# Build a custom structural steel scope and gap register in Piper

1. Track the obligation, trade assignment and pricing treatment separately.
2. Connection design needs a connection-family basis, not one yes-or-no field.
3. An embed handoff is not complete until setting, survey and release responsibilities are assigned.
4. An addendum should reopen affected decisions for review, not silently approve a new scope.

For a GC estimator preparing a structural steel package on a commercial hard-bid project, build the register around **decisions that can become stale**, not just a list of included steel. A row should connect a project requirement to its source, the parties responsible for each part of the work, the bidder's response and the current pricing treatment.

Piper lets teams describe a custom register in plain language and review the result like any other workspace file. What they build reads the same drawings, specifications, addenda, scopes, bids and decisions as the rest of Piper. That is the useful distinction: a steel scope tool can work from the project behind the scope sheet rather than another manually maintained copy. These are [Build with Piper capabilities](https://piper-ai.com/use-cases/construction-app-builder), not a claim that a particular steel register has already been built or tested.

The estimator still decides the assignments and carry. Start by defining what the tool must keep unresolved.

## Hold three separate answers for every steel obligation

A single status such as “included” is too weak for this proposed register. It can mean the work appears in the documents, the GC assigned it to a package, or a bidder actually priced it. Those are different answers.

Use three separate records:

1. **Requirement basis:** what work is required, where it appears and which revision supports it.
2. **Scope assignment:** who furnishes, designs, details, delivers, installs, verifies or releases the work, as applicable.
3. **Pricing treatment:** what the bidder confirmed, what remains qualified and what the estimate carries pending resolution.

For example, “anchor rods included” should not close an embed item. In the proposed register, it answers only the furnishing question unless the proposal says more. Setting, surveying and handling discrepancies need their own treatment.

This guide concerns the structure and review of a custom tool. Use the structural steel scope-of-work guide for the package language itself. On CMAR work with incomplete design, retain provisional assignments and assumptions instead of making the register appear buyout-ready.

### The minimum information worth storing

Ask for these fields in the register design. They are proposed content requirements, not existing Piper interface labels:

- Stable item identifier and affected location, grid, level or connection family.
- Requirement text with drawing detail, specification paragraph and revision references.
- Basis classification: explicit project requirement, applicable standard practice, company check or estimator assumption.
- Furnish, design/detail, install and verify responsibilities, where relevant.
- Adjacent package and the handoff that must occur between packages.
- Open question, assigned reviewer and requested response date.
- Bidder inclusion, exclusion or qualification, linked to the proposal or clarification.
- Current carry treatment and its basis, separate from the bidder's raw price.
- Addendum impact, previous decision and whether review is required again.
- Reviewer disposition and the evidence that supports closure.

Do not use an official standard as evidence that a bidder accepted a commercial assignment. Likewise, do not use a bidder's acknowledgment as evidence that the design information is complete.

## Make connection design a family-level decision

AISC's current standards page identifies ANSI/AISC 303-22 as the Code of Standard Practice. AISC explains that its trade practices apply unless the contract documents contain specific provisions to the contrary. Its errata index lists January 2025 and September 2026 corrections. Record the project's applicable edition and corrections rather than assuming the latest publication governs every contract. See [AISC's current-standard page](https://www.aisc.org/aisc/publications/current-standards/aisc-303) and [errata index](https://www.aisc.org/aisc/publications/revisions-and-errata).

AISC's 2025 [Requirements for Connections guidance](https://www.aisc.org/media/dw0hzmt5/gc_toolboxtalk3_2025.pdf), reproducing Section 3.2.3 of AISC 303-22, distinguishes three options: complete connection design in the structural documents, selection or completion by an experienced detailer, and design by a licensed engineer working for the fabricator. Different connection types can use different options. For the latter two options, the design representative must supply connection criteria, including sufficient load information and the design method.

**Register consequence:** “connection design included” cannot establish coverage for every connection. Ask the tool to organize the review by family, such as beam shear connections, bracing connections and moment connections, using the project's actual classifications.

For each family, connect:

- The stated design-responsibility option.
- The drawing and specification criteria supporting that option.
- Any missing or conflicting inputs requiring a design-team response.
- The bidder's stated design and detailing coverage.
- The required substantiating information and review path.

Here is a specific failure worth testing. A synthetic proposal includes detailing but excludes engineering. The general notes require fabricator-engineered brace connections, while typical shear connections are selected from specified reference information. A package-level “detailing included” check would hide the brace engineering gap. A family-level check leaves that item open and asks the bidder for its engineering coverage and price.

The important consequence is not just an engineering fee. AISC's guidance says the licensed engineer's review under Option 3 does not replace the design representative's approval process. The register therefore needs separate evidence for the bidder's design scope and the required review path. Paying for the former does not establish completion of the latter.

