# Leveling design-build and delegated-design subcontractor bids

1. Compare the promised performance and design boundary before adjusting price.
2. An engineering fee does not establish who pays for the resulting construction.
3. Keep missing criteria separate from missing priced scope.
4. Trace each proposed solution through the adjoining trades and acceptance work.

A design-build subcontractor's low bid is not comparable until you know what design it promises to complete, which inputs it relies on, and what happens when that design changes the installation. For GC estimators pricing commercial MEP, fire protection or curtain wall packages at schematic design or DD, the first leveling task is to establish a common performance commitment, not a common equipment list.

**An engineering fee is not the same as carrying the construction that engineering produces.** A proposal can include calculations and sealed drawings while reserving every resulting change in pipe size, equipment capacity or anchorage for later pricing.

Level these packages in two passes: establish whether each offer answers the same requirements, then compare the cost of delivering and demonstrating that performance. Do not turn an undefined design obligation into a confident plug. The [construction bid leveling guide](https://piper-ai.com/resources/construction-bid-leveling-guide) covers the underlying process; this guide addresses the design commitments behind the number.

## Identify the design boundary, not just the delivery label

Delegated design and design-build are not interchangeable contract descriptions. AIA's [2025 Design-Build Guide](https://learn.aiacontracts.com/wp-content/uploads/2025/07/DesignBuildGuide_V4.pdf), explaining its 2024 document family, describes design-build as an owner contracting with one design-builder for design and construction. It also identifies A441-2024 as the design-builder/subcontractor agreement that accommodates subcontractor professional services.

For delegated portions of work under A201-2017, AIA's [publisher explanation](https://learn.aiacontracts.com/articles/delegated-design-what-does-it-really-mean) describes performance and design criteria supplied by the owner and architect, design services provided through an appropriately licensed professional, and limited architect review of the delegated submittals. Those provisions are contract-specific, not a rule to impose on every design-build subcontract.

The estimating consequence is straightforward: do not assume the phrase *design-build included* transfers every missing criterion, engineering task and downstream cost to the bidder. Read the actual subcontract requirements and proposed qualifications together. Have counsel and the responsible design professionals resolve contractual or professional responsibility questions.

Use three boundaries in the review:

- **Criteria boundary:** Who establishes the required capacity, loads, environmental conditions, redundancy and acceptance criteria?
- **Design boundary:** Who develops the solution, signs the applicable documents, coordinates it and responds to review comments?
- **Cost boundary:** Who carries construction changes needed to deliver that solution within the agreed criteria?

These boundaries can differ. The mechanical subcontractor might design duct distribution while the design-builder's engineer establishes loads and outdoor-air requirements. A curtain wall engineer might design anchors while the structural engineer establishes supporting-structure movement. Record the actual arrangement rather than assigning all three boundaries to the party carrying an engineering fee.

This guide does not apply as a substitute for legal review, engineering verification or determination of the locally adopted code. On a fully designed installation-only package, keep the design review focused on any expressly delegated elements rather than inventing a broader design obligation.

## Make a design-basis register before the bid tab

Prepare a short register that joins each requirement to the input and deliverable that make it priceable. This is an estimating recommendation, not a prescribed contract form.

For each row, retain the project source and revision, bidder's stated assumption, design owner, construction owner, acceptance evidence, clarification and price treatment. Use these starter rows:

| Package | Criteria or input to reconcile | Deliverable and cost boundary to confirm |
| --- | --- | --- |
| HVAC | Loads, outdoor-air basis, operating modes and equipment duty | Calculations and selections; controls interfaces; testing support and capacity verification |
| Fire protection | Hazard and storage basis, protected areas, waterflow data and calculation endpoint | Hydraulic design; supply verification; underground boundary; treatment of inadequate supply |
| Curtain wall | Loads, supporting-structure movement, geometry and assembly performance | System and anchor design; adjacent-work coordination; mockup and project acceptance testing |

Do not mark a row complete because a proposal says *per plans and specifications*. Ask whether its explicit assumptions conflict with the cited requirement. Silence is an open item, not an inclusion you have verified.

Classify the discrepancy before pricing it:

1. **Known requirement omitted:** Obtain a firm addback or carry a documented estimating adjustment.
2. **Input missing or contradictory:** Seek design clarification and price a stated scenario, not an invented final design.
3. **Different solution to the same requirement:** Check technical acceptability and the complete installed consequence.
4. **Different allocation of responsibility:** Obtain a revised commitment or identify the work the GC retains.

This sequence prevents a familiar failure: adding a design fee to make the spreadsheet look comparable while leaving the actual performance promise unequal. For a defined omission, follow the separate plug-number treatment; for an undefined input, retain the uncertainty in the register.

