---
title: 'How to write a doors, frames and hardware scope subs will price the same way'
url: 'https://piper-ai.com/resources/doors-hardware-scope-of-work'
description: 'Write a doors, frames and hardware scope around opening IDs, supply and installation duties, electrical interfaces, keying and final acceptance checks.'
contentTypes: [guide]
publishedAt: '2026-11-29T11:07:09.369Z'
author: 'Ido Gedanken, CEO'
readingTime: 11
---

# How to write a doors, frames and hardware scope subs will price the same way

1. Use opening IDs to connect door and frame types, hardware sets and trade responsibilities.
2. Separate factory preparation from field installation and electrical connections.
3. Assign keying, final adjustment and acceptance work before requesting prices.
4. Price alternates as complete opening changes, not isolated hardware substitutions.

A doors, frames and hardware bid package should define a **completed opening**, then allocate each operation needed to deliver it. A list of Division 08 sections is not enough. For a GC estimator pricing a commercial building at bid-stage CDs, the scope must say which openings are included, who furnishes each component, who sets frames, who hangs doors and installs hardware, and who completes electrical connections, keying and final adjustment.

The position of this guide is simple: **keep one opening-based scope even when you buy the work through several contracts.** Separate supply and installation prices are useful. Separate definitions of the opening are not.

The outline below is practical estimating advice, not a substitute for the project's specifications, adopted codes or subcontract terms. It suits conventional swinging doors. Treat overhead doors and specialized assemblies as separately identified work, not an assumed extension of the package.

## Start with an opening register, not a hardware shopping list

Create a register with one record for each opening ID. Keep leaf count separate from opening count. Attach the door type, frame type, hardware set, rating, wall condition, finish and electrical status to that record.

This structure follows the interaction between two official guide specifications. [UFGS 08 11 13, Steel Doors and Frames](https://legacy.wbdg.org/FFC/DOD/UFGS/UFGS%2008%2011%2013.pdf), August 2020 with Change 1 of August 2025, calls for a door schedule with opening numbers, dimensions, materials, ratings and hardware set numbers. [UFGS 08 71 00, Door Hardware](https://legacy.wbdg.org/FFC/DOD/UFGS/UFGS%2008%2071%2000.pdf), February 2016 with Change 4 of February 2022, connects hardware sets to opening numbers, single or double leaves, handing, materials and ratings. Both fetched copies carry July 2026 reference coordination.

These are federal guide specifications intended for project editing. They are examples of useful document structure, not universal requirements for private commercial work.

The estimating consequence is more important than the format: a hardware set is not a quantity until it has been mapped to openings. A pair can have two leaves but one frame assembly. A reused hardware set can occur at many openings. Ask bidders to confirm the same mapping rather than submit only a total door count.

For each opening, record:

- Opening ID, building area and phase.
- Number of leaves, dimensions, handing and active leaf where applicable.
- Door material, construction, finish, glazing and louvers.
- Frame profile, jamb depth, wall type and anchorage basis.
- Hardware set and revision, including electrical devices.
- Fire, smoke, acoustic or other specified performance.
- Supply, installation and acceptance owners.
- Unresolved document question and its pricing treatment.

The broader [construction scope generation process](https://piper-ai.com/resources/construction-scope-generation-guide) explains how to assemble the document basis; here, the opening ID is the unit that keeps this trade package coherent.

## Reference the documents that change fabrication and installation

Attach an exact document register. Identify sheet numbers, issue dates, specification sections, addenda and issued clarifications. Do not let “per plans and specs” be the only description of the pricing basis.

Review the project's actual titles and numbering. Include the applicable hollow metal, wood door and hardware sections, plus sections governing glazing, sealants, painting, electrical work, access control and any special door assembly. Include Division 01 requirements that affect delivery, submittals, protection, testing or closeout.

The drawing list should include door and frame schedules, door elevations, wall types, jamb and head details, life-safety plans, finish schedules, security device plans and electrical details. Owner keying requirements belong in the same basis, even if they arrive as a separate attachment.

### Use a fabrication-release check that crosses three documents

Before authorizing fabrication, compare the opening register, wall detail and approved hardware information. Check the frame throat against the finished wall assembly, the anchor arrangement against the installation condition, and the door/frame preparation against the selected hardware.

