottom of the base move down 2 inches. The earthwork/base record therefore needs review even though the base material quantity has not increased. Do not call 5.56 CY of additional excavation a payable adjustment without checking the actual contract and bidder coverage.

A good test result is not merely a new $43,200 total. The requested register should help the reviewer find:

1. The source for the changed thickness zone.
2. The quantity split between 4-inch and 6-inch work.
3. The bidder's written confirmation of the revised basis.
4. An open grading/base handoff question.
5. The estimator's disposition of that question and the carry.

If the system updates the sidewalk cost but leaves the prior base acceptance decision looking current, the fixture has failed. If it adds both the $2,700 SF adjustment and a separate concrete-volume allowance for the same change, it has also failed. These are test expectations, not reported Piper results.

## Choose a spreadsheet or a tool on project data deliberately

A spreadsheet can hold source links, revisions, formulas and decisions. The distinction is how the team maintains the connections, not whether a spreadsheet can contain them.

| Review need | Spreadsheet scope sheet | Custom tool on Piper project data |
| --- | --- | --- |
| Construction basis | Team structures thickness and profile fields and maintains links | Team requests source-linked fields using the project data Piper reads |
| Addendum impact | Reviewer locates affected rows and connected decisions | Team can request an automation to review affected scopes when an addendum arrives |
| Bidder clarification | Team maintains quote revision and response references | Requested register can read bids and decisions in the same project context |
| Boundary approval | Estimator confirms assignments and records treatment | Estimator still confirms assignments and reviews proposed treatment |
| Reuse | Copy structure and check for inherited job assumptions | Add tested structure and workflows to company templates |

For a small package with stable documents and one responsible reviewer, a disciplined workbook may be enough. For repeated revisions across civil, electrical and structural sources, the case for a project-connected tool is stronger. Its value is the ability to review connected obligations, not a more elaborate list of curb quantities.

## Give Piper a construction-specific request

[Build with Piper](https://piper-ai.com/use-cases/construction-app-builder) supports plain-language requests for forms, registers, trackers, workbooks and workflow automations. What teams build reads the same project information as Piper: drawings, specifications, revisions, addenda, takeoff quantities, scopes, bids and decisions. The supported workflow does not require exporting and copying that project data into a separate tool.

Use this **example request**, adapted to the issued package and company process:

> Build a site concrete scope and gap register for this project. Organize records by location, curb profile, sidewalk thickness zone, ramp type, pad type and pole-base type. Hold source citations, quantities and units separately from trade assignments and bidder coverage. >Include base preparation, reinforcing, joint filler and sealant, detectable warning panels, testing, pole-base interfaces and the dumpster enclosure. Keep enclosure slabs, walls, footings and gates separate where the documents show different responsibilities. Do not assign a site wall to site concrete solely because it is outside the building. >For each record, show the current requirement, source and revision, proposed furnishing and installing parties, adjacent package, bidder inclusions or exclusions, open questions, clarification responses and estimator treatment. Distinguish silence from confirmed inclusion. Ask me where the request or assignment is unclear. >When an addendum arrives, review the scope items it affects and the connected base, grading and electrical interfaces. Prepare affected records for estimator review with the prior basis, new source, bidder clarification needed and any carry decision that needs another look. Do not treat an addendum acknowledgment as confirmation of revised price or scope.

This describes the tool you want built. It does not establish that every requested check will work correctly on the first attempt. Review and ask Piper to change the result, just as you would revise another working file.

The underlying [Scope Generation workflow](https://piper-ai.com/use-cases/scope-generation) organizes project requirements by trade and surfaces unclear responsibilities for estimator review; the custom register defines how your team wants those requirements, questions and decisions maintained.

## Make the automation reopen review, not approve the carry

Piper's public building workflow includes automations that run when information changes, including reviewing an addendum against affected scopes. One step can hand off to the next. [The product description](https://piper-ai.com/use-cases/construction-app-builder) supports that workflow, not a promise of complete change detection.

For this register, request a sequence of **change, impact review, clarification and disposition**. In the illustrative crossing example, the addendum review should lead to the thickness split and the grading question. The estimator then checks the sources, obtains bidder confirmation and approves the carry treatment.

Review the result like any file in the workspace. Test it against a known small fixture before relying on it during bid week:

- Can the reviewer reach the source behind the changed thickness?
- Does the old quote remain distinguishable from a revised proposal?
- Is a missing foundation assignment visible rather than silently resolved?
- Does the tool distinguish a required panel from confirmed panel coverage?
- Can the reviewer see why an item remains open despite having a price?

The detailed source-to-scope drafting sequence belongs in generating a site concrete scope with AI. Here, the acceptance test is whether the custom tool preserves the decision chain after the scope changes.

## Promote the review structure, not the last project's answers

Piper allows working tools to be added to company templates; built files live in the workspace with the same permissions and history as the rest of Piper. Those are [supported product facts](https://piper-ai.com/use-cases/construction-app-builder). Your template still needs a construction review.

Reuse the record structure, unit conventions, boundary questions and addendum review sequence. Do not reuse a previous job's blanket answer that base is by earthwork, pole bases are by electrical or warning panels are excluded. Require fresh source support and bidder confirmation on the next job.

For the wider reusable structure, see the custom scope-tool guide.

A site concrete register is ready for company reuse when it can keep a requirement confirmed, its ownership unresolved and its price provisional without confusing the three. That is the discipline worth systemizing on shared project data.

## Questions before building the register

### Can we keep our existing spreadsheet scope sheet?

Yes. A spreadsheet can remain a useful working format. Build with Piper supports Excel workbooks as well as registers and trackers. Decide first which relationships need maintaining, then review the requested tool against your company's existing scope structure rather than replacing a format simply to add software.

### Does Piper automatically decide who owns pole bases or base course?

No. Clear requirements can be organized by package, but unclear responsibilities need estimator review. Request separate proposed assignments and confirmed bidder coverage. A foundation requirement in an electrical section, or a base reference in a concrete section, is not by itself proof that a particular bidder included the work.

### What should happen when an addendum changes a ramp detail?

Request review of the affected ramp record and its connected requirements, including thickness, grading, warning panels and bidder clarifications. The automation can prepare work for review; the estimator checks the source and decides the treatment. An acknowledgment of the addendum does not replace confirmation of the revised scope and price.

### When should we add the tool to company templates?

After testing it on a known fixture and correcting its record structure and review behavior. Preserve useful questions and workflows, not project-specific answers. Each new job needs its own source basis, boundary assignments and bidder coverage checked before the team treats the register as a dependable basis for carry.