## Fire protection: compare the water-supply basis before the head count

The current public [UFGS 21 13 13 wet-pipe sprinkler guide](https://www.wbdg.org/FFC/DOD/UFGS/UFGS%2021%2013%2013.pdf) is dated August 2020, with references coordinated to October 2026. Its performance-design notes call for waterflow information, supply-to-riser piping information and explicit design criteria. Paragraph 1.2.1.1 calls for a hydrant flow test before shop-drawing submission while specifying the stated flow-test basis for calculations unless a different basis is approved. Paragraph 1.2.1.2 also addresses backflow-preventer loss and calculations back to the actual flow-test location.

UFGS is an editable federal guide specification, not a universal commercial-project requirement. Use the project's issued section and adopted standards. The useful interaction is between the **test basis** and the **calculation boundary**: two bidders can use identical sprinkler criteria yet price different supply conditions.

Consider an illustrative warehouse proposal review. Bidder A includes hydraulic calculations but assumes the stated supply is adequate at the riser. Bidder B includes supply verification and calculates back through the service and backflow assembly. Before treating B's higher price as conservatism, establish where A's calculation begins and who carries a supply deficiency.

The failure is not necessarily a missing pump. It is an unpriced decision chain. Changed waterflow information could require the designer to reconsider the solution, which could affect underground piping, a pump arrangement and associated electrical work. The estimator should not size those changes or declare a pump necessary.

Send one connected clarification:

> Identify the waterflow record and calculation endpoint used in your price. Confirm treatment of service-pipe and backflow losses, responsibility for required verification, and whether construction changes needed to meet the stated criteria are included or separately priced.

Then connect the answer to the site-utility and electrical packages. A sprinkler addback alone does not close exposure in those adjoining trades. If the supply basis remains unresolved, compare bounded scenarios with the design team rather than assigning one speculative equipment plug to the sprinkler bid.

## MEP: separate design development from performance demonstration

For an early-design office package, ask what the HVAC bid must prove after installation, not only what equipment it proposes to buy.

The [May 2025 UFGS 23 05 93 TAB guide](https://www.wbdg.org/FFC/DOD/UFGS/UFGS%2023%2005%2093.pdf), with October 2026 coordinated references, connects several requirements that deserve one review. Paragraph 1.9 addresses design review for test devices and required design values. Paragraphs 1.3.1 and 1.3.2 require technical support personnel and coordination for testing. Its tailoring notes distinguish proportional balancing and thermal performance work, including seasonal testing where selected.

Again, apply the issued project section, not every option in the guide. The estimating lesson is that **including TAB does not, by itself, establish coverage for the work that makes TAB possible or proves capacity**.

An illustrative bidder might include one balancing visit, exclude controls attendance, and assume all test ports are provided by others. Another might include those interfaces and the specified seasonal return. These are different completion commitments even if both equipment schedules match.

Follow the acceptance chain in reverse:

- What report or demonstrated result is required?
- What operating condition must exist to obtain it?
- Which controls technician, factory representative or installer must attend?
- Which devices and access provisions must be installed beforehand?
- Who corrects a failed result within the bidder's design responsibility?

This catches a cost that a line labeled *TAB included* conceals: the balancing contractor's fee may be covered while attendance, enabling installation and return work remain unassigned.

There is also a legitimate judgment call. At DD, should the GC standardize an exact equipment selection or allow bidders to optimize the system? Standardize the performance inputs and physical constraints first. Allow different solutions only where the responsible design team can evaluate them and the estimate includes their adjoining costs. A cheaper HVAC selection is not equivalent if its electrical demand, roof support or controls arrangement changes another package.

## Curtain wall: distinguish prior product evidence from project acceptance

The [May 2019 UFGS 08 44 00 curtain wall guide](https://www.wbdg.org/FFC/DOD/UFGS/UFGS%2008%2044%2000.pdf), with October 2026 coordinated references, treats mockups, factory tests and field tests separately. The mockup notes say previously tested assemblies may serve the purpose in appropriate cases; the construction language specifies a full-size assembly with joints and accessories when that option is selected. Paragraph 1.5.2 also requires coordination of adjacent work, compatibility, deflection limitations, thermal movement and tolerances.

Read those ideas together. Evidence that a product configuration has been tested does not settle whether a bidder has priced the project's mockup, its actual interfaces or the required field acceptance work.

Do not automatically add a new laboratory mockup to every bid. Equally, do not accept *tested system* as a blanket substitute for the specified project work. Ask the responsible reviewer whether prior evidence is acceptable for the proposed geometry, components and performance criteria. Until resolved, keep the proposed substitution outside the comparable base.