This is a proposed GC check, built from two different technical sources. [ANSI/SDI A250.11-2026](https://steeldoor.org/ansi-250-11) distinguishes frame installation methods by wall condition and warns against wall construction that increases thickness beyond the intended finished thickness. [ANSI/SDI A250.6-2024](https://steeldoor.org/ansi-250-6) distinguishes factory reinforcement and mortised preparation from field preparation for surface-applied hardware.

Reading those requirements together changes the release decision. “Hardware by others” does not mean the frame can be ordered without hardware information. Conversely, “factory prepared” does not mean the installer has no drilling or tapping to price.

**Illustrative failure analysis:** a frame supplier orders to an old partition thickness while the framing subcontractor prices the revised wall. Both quotes can look complete within their own documents. The mismatch becomes replacement or corrective-work exposure, not a missed frame count. The check that catches it is an opening-level comparison of wall revision, frame profile and hardware preparation before release.

Require the bidder to identify discrepancies before fabrication and state how unresolved questions are priced. Route design questions through the [prebid RFI process](https://piper-ai.com/resources/construction-rfi-prebid-scope-review); the scope sheet should preserve the answer and affected opening IDs, not silently resolve a design conflict.

## Write inclusions as operations, not just products

Organize inclusions into supply, field work and completion. That makes a supply-only quote distinguishable from a furnished-and-installed quote without relying on an exclusion at the bottom of a proposal.

### Supply and preparation

Spell out the scheduled doors, frames and hardware, including the applicable:

- Hollow metal or wood door construction and finishes.
- Welded or knocked-down frames, profiles, anchors and accessories.
- Glazing kits, glass, louvers and astragals, with furnish and install owners identified.
- Hinges, pivots, locks, latches, exit devices, closers and stops.
- Protection plates, thresholds, sweeps, gasketing and other scheduled accessories.
- Cylinders, construction cores, permanent cores and keys.
- Electrified locks, strikes, power transfers and other scheduled electrical hardware.
- Factory reinforcement, cutouts, templates and preparation coordination.

These categories are grounded in the product and preparation provisions of [UFGS 08 11 13](https://legacy.wbdg.org/FFC/DOD/UFGS/UFGS%2008%2011%2013.pdf) and the hardware item list in [UFGS 08 71 00](https://legacy.wbdg.org/FFC/DOD/UFGS/UFGS%2008%2071%2000.pdf). Include only what the project requires; the list is a review aid, not permission to add every accessory to every door.

Identify shop primer separately from factory finish and field painting. If glass comes from another package, identify who provides the kits, installs the glass and verifies compatibility with the specified assembly.

### Field installation and protection

Allocate unloading, storage, distribution to floors, frame assembly, setting, anchoring, bracing, door hanging, hardware mounting and final adjustment. State responsibility for field preparation, touchup, damage and replacement under the subcontract terms.

Do not write “grout all rated frames” as a house default. [ANSI/SDI A250.11-2026](https://steeldoor.org/ansi-250-11) states that steel frames, including fire-rated frames, do not inherently require grouting and does not recommend grouting in drywall. Carry the project's actual requirement and assign the work where it is specified.

For a package with frames set by the framing subcontractor, require an inspection handoff before wall closure and another before door hanging. The proposed handoff should check opening ID, swing, frame condition and installation alignment, with a named owner for correcting deficiencies. SDI's erection standard calls for verification of swing, size and labeling before installation and notes that improper frame tolerances prevent proper opening function.

That handoff is a commercial decision. It does not create an automatic right to reject work or transfer liability; align it with the contract's inspection and correction provisions.

## Make the electrical boundary a connection schedule

“Access control by others” leaves too much room for different prices. Use opening IDs to allocate equipment, pathways, wiring, terminations, programming and testing.

[UFGS 08 71 00](https://legacy.wbdg.org/FFC/DOD/UFGS/UFGS%2008%2071%2000.pdf) requires coordination of electrified hardware with Division 28 electronic security components and provides for shop drawings showing power components and wiring coordination. The specification does not establish your project's subcontract split. The GC must write that split.

The following is an **illustrative allocation**, not a universal trade convention:

| Operation | Doors and hardware package | Other named package |
| --- | --- | --- |
| Electrified lock or strike | Furnish and mechanically install scheduled device | Security trade confirms compatibility |
| Door and frame preparation | Coordinate and furnish required preparation | Framing trade sets prepared frame |
| Power transfer | Furnish and mechanically install | Security trade wires through transfer |
| Branch power and pathway | Provide device requirements and coordination | Electrical trade provides assigned power and pathway |
| Low-voltage conductors and terminations | Identify device leads and connection information | Security trade provides assigned wiring and terminations |
| Programming and integrated test | Attend and correct mechanical/hardware issues | Security trade programs; GC coordinates test |

Expand the allocation for power supplies, readers, door-position switches, request-to-exit devices, operators and fire-alarm interfaces wherever specified. Identify each terminal boundary. If the hardware installer terminates a device but the security trade pulls cable, say so.

