# DSNY Manhattan 3 hot water: heat pumps, storage tanks and controls define the retrofit

A Manhattan 3 domestic hot-water estimate needs a plant layout and controls boundary, not just a heat-pump equipment price. The proposed arrangement replaces one gas water heater with two heat-pump units, two storage tanks and a swing tank with resistance heat, so piping, electrical capacity, access and cutover deserve separate review.

The [May 2026 DCAS agency record](https://data.cityofnewyork.us/resource/fb86-vt7u.json?$where=reporting_period%3D%27202605%27%20AND%20managing_agency%3D%27DCAS%27%20AND%20fms_id%3D%27ACEDOS251%27) describes the existing 520 MBH gas heater and 200-gallon tank and proposes two heat pumps, two 500-gallon storage tanks and a 150-gallon swing tank. It describes a local building management system capable of BACnet integration. Its May 28 agency data lists construction procurement, not a verified current bid opportunity.

## Trace the water and control boundaries

Estimator analysis follows; capacities and equipment reflect the agency narrative, while responsibilities require issued documents.

| Component | Estimating question | Evidence required |
| --- | --- | --- |
| Heat pumps | Where are they located and who supplies power and connections? | Equipment layout, electrical design and manufacturer requirements |
| Storage tanks | Who carries foundations or supports, insulation and piping connections? | Tank schedule, structural and plumbing details |
| Swing tank | Who supplies resistance heat, controls and electrical protection? | Electrical and control diagrams and equipment schedule |
| Circulation | Which pumps and piping remain or change? | Existing survey and proposed hydraulic schematic |
| Local controls and BACnet | Who supplies points, integration, programming and verification? | Points list, sequence and network responsibility matrix |

Do not infer actual performance or savings from nominal equipment data. Review access and removal paths against field measurements, and ask whether structural work, temporary water service or electrical distribution is included in the issued scope.

## Price the cutover as a sequence

An illustrative shutdown plan identifies the affected showers and bathrooms, temporary hot-water arrangement if required, isolation and removal, tank installation, electrical energization and restart. Confirm the actual operating constraints with the owner. For acceptance, assign flushing, temperature and controls checks, integration demonstration, documentation and training to responsible parties under the issued requirements. A proprietary controller's integration capability does not itself establish a completed BMS connection.

For the broader package review, use the [MEP coordination review](https://piper-ai.com/resources/mep-coordination-preconstruction-scope) and the [trade scope generation](https://piper-ai.com/resources/construction-scope-generation-guide).