### Worked comparison: the ranking changes, but the cheaper wall still needs a decision

The following figures are **illustrative**, not market prices or customer results. Assume both bidders price the same 20,000 square feet of curtain wall. The hypothetical issued package requires project anchor engineering, a tested project mockup and identified perimeter transitions.

| Comparison item | Bidder A | Bidder B |
| --- | --- | --- |
| Raw proposal | $1,800,000 | $1,890,000 |
| Project anchor engineering | Excluded; firm addback $24,000 | Included |
| Project mockup and testing | Excluded; firm addback $48,000 | Included |
| Perimeter transitions assigned to wall package | Excluded; firm addback $36,000 | Included |
| Comparable package position | $1,908,000 | $1,890,000 |

A's raw advantage is $90,000. Its confirmed additions total $108,000, so its comparable position is $18,000 higher than B's. Dividing the raw bids by area produces $90.00 versus $94.50 per square foot; dividing the comparable positions produces $95.40 versus $94.50. Area normalization did not identify the unequal design and acceptance obligations.

Do not add the $36,000 again in a separate sealant package. In this hypothetical, that work is assigned to the wall package and covered by the addback. Likewise, A's raw exclusion disappears only after the firm addition becomes part of its revised offer, not because the GC typed it into a bid tab.

Now suppose A offers to delete the $48,000 mockup addition using prior test reports. If the designated reviewer accepts that route under the project requirements, A's comparable position becomes $1,860,000, or $30,000 below B. If it is not accepted, $1,908,000 remains the comparison basis. Keep the proposal as a conditional alternate, using the separate alternate and allowance leveling method.

The decision is not whether mockups are always worthwhile. It is whether the permitted proof route answers this project's requirement without leaving interfaces or acceptance work uncovered.

## Carry the obligation through review comments and revisions

AIA's delegated-design explanation makes an important distinction: architect submittal review is limited, while responsibility for the delegated design remains with the contractor and its licensed professional under that framework. Do not treat a planned review as a transfer of the bidder's design commitment.

Before carry, require the proposal to state its treatment of design development within the agreed criteria, review responses, and changes to those criteria. These are different events. AIA's Design-Build Guide separately discusses design-refinement contingency when a fixed price is committed before design is complete; it does not supply a universal percentage or determine your subcontract allocation.

Our estimating recommendation is to close the review with a short commitment note:

- Design basis and revision used for pricing.
- Named party responsible for each design deliverable.
- Included construction scope and confirmed additions.
- Defined limits on revision or review-response services.
- Unresolved input, affected packages and retained exposure.
- Accepted alternatives and the authority accepting them.

When upstream criteria change, reopen the affected register rows, not just the engineering fee. The revised-quote leveling guide covers the mechanics of preserving the earlier and revised price basis.

For carry approval, the chief estimator should be able to answer two questions: Are we comparing the same obligation? If not, have we deliberately priced and assigned the difference? A precise adjusted total cannot compensate for an unresolved answer.

## Keep the design basis connected to scope and carry

This workflow needs one project basis that survives solicitation, clarification and carry approval. Separate copies of an assumption can leave the scope sheet promising one thing while the bid tab prices another.

[Piper's Scope Generation workflow](https://piper-ai.com/use-cases/scope-generation) organizes requirements from drawings, specifications and addenda into trade scopes with source references and surfaces uncertain boundaries for review. Its [Bid Leveling workflow](https://piper-ai.com/use-cases/bid-leveling) compares proposals against the intended project scope, extracts qualifications and exclusions, and keeps source-backed differences beside the raw and leveled positions.

For these packages, the useful application is connecting a stated requirement to the bidder's qualification and the estimator's clarification or carry treatment. Piper supports that review; it does not establish engineering adequacy, approve a substitute design or decide the carry. Those consequential decisions remain with the team and the responsible professionals.

### Does an included engineering fee make two delegated-design bids comparable?

No. Confirm the criteria, design deliverables and construction obligation separately. A fee can cover calculations or sealed documents without covering construction changes that follow. Obtain the bidder's commitment on those changes before treating its offer as equivalent to a bid carrying the complete package.

### Should the GC plug missing performance criteria?

Do not plug undefined criteria as though they were a known omission. Ask the responsible design team to resolve the input, then price the resulting scope. If pricing must proceed first, compare clearly stated scenarios and identify retained exposure rather than presenting a speculative adjustment as a completed design.

### Can prior curtain wall testing replace a project mockup?

Only where the project requirements and designated reviewer permit that evidence. Establish whether it represents the proposed assembly and required performance, and distinguish it from remaining field acceptance work. Keep a bidder's proposed substitution conditional until the applicable review is complete.

### Who should decide whether a different MEP solution is equivalent?

The responsible design professionals should determine technical acceptability; the estimating team should compare its complete cost consequence. Check adjoining electrical, structural, controls and acceptance scope before recognizing savings. Equal equipment capacity on a proposal does not establish equal installed scope or equal design commitments.