---
title: 'Build a custom site utility bid leveling tool in Piper'
url: 'https://piper-ai.com/resources/custom-site-utilities-bid-leveling-app-piper'
description: 'Build a site utility leveling tool that separates depth pricing, connection ownership and restoration costs, then tests revised bids before you choose a carry.'
contentTypes: [guide]
publishedAt: '2026-11-26T10:05:55.478Z'
author: 'Ido Gedanken, CEO'
readingTime: 11
---

# Build a custom site utility bid leveling tool in Piper

1. Keep physical quantities separate from bidder payment quantities.
2. Treat connection ownership and testing as scope, not just price adjustments.
3. Replace resolved plugs rather than stacking them onto revised bids.
4. Automate comparison updates, but leave the carry decision with the estimator.

For a GC estimator leveling storm, sanitary and water proposals on a commercial site package, the custom tool should answer one question: **what changes in the project cost if we carry this bidder on the current scope?** A total beside a total is not enough. The tool needs to distinguish pipe installation from payment quantity, depth surcharges from replacement rates, and a utility-owner connection from contractor work around that connection.

Build those rules before asking for a dashboard. Otherwise, a revised quote can produce a cleaner comparison while leaving an old restoration plug or an unsupported connection assumption in the number.

This guide develops a proposed tool specification, then shows how to request it in Piper. It is not a report of a completed app test. The setup fits subcontractor leveling for a GC-controlled package, including a CMAR estimate approaching GMP. It does not replace the solicitation rules for public prime bids, utility-owner approval, or engineering review. For the underlying process, use the [construction bid leveling guide](https://piper-ai.com/resources/construction-bid-leveling-guide).

## Define the rows around utility reaches, not just pipe sizes

Start with a reach identifier: system, start point, end point and drawing revision. Then attach the pipe size, material, applicable depth basis, surface condition and package owner. A row called “8-inch sanitary” cannot distinguish a shallow run through landscape from a deeper connection beneath existing pavement.

Use these row groups as a starting specification for the tool, not as a universal subcontract scope:

- **Installed systems:** storm, sanitary, domestic water and fire service, separated by reach, size and material. Keep dry utility crossings visible as interfaces unless the package expressly includes dry utility installation.
- **Structures and appurtenances:** manholes, inlets, cleanouts, valves, hydrants, meters, backflow assemblies, restraints and connection fittings where applicable.
- **Trench work:** excavation, bedding, backfill, unsuitable-material replacement, rock, water control and temporary protection.
- **Connection work:** locating or exposing existing services, taps, shutdown coordination, connection labor, utility-owner work and fees.
- **Surface work:** sawcutting, removal, temporary patch, final restoration, base replacement and striping where required.
- **Acceptance and existing systems:** specified testing, inspection, reports, abandonment and temporary service requirements.

There is a reason to keep acceptance separate from “pipe complete.” The current [UFGS water distribution guide](https://www.wbdg.org/FFC/DOD/UFGS/UFGS%2033%2011%2000.pdf), section 3.3.1, addresses field-test labor, equipment, incidentals and wastewater-disposal coordination. The [sanitary sewerage guide](https://www.wbdg.org/FFC/DOD/UFGS/UFGS%2033%2030%2000.pdf), section 3.3, addresses different leakage, deflection and inspection provisions. Those are federal guide specifications requiring project editing, not rules automatically applicable to every commercial site.

The estimating implication is to store the **specific acceptance task and responsible package**, rather than a single “testing included” checkbox. A bidder may have priced one test without carrying another required inspection or report. Do not infer that every test option in a guide applies to the project.

At the building, record the agreed endpoint and both adjoining package owners. UFGS 33 11 00, section 3.2.1.1.1, terminates its water work approximately five feet from the building unless otherwise indicated. That illustrates a document boundary, not a universal trade allocation. Use the [plumbing and site utility boundary review](https://piper-ai.com/resources/plumbing-underground-scope-boundary) when confirming the actual interface.

## Store two quantities when measurement and payment differ

A useful leveling tool should retain both:

1. **Physical takeoff quantity:** what the reviewed drawings show, with its measurement method.
2. **Bidder or contract payment quantity:** what the quoted rate applies to, including any specified measurement convention.