The custom tool should surface these questions. It should not select a connection option, design a connection or provide licensed approval.

## Treat embeds as a handoff with a release condition

AISC's 2025 [anchor-rod and embedded-item guidance](https://www.aisc.org/media/2yaj55d0/gc_toolboxtalk10_2025.pdf) reproduces Section 7.5 of AISC 303-22. It assigns setting to the owner's designated representative for construction using approved embedment drawings. It also assigns that representative an as-built survey and verification against the applicable tolerances; necessary corrective action requires the design representative's guidance and approval. Check the actual contract for any different provisions.

For U.S. work subject to OSHA's steel erection requirements, [29 CFR 1926.755(b)](https://www.osha.gov/laws-regs/regulations/standardnumber/1926/1926.755) prohibits anchor-rod repair, replacement or field modification without the project structural engineer of record's approval. It also requires the controlling contractor to notify the erector in writing of such changes before column erection. [29 CFR 1926.752](https://www.osha.gov/laws-regs/regulations/standardnumber/1926/1926.752) separately addresses written notifications before erection, including the required concrete-strength basis.

Read together, these provisions suggest a better closure rule for a GC's register:

**Close pricing coverage separately from erection release.** A confirmed setting price does not prove that the survey is complete, a discrepancy has approved treatment or the required notifications have been delivered.

In the proposed tool, an embed group should connect furnishing, approved setting information, installation, survey and discrepancy treatment. Record the responsible party for each. At bid stage, record the obligations and price coverage, not fictional completion dates. Later, actual survey and approval records can support the handoff.

A useful acceptance test is a synthetic anchor-rod discrepancy. Supply an as-built survey reference and an unresolved correction question. The register should retain the question and responsible reviewer. It should not change the item to “released” because someone added a repair allowance.

That distinction gives the precon manager a way to see whether the number contains money for a problem while the operational decision remains unresolved.

## Separate the crane from the ground it needs

For U.S. steel erection covered by the cited OSHA rule, Section 1926.752(c) places adequate site access and a firm, properly graded, drained equipment and storage area with the controlling contractor. Section 1926.752(d) requires overhead hoisting operations to be preplanned. Those requirements do not establish whether a subcontractor's quoted erection price includes crane rental. Read the [current OSHA provision](https://www.osha.gov/laws-regs/regulations/standardnumber/1926/1926.752) alongside the proposal and site logistics basis.

**Register consequence:** do not combine “crane included” and “erection access covered” into one closed row. Give the crane service and the supporting site conditions separate assignments, connected to the same erection operation.

Competent estimators can reasonably differ on whether one erector should furnish hoisting for steel, joists and deck or whether separate packages should carry separate equipment. Decide from the actual erection sequence, subcontract boundaries and access conditions. Do not settle it with a company default that ignores the job.

Also request explicit reviews for deck and joists, miscellaneous metals, grout, fireproofing and coating touch-up wherever they appear in the project. Treat these as project-specific boundary questions, not universal exclusions from the steel package. The structural steel scope-gap guide addresses the underlying interfaces.

## Test the register with a number that moves

The following is an **illustrative fixture**, manually prepared to test the proposed register. All prices and quantities are invented for the exercise, not market benchmarks or Piper-generated results.

Assume a steel proposal is $620,000. It includes fabrication, delivery and erection, but excludes connection engineering and anchor-rod setting and survey. A separate deck package is already carried elsewhere.

The estimator prepares these illustrative treatments:

- Connection engineering allowance: $7,500.
- Anchor-rod setting: 24 groups × $180 per group = $4,320.
- As-built survey allowance: $2,000.
- Erection working-area preparation in general requirements: $9,000.

The steel-related exposure is therefore $620,000 + $7,500 + $4,320 + $2,000 + $9,000 = **$642,820**. This is a review total across packages, not a proposed steel subcontract value. The $9,000 remains in general requirements; the register must show its location rather than add it to steel and leave it in general requirements too.

Now introduce a synthetic addendum with four additional anchor-rod groups and revised criteria for a brace-connection family. The bidder's illustrative clarification confirms crane service within its base erection price and replaces the engineering exclusion with a firm $11,000 add price.

The revised review total is:

$620,000 + $11,000 + (28 × $180) + $2,000 + $9,000 = **$647,040**.

The movement is **$4,220**: $3,500 replacing the old engineering allowance, plus $720 for four additional setting groups. The crane clarification causes no price movement in this fixture. It also does not remove the separately assigned working-area preparation.

Use the exercise to inspect three things:

1. Did the engineering allowance get replaced, rather than retained beside the firm add price?
2. Did the changed embed quantity reopen the setting item and its pricing basis?
3. Did the crane response close only crane coverage, leaving site preparation in its assigned package?

