# Daisy Field: separate field drainage from riparian restoration

Carry the field drainage response separately from riparian restoration. The November 2025 briefing describes green infrastructure intended to address infield washout, while woodland and riparian restoration and permanent restrooms were outside the then-current scope.

The following register is an estimator's interpretation of the cited public records, not a contract scope or a substitute for the current procurement documents.

## Define field, drainage and excluded restoration limits

| Work or location | Public record | Estimator's review |
| --- | --- | --- |
| Fields | Two hybrid softball and little-league fields with skinned infields | Confirm grading, surfacing and field equipment in the issued set. |
| Stormwater | Green infrastructure intended to address infield washout | Define collection, overflow, outfall and restoration interfaces. |
| Pond edge and woodland | Restoration excluded from existing scope | Identify temporary protection and any separate package. |
| Parking | Renovation TBD because of a funding gap | Price separately until procurement documents establish inclusion. |
| Restrooms | Space and pad for two portable units; permanent facilities excluded | Confirm pad, service access and unit responsibility. |

## Treat washout reduction as an intended result

The owner said existing permit-holder logistics required both fields to remain hybrid. That affects the review of skinned infields and transitions, but the meeting record is not a final field specification.

The briefing reported no formal comprehensive study of water quality or erosion impacts. The stated green infrastructure benefits are project intentions, not measured reductions. Keep a distinction between controlling sediment during the work and the permanent system’s designed performance.

The primary records are [Improvements to Daisy Field (Olmsted Park) official City project page](https://www.boston.gov/departments/parks-and-recreation/project/improvements-daisy-field-olmsted-park) [Daisy Field Community Briefing Notes (November 5, 2025)](https://www.boston.gov/sites/default/files/file/2025/12/Daisy%20Field%20Community%20Briefing%2011.05.2025_Meeting%20Notes%20%281%29.pdf).

## Reconcile drainage, parking alternatives and portable facilities

Ask for drainage calculations, utility and pond-edge limits, temporary erosion controls, parking alternates and issued specifications. Separate field work from any restoration proposed by others, and reconcile the portable-restroom pad with access and maintenance. A historical 2027 expectation is not a current contract schedule.

Before relying on a public presentation, trace the official Boston project record and [check the controlling issued revision](https://piper-ai.com/resources/construction-addenda-management-for-gc-estimators).