Competent estimators can disagree on whether to buy electrified hardware with the door package or the security package. Decide based on the specified system, qualified installer coverage, warranty obligations and who can coordinate preparation before fabrication. Do not decide merely because a device appears in Division 08 or Division 28.

Preserve one responsibility for managing the coordinated submittal even if several trades contribute. Otherwise, a supply saving can create a second procurement decision after the frames are already released.

## Define keying and acceptance as paid work

Separate cylinder supply from the keying process. State who attends the owner keying meeting, prepares the schedule, provides construction cores, installs permanent cores, delivers keys and supplies the required records.

[UFGS 08 71 00](https://legacy.wbdg.org/FFC/DOD/UFGS/UFGS%2008%2071%2000.pdf) treats cylinders and cores, keying systems, keys, coordination meetings and key-bitting closeout as distinct requirements. Your project may use a different owner process. The pricing question remains: does “keying excluded” remove only owner decisions, or also material and installation?

Write the answer. For example: “Owner approves the key hierarchy. This package includes the specified cylinders, construction cores, permanent cores, core changeover and key delivery. Keying schedule submission and meeting attendance are included.” Revise that illustrative language to match the actual contract.

### Acceptance must test the opening, not only the supplied closer

The [2010 ADA Standards, Section 404](https://www.access-board.gov/ada/) apply technical door requirements where scoped. Section 404.2.8.1 requires closers to be adjusted for at least five seconds from 90 degrees to 12 degrees. Section 404.2.9 sets a five-pound maximum opening force for interior hinged non-fire doors and sliding or folding doors; fire doors receive different treatment, and exterior hinged doors are not covered by that five-pound rule.

Do not turn those provisions into a blanket “five-pound closer” purchase description. Pair the applicable acceptance criteria with the frame installation and hardware mounting requirements in [SDI A250.11-2026](https://steeldoor.org/ansi-250-11) and [SDI A250.6-2024](https://steeldoor.org/ansi-250-6).

The resulting scope decision is to allocate final adjustment and verification after the opening is assembled, with correction duties assigned by cause. A closer adjustment cannot correct a badly aligned frame. A hardware installer should not be assumed to carry unlimited frame remediation merely because it performs the final test.

For rated openings, carry the project's specified labels, compatible components, inspections and documentation. UFGS 08 11 13 addresses door/frame labels, while UFGS 08 71 00 requires fire-door hardware compliance even when necessary hardware is not explicitly listed in a set. Confirm the applicable contract and code editions with the design team; a current guide-specification reference is not proof of local adoption.

## Price a complete opening change: an illustrative example

Assume a commercial package has **40 openings: 36 singles and four pairs**. That is 44 leaves and 40 frame assemblies. All counts, rates and costs below are illustrative, not market benchmarks.

The proposed base allocation is supply by the doors/hardware bidder, frame setting by framing, and door hanging plus hardware installation by a separate installer.

Illustrative base costs are:

- Door/frame/hardware supply: $82,000.
- Frame setting: 40 assemblies × $150 = $6,000.
- Hanging and mechanical hardware installation: 44 leaves × $220 = $9,680.
- One defined final adjustment and key/core changeover visit: $1,200.

**Illustrative complete carry: $98,880.** An $82,000 supply quote is not the package's completed-opening cost.

Now an alternate converts six of the single openings to electrified hardware. Assume the net hardware supply premium is $850 per opening, additional preparation is $95 per opening, security wiring/termination is $240 per opening, and coordinated testing attendance is $480 total.

The illustrative alternate is:

**6 × ($850 + $95 + $240) + $480 = $7,590.**

The revised completed-opening carry is **$106,470**, with unchanged base hanging and frame-setting assumptions. A hardware-only alternate of $5,100 understates this defined alternate by $2,490.

The useful distinction is not the arithmetic. It is that an opening function change must be checked against fabrication preparation, electrical coverage and acceptance work before it becomes an alternate price. Those operations come from different documents and may land in different contracts.