Do not overwrite one with the other to make the bid appear aligned.

The water guide's unit-price provisions measure pipe along centerlines without deductions for valves or fittings, include fittings in the line payment, and pay specified valves and hydrants separately. The [stormwater guide](https://www.wbdg.org/FFC/DOD/UFGS/UFGS%2033%2040%2000.pdf), section 1.1.1, also uses a centerline pipe measurement without deductions for manhole diameter. Its structure provisions distinguish a base depth from additional depth. These provisions matter only if retained in the applicable project documents and payment basis.

Read together, they suggest a tool rule that is less obvious than “check the quantities”: **a fitting or structure can occupy measured line length without being an extra payable pipe-length deduction, while still having a separate cost row.** Do not subtract structure widths from one bid and retain them in another without first reconciling their measurement bases.

For each quoted rate, request these fields:

- Unit and quantity basis.
- Applicable system, size and material.
- Depth definition: cover, invert depth, trench excavation depth or another expressly defined measure.
- Depth band and treatment at its limits.
- Whether the rate replaces the base rate or adds to it.
- Included excavation, bedding, backfill, fittings, testing and restoration.
- Whether quantity changes affect payment or are merely the bidder's estimating breakdown.

A lump-sum quote with a quantity schedule is not automatically a remeasurement contract. Ask what the schedule controls before calculating a quantity adjustment. The tool should show an unresolved commercial basis rather than turn every takeoff difference into an add-back.

## Test the logic with a carry that actually changes

**Illustrative example only.** The following quantities, rates and prices are synthetic acceptance-test inputs, not market rates or customer results.

Assume a commercial package with 600 LF of sanitary pipe and four manholes. The reviewed profile allocates 420 LF to the agreed shallow band and 180 LF to the deep band. For this exercise, both bidders accept the same endpoints and measurement convention.

Bidder A's raw proposal is $148,000. Its stated basis carries all 600 LF at $100/LF and includes four manholes. It quotes **an additional** $40/LF for the deep band, excludes final paving restoration and excludes required CCTV inspection. The remaining base covers other confirmed work in the package.

Bidder B quotes $162,000 lump sum and confirms the current depths, final restoration and required CCTV. Other scope is assumed equal solely for this example.

The GC has a separate paving quote of $8,400 for the affected restoration and an inspection quote of $2,100. The provisional comparison is:

| Cost component | Bidder A | Bidder B |
| --- | --- | --- |
| Raw proposal | $148,000 | $162,000 |
| Deep-band adjustment: 180 LF × $40/LF | $7,200 | Included |
| Final restoration outside utility subcontract | $8,400 | Included |
| Required CCTV outside utility subcontract | $2,100 | Included |
| Comparable project cost | $165,700 | $162,000 |

A's adjusted utility subcontract position is $155,200: $148,000 + $7,200. Its comparable **project cost** is $165,700 after adding the separately procured restoration and inspection. B is $3,700 lower on this defined basis. The tool must show both positions so the GC does not accidentally put the paving price into the utility award and also carry it in the paving package.

Now test a change in rate wording. If A's $140/LF deep rate is a **replacement** for the included $100/LF shallow rate, the adjustment is 180 × ($140 − $100) = $7,200. Adding 180 × $140 would incorrectly add $25,200 and overstate the comparison by $18,000.

Finally, test a revised proposal. A issues a $159,000 revision confirming deep-band work and CCTV, but still excluding final paving. The new comparable project cost is $159,000 + $8,400 = $167,400. The old $7,200 and $2,100 adjustments must be retired, not stacked onto the revision. Stacking them would show $176,700, an overstatement of $9,300.

The arithmetic is simple. The useful test is whether the tool distinguishes **embedded scope, replacement adjustments and costs owned by another package**, then changes those treatments when the evidence changes.

## Build an exclusion library that asks for ownership

Use the library as a set of review questions, not a list of mandatory plugs. Preserve the bidder's actual wording beside the interpreted issue. For a more general review method, see [subcontractor exclusions and qualifications](https://piper-ai.com/resources/review-subcontractor-exclusions-and-qualifications).

