title: 'East Village CLMC1105: separate jack-and-bore, duct bank and owner conductor work'
url: 'https://piper-ai.com/resources/east-village-clmc1105-ductbank-bore-guide'
description: 'Review East Village CLMC1105 across jack-and-bore, carrier ducts and manholes, keeping groundwater assumptions and Austin Energy''s conductor handoff separate.'
contentTypes: [guide]
publishedAt: '2026-11-26T00:30:49.845Z'
author: 'Ido Gedanken, CEO'
readingTime: 2
---

# East Village CLMC1105: separate jack-and-bore, duct bank and owner conductor work

Price the bore assembly and its transitions separately from the owner’s later conductor installation. The 36-inch dimension describes the casing bore, not each carrier; groundwater in the summary is a site description, not a priced dewatering allowance.

## The dated project record

The City listing for IFB 6100 CLMC1105, checked November 17, 2026, showed a December 3, 2026, 2 p.m. deadline. It describes approximately 342 feet of 36-inch jack-and-bore with twelve five-inch carrier pipes grouted within the casing, 386 feet of twelve-duct open-cut bank, 79 feet of two-duct open-cut bank and two 12-by-12-foot manholes. Austin Energy will install conductors at project completion. The source is [Official IFB6100CLMC1105](https://financeonline.austintexas.gov/afo/account_services/solicitation/solicitation_details.cfm?sid=142008). Check the current owner record before relying on any date or project status.

## Follow the casing-to-duct-bank transitions

The following is an estimating review, not a statement that the owner assigned these tasks to a particular contractor. Use the current drawings, specifications and contract documents to settle the actual boundaries.

| Scope or location | Review and assignment question |
| --- | --- |
| Bore and casing | Trace launch and receiving limits, casing installation, access and restoration to the issued details. |
| Carriers and grout | Assign twelve carriers, spacers if required by the documents, grouting and the transition into the manholes. |
| Open-cut banks and manholes | Separate the twelve-duct and two-duct runs; identify excavation, structure connections, backfill and surface restoration. |
| Owner conductors | Record Austin Energy’s later conductor installation and confirm acceptance, access and handoff requirements. |

## Separate construction acceptance from conductor work

A bore quote and duct-bank quote may both stop at a manhole wall. Ask who connects and seals the carriers, completes the bank and restores the work area. Separately obtain the groundwater requirements and each bidder’s dewatering basis; do not insert an allowance unsupported by the documents.

Make a handoff line for the completed raceway before Austin Energy installs conductors. Confirm whether its acceptance requires a particular cleaning, verification or access condition; the listing names the owner-installed work but does not state those detailed obligations.

## Evidence needed for this package

Request bore and manhole connection details, groundwater requirements, duct-bank sections and Austin Energy's acceptance and conductor-installation sequence. Preserve the separate twelve-duct and two-duct runs and verify the crossing dimensions from the issued drawings.

For the broader method, see the [underground piping scope review](https://piper-ai.com/resources/plumbing-underground-scope-boundary). Use the project-specific register above to bring the general boundary review back to the actual work.