Ask bidders for the net add or deduct against an identified base, with opening IDs and retained work stated. For unit prices, define “each” as a leaf, frame assembly, hardware set application or completed opening. State whether preparation, installation, freight, adjustment and keying are included. Do not apply one generic “door add” rate to materially different opening types.

## Reusable scope outline for solicitation and buyout

Use this outline as an attachment to the opening register. Replace every placeholder and reconcile the allocation with adjacent packages before issue.

### General and document basis

- Project, package name, areas, phases and included opening IDs.
- Exact drawings, specifications, owner requirements, addenda and issued answers.
- Pricing status of unresolved questions, without silently overriding contract requirements.
- Submittal responsibilities, field verification and coordinated fabrication release.
- Delivery sequence, unloading, storage, protection and distribution responsibilities.

### Inclusions

- Scheduled doors, frames, hardware and accessories by opening.
- Glazing, louvers, seals and finishes where assigned.
- Factory reinforcement/preparation and hardware template coordination.
- Frame setting, door hanging, field hardware preparation and installation where assigned.
- Electrified hardware equipment and connection duties by opening.
- Cylinders, cores, keying work and owner coordination.
- Final adjustments, applicable inspections, test participation and closeout records.

### Exclusions and by-others work

For every accepted exclusion, record the receiving package, affected opening IDs and exact retained duties. “Finish painting by painting package” should not accidentally remove factory primer or assigned installation touchup. “Frame installation by framing” should not remove frame supply or template coordination.

Identify overhead doors separately. [UFGS 08 36 13, August 2020](https://legacy.wbdg.org/FFC/DOD/UFGS/UFGS%2008%2036%2013.pdf), covers sectional overhead doors with tracks, counterbalancing, operators, controls, electrical work and testing. That scope cannot be represented by a swinging-door hardware set. State whether the specialist package is included or excluded and where its power, supports and controls are carried.

### Clarifications, alternates and unit prices

- Base opening quantities and hardware-set mapping confirmed by bidder.
- Specific qualifications with the proposed treatment and required answer.
- Alternates by opening ID, with net equipment, preparation, installation and testing effects.
- Unit-price definition, included operations and conditions of use.
- Subcontract exhibit reconciled to the agreed bid basis before execution.

Before issue, perform three checks: every opening has coverage; every operation has an owner; every unresolved decision has visible pricing treatment. The door scope gaps guide addresses missing coverage, while door scope writing mistakes addresses wording that changes that intended allocation.

## Keep the issued opening scope connected to its sources

The operational problem is maintaining the same opening definition as schedules, wall details, hardware sets and owner decisions change. Do not allow a clarified bid to become a subcontract exhibit that drops the clarification or reverts to an earlier allocation.

[Piper's Scope Generation workflow](https://piper-ai.com/use-cases/scope-generation) prepares trade-specific scopes from drawings, specifications, addenda and company knowledge. Scope items remain linked to their sources, furnished-by/installed-by boundaries and uncertain responsibilities are surfaced for review, and the scope can use the team's existing structure. Affected scope can be surfaced when upstream information changes.

For this package, that means preparing a source-backed scope for the team to challenge, not delegating door function, code interpretation or trade ownership decisions. The estimator and preconstruction team still approve the allocation and the number.

### Should the doors and hardware bidder furnish and install everything?

Not necessarily. Buy supply and installation together or separately based on qualified coverage, project conditions and contract obligations. Keep one opening register either way, and explicitly allocate frame setting, door hanging, hardware mounting, electrical connections, keying and final adjustment so separate purchases share the same definition.

### What should a door hardware scope say about access control?

Allocate the devices and connections by opening ID rather than simply saying access control is by others. Identify hardware supply, preparation, power transfer, power supplies, pathways, conductors, terminations, programming and test participation. The allocation must match the specified system and the adjacent electrical and security packages.

### Can keying be excluded if the owner chooses the key system?

Owner approval of the key system should not automatically exclude cylinders, cores, changeover or key delivery. Separate the owner's decision from the supplier's materials and installer’s work. State who prepares the keying submission, attends coordination, supplies construction and permanent cores, and completes turnover.

### Is one unit price per door enough?

Only when the unit and included work are clearly defined and the opening types are comparable. A leaf, frame assembly and completed opening are different units. Separate rates where materials, ratings, hardware functions or electrical duties differ, and identify preparation, installation and completion work included in each rate.