For this utility tool, specify the following checks:

- **Fees and taps:** Separate utility-owner charges, owner-performed connection work and contractor preparation. Ask who excavates, provides fittings, coordinates shutdowns and restores the surface. “Tap by utility” should not close those other rows.
- **Rock:** Record the definition, measurement limits and whether the rate is standalone or incremental. Check what replacement backfill is included.
- **Dewatering:** Separate a priced water-control method from an assumption that the trench stays dry. Assign review of duration, operating attendance and discharge requirements where applicable.
- **Paving patch:** Distinguish temporary reinstatement from final restoration and identify the estimate package carrying each.
- **Testing or televising:** Name the required method, reach, report and responsible party. Treat ambiguous “testing by others” language as an open ownership question.
- **Abandonment:** Identify the existing line, limits, isolation, removal or filling requirements, and any temporary service obligation actually shown in the documents.

Two source interactions deserve dedicated checks.

First, the stormwater guide's section 1.1 notes say rock unit prices should be independent of common excavation unless otherwise specified, and section 1.1.7 includes replacement backfill in the rock price. A separate rock quote and a separate imported-backfill quote can therefore overlap if the project adopted that basis. Ask for the payment inclusion map before adding both. Neither “rock excluded” nor “backfill included” settles it alone.

Second, [OSHA 1926.651(b)](https://www.osha.gov/laws-regs/regulations/standardnumber/1926/1926.651) requires locating underground installations and determining their exact location by safe means as excavation approaches. Paragraph (h) addresses protection against water accumulation and competent-person monitoring when water-removal equipment is used. Combine those requirements with the actual utility connection and inspection sequence when reviewing a bidder's work plan.

For example, if the project retains the sanitary guide's post-connection inspection before burial, a delayed inspection may leave an excavation open longer than the bidder's assumed installation cycle. That can change the duration of protection and water-control work even though pipe length is unchanged. This is an estimating review question, not a finding about a real bid. Ask what the quote carries for that interval rather than inventing a per-foot allowance.

## Give every plug a replacement condition

In the proposed register, each adjustment should contain an issue identifier, affected reach, project requirement, proposal wording, cost owner, amount basis, reviewer treatment and replacement condition.

Use distinct treatments for confirmed scope adjustments, provisional plugs, costs carried elsewhere and unresolved items. An unpriced issue should say “unpriced,” not appear as zero. Keep unresolved exposure beside the comparable total so a numeric rank does not imply complete coverage.

A clarification record should connect the question to the source, bidder, affected row and response. It should also record who accepted the treatment and whether the answer changes price, scope or both. A reply confirming CCTV coverage should retire the CCTV plug only for the stated reach and proposal revision.

Competent estimators may disagree about where restoration belongs. On a site with several utility trenches feeding one final paving operation, the chief estimator may prefer a single paving carry. Another GC may buy complete restoration within each utility package. **Choose the ownership that matches the intended buyout and sequencing, then compare all bidders on that basis.** Do not use the tool to pretend there is one correct trade allocation for every project.

Revision handling should preserve the previous comparison as evidence while presenting the current treatment clearly. A changed profile can move length between depth bands without changing total LF; a price-only revision can change the raw bid without resolving exclusions. For the wider dependency review, use [drawing revisions and their effect on scope, bids and estimates](https://piper-ai.com/resources/drawing-revisions-cascade-scope-bids-estimate).

## Decide whether the tool needs to live with the project

A spreadsheet can hold source links, formulas, history and clarification records. The decision is not whether a workbook can do the arithmetic. It is who maintains the connection between each value and the changing project basis.

| Review task | Spreadsheet maintained on the side | Requested tool on project data |
| --- | --- | --- |
| Quantity basis | Reviewer transfers quantities and maintains revision references | Reads project takeoff quantities; reviewer checks applicability |
| Scope evidence | Reviewer maintains links between rows and source documents | Starts from the same drawings, specs, scopes and bids |
| Revised proposal | Reviewer replaces totals and revisits affected adjustments | Requested automation prepares an updated comparison for review |
| Company checks | Workbook rules must be maintained and applied to each package | Working tool can be added to company project templates |
| Carry authority | Estimator chooses and records the carry | Estimator chooses and records the carry |

The project-data column describes the supported building model and the workflow requested here, not a completed demonstration of this particular utility app. Piper's [Build with Piper description](https://piper-ai.com/use-cases/construction-app-builder) states that tools read the same project information as its other workflows and that automations can run when information changes. Validate the requested rules before relying on the resulting file.

