# DTX and Central Square: map elevator paths and station interfaces

For A34CN01, price the path served by each elevator and its adjacent passage work, not a single station-wide elevator allowance. The Boston transfer connections and Cambridge street-to-platform work have different boundaries; the Winter Street replacement also changes the number of stops, so treating it as a wholly new shaft without drawings would be premature.

## What the owner described

The MBTA's [archived CMAR listing](https://www.bidexpress.com/businesses/83754/home?page=5) describes a new two-stop Macy's elevator between Orange northbound and Red southbound at Downtown Crossing. The existing two-stop Winter Street elevator is to be replaced by a three-stop elevator serving street, Orange southbound and Red southbound, with a Red Line lobby and South Passageway extension. A new two-stop Park Street connection serves Orange southbound, Green eastbound and the Red center platform. At Central Square in Cambridge, the description replaces elevator 860 and its outbound-to-street hoistway and adds inbound and outbound street-to-platform elevators. It also describes rescue assistance areas, call boxes, smoke-proof enclosures, curb and bollards, and inbound escalator modernization.

These are historical procurement descriptions, not a current construction status or a complete issued set. The [2026 trade solicitation and reinvite](https://www.bidexpress.com/businesses/83754/home?page=2) are stages of the same procurement, not separate projects.

## A path-by-path interface register

The following is analyst review guidance, not an issued owner requirement. Assign each open boundary to a scope owner only after checking the drawings and trade packages.

| Location and path | Described work | Estimator's boundary question |
| --- | --- | --- |
| Macy's | New two-stop transfer elevator | Who carries excavation, enclosure, power and finishes at both landings? |
| Winter Street | Replace two stops with three; lobby and passage extension | Which existing shaft and equipment remain, and who carries demolition and modifications at the new stop? |
| Park Street connection | New two-stop connection among described platforms | Where do landing work and passage finishes end, and which package carries MEP tie-ins? |
| Central Square outbound | Replace elevator 860 and hoistway; add another outbound elevator | Are removal, replacement and added elevator work separately delineated in each bid? |
| Central Square inbound | Add elevator and modernize inbound escalator | Who carries surrounding station finishes, power and access interfaces? |
| Central Square shared areas | Rescue areas, call boxes, enclosures, curbs and bollards | Map each location to architectural, electrical, civil and elevator packages; confirm the actual extents. |

For each row, record the drawing revision, landing or passage limits, demolition, temporary protection, power and communications connection, finish restoration, and the bidder carrying each item. A bidder's elevator equipment price may be complete for its package while the surrounding landing remains unassigned. Conversely, two quotes may both include restoration; reconcile inclusions before carrying both.

## Close the unresolved boundaries

Ask for the issued plans and specifications, existing-conditions information, elevator package boundaries and any revised access or sequencing documents. Do not assume a closure, a code-compliance finding or a new shaft extent from the public summary. Mark each open item as included, excluded, allowance or unresolved, with a named follow-up and source revision. Use the local guide to verify the owner and issued procurement record, then [trace the controlling revision](https://piper-ai.com/resources/construction-addenda-management-for-gc-estimators) before leveling bids.