Keep the survey allowance unchanged only as an explicit exercise assumption. On a real job, ask whether the revised quantity or mobilization changes that price. The math proves the fixture's reconciliation; it does not prove the real scope is complete.

## Choose the tool by how it maintains the basis

A spreadsheet can hold source links, responsibilities, revision history and pricing adjustments. The decision is whether your team will maintain those relationships manually or build a tool that reads the shared project context. Piper's public [app-builder description](https://piper-ai.com/use-cases/construction-app-builder) supports the latter capability, not an independent performance comparison.

| Review need | Spreadsheet scope sheet | Custom tool on Piper project data |
| --- | --- | --- |
| Source basis | Team enters and maintains drawing and specification references | Built work reads the project's drawings, specifications and addenda |
| Boundary assignments | Team maintains separate responsibilities and linked package references | Request separate assignments and uncertain boundaries for review |
| Revised documents | Team identifies affected rows and reconciles their treatment | Request an automation to review an addendum against affected scopes |
| Bidder response | Team connects the clarification to the row and pricing decision | Built work can read bids and decisions in the shared project context |
| Closure | Team controls status and carries unresolved items | Team reviews the result and decides assignment, treatment and closure |
| Reuse | Team copies and checks the workbook for the next project | Add a tested tool to company project templates |

A one-package job with a stable document set may need only a carefully maintained sheet. The custom tool earns its place when changes must be checked against multiple related decisions without creating another isolated document basis.

## Describe the register in plain language

Use this as an example request for [Build with Piper](https://piper-ai.com/use-cases/construction-app-builder). It specifies desired behavior to build and verify, not a description of a preconfigured steel app:

> Build a structural steel scope and gap register for this project using our scope structure. Read the current drawings, specifications, addenda, steel scope, related packages, subcontractor proposals and clarification records. Give each obligation a source reference and separate fields for requirement basis, responsibility and pricing treatment. Separate connection families and their stated design responsibilities. For embeds, separate furnishing, setting, survey and discrepancy treatment. Keep crane service separate from working-area preparation. Show open questions, affected packages, bidder qualifications and the estimator's carry basis. When an addendum arrives, review affected scope items and present changed sources and decisions needing review. Preserve unresolved questions rather than assuming coverage. Ask where this request is unclear.

Piper's approved building workflow lets teams describe and change tools without coding. Registers and change-triggered workflow automations are supported categories; built work uses the same project information, permissions and history as the workspace. Numbers link to their source pages. Your team reviews the result like any other workspace file.

[Scope Generation](https://piper-ai.com/use-cases/scope-generation) can organize requirements by trade, link scope items to sources and surface uncertain boundaries. The custom register should extend that reviewed scope into the company's chosen decision record, not silently convert uncertain assignments into accepted commitments.

For the underlying drafting sequence, use how to generate a structural steel scope with AI. For the reusable tool framework, see building a custom scope tool in Piper.

## Review the addendum behavior before making it a template

Piper supports automations that run when information changes, including reviewing an addendum against the scopes it affects. For this tool, specify that the event initiates **review**, not automatic acceptance of new commercial scope.

Run the synthetic fixture before reuse. Check that the proposed workflow presents the revised connection criteria, changed embed groups and affected pricing treatments. Inspect the source references yourself. Then check the non-events: unchanged deck coverage should not become a new steel add, and confirmed crane service should not erase the site preparation obligation.

Ask Piper to change the tool if its classifications obscure those distinctions. Only after the team verifies the result should it add the tool to company templates. Reuse the fields, review logic and standard questions. Do not reuse the last project's connection-design option, embed assignment or crane arrangement as settled answers.

The deliverable is not a dashboard with fewer red rows. It is a register in which every material closure has a source, an assignment, a pricing treatment and a human decision that can be challenged when the project changes.

### Does this require coding or an API?

No. Piper's building workflow uses plain-language requests, and the team reviews the result like another workspace file. Piper has no public API. Define the register's fields and review behavior, then inspect the built result rather than specifying endpoints or inventing interface steps.

### Can an addendum automatically close a steel scope gap?

The workflow proposed here should not close a consequential gap without review. Piper supports change-triggered automations, but a changed requirement may need a revised bidder response, trade assignment or carry treatment. An affected item being reviewed is not the same as its commercial coverage being accepted.

### Should connection design be one inclusion field?

No, not for this register. AISC's guidance permits different responsibility options for different connection types. Organize the review by the project's connection families, then connect the specified option, required inputs and bidder coverage. A broad detailing inclusion does not resolve an explicit engineering exclusion.

### What should become a company template?

The tested register structure, review questions and change-review workflow should become the template. Project-specific answers should not. Keep responsibilities for embeds, deck, hoisting and connection design open until the next project's documents and proposals support them, even when the last project used a familiar arrangement.