## Request, test and reuse the utility workflow in Piper

Piper's [Bid Leveling workflow](https://piper-ai.com/use-cases/bid-leveling) compares proposals against intended scope, extracts exclusions and pricing terms, and surfaces source-backed differences. The custom tool should extend that work with your utility-specific normalization and ownership rules, not create a separate interpretation of the job.

With [Build with Piper](https://piper-ai.com/use-cases/construction-app-builder), teams describe what they need in plain language, Piper builds and changes it, and the team reviews the result like any other workspace file. Supported outputs include trackers, registers, workbooks and workflow automations. Start with a request such as this:

> Build a site utility bid comparison and clarification register for this project using our leveling structure. Read the current subcontractor proposals, issued utility scope, civil plans and profiles, applicable specifications, addenda and reviewed takeoff quantities. Separate storm, sanitary, domestic water and fire service by reach. Show physical and quoted payment quantities, endpoints, depth definitions and whether rates replace or supplement the base. Preserve proposal exclusions beside their sources. Show raw bid, reviewed adjustments, separately carried package costs, unresolved issues and comparable project cost. Give every plug a replacement condition. Ask where measurement, ownership or rate wording is unclear. Do not select or approve the carry.

Then request an automation:

> When a new or revised utility proposal arrives, prepare an updated comparison against the current project scope. Identify changes in price, quantities, exclusions, depth assumptions and addenda acknowledgments. Revisit affected clarifications and provisional adjustments, showing proposed replacements for estimator review. Retain the prior proposal and decision basis in the workspace history. Leave unresolved issues visible and do not approve the carry.

These are example requests, not guaranteed out-of-the-box fields or interface labels. Piper can run automations when a sub bid or addendum arrives, and one step can hand off to the next. The specific behavior must still pass your review.

Use the synthetic example above as an acceptance fixture. Confirm the $165,700 comparison, the $18,000 replacement-rate error check and the $9,300 stale-adjustment check. Also test a blank depth definition, a duplicate revision and a restoration cost already assigned to paving. Reject an output that resolves ambiguity by silently choosing a rate or scope owner.

After the team verifies the behavior, add what works to company templates. Keep calculation rules and review questions reusable; keep project rates, utility-owner terms and endpoints project-specific. The built work lives in the workspace with its permissions and history. For the broader pattern, see building a custom bid leveling tool.

The goal is a comparison whose reasoning changes when the project changes. Piper drafts and checks that work. The estimator still decides which bidder, adjustments and unresolved exposure belong in the carry.

### Should the tool use the GC takeoff quantity or the subcontractor quantity?

Retain both until their measurement and commercial bases are reconciled. Use the reviewed GC quantity for a defined comparison exercise, but do not treat a lump-sum bidder's quantity breakdown as an automatic payment adjustment. Show the discrepancy and request clarification where the quote basis is unclear.

### Should every utility exclusion receive a plug?

No. First determine whether the work is required, who owns it and where it is already carried. Then price an uncovered obligation or identify it as unresolved. A final paving cost owned by another package belongs in the project-cost comparison without also inflating the utility subcontract award.

### Can Piper automatically choose the utility subcontractor?

No. Piper can structure proposals, check them against project scope, surface differences and support adjustments, but the consequential assumptions and final carry remain estimator decisions. An automation should prepare the changed comparison and open questions for review, not approve the award or carry.

### What should happen when a revised quote includes work previously plugged?

Replace the old treatment after confirming the revised scope and price basis. Do not add the old plug to a price that now includes the same work. Keep the previous proposal, clarification and adjustment reasoning available so the reviewer can explain why the current comparison changed.

A revised utility bid may depend on a phone or text clarification that explains why an old plug should be replaced. The guide to [preconstruction software with phone and SMS workflows](https://piper-ai.com/resources/best-preconstruction-phone-sms-workflow-software) compares communication records with estimating workflows, including how Piper connects clarifications to source-backed scope, bid leveling and final review before the estimator accepts the carry.
