---
title: 'Feura Bush filter upgrades: separate mixing basins, media and underdrains'
url: 'https://piper-ai.com/resources/feura-bush-filter-mixing-basin-upgrades-scope'
description: 'A dated Albany capital-plan case for separating mixing-basin work, filter media, conditional underdrains and live-plant interfaces in an estimate.'
contentTypes: [guide]
publishedAt: '2026-11-23T06:53:49.540Z'
author: 'Ido Gedanken, CEO'
readingTime: 4
---

# Feura Bush filter upgrades: separate mixing basins, media and underdrains

For a GC or CM pricing work at Albany's Feura Bush filtration plant, the first scope decision is to separate the mixing-basin phase from later filter rehabilitation. Carry an underdrain assessment as a different decision from wholesale underdrain replacement, and do not automatically price a second set of filter valves and actuators. The [December 2025 Albany Water capital improvement program](https://www.albanyny.gov/DocumentCenter/View/14038/Albany-Capital-Improvement-Program---CIP---Five-Year-2026-2030-PDF) describes replacement of those controls as completed in 2024 and makes underdrain replacement dependent on an assessment (printed page 2-14, physical PDF page 24).

This is a capital-plan case, not an issued scope or a current bid announcement. The plan describes anticipated work and conditions at its publication date. A preconstruction team needs the current design, procurement documents and operating constraints before assigning a firm carry.

## Separate the phase and the decision

The plan identifies Phase 1 as mixing-basin rehabilitation, including removal of unused mechanical mixers and work on flocculation-basin sluice gates. It reports failing baffles and describes their replacement in Phase 1 (printed page 2-13, physical page 23). The same plan says the gates need repair, replacement or plating off pending review and design (printed page 2-14). Its project summary describes gate replacement. That difference is a reason to seek the design disposition, not to assume all three treatments are required.

The plan also schedules full filter rehabilitation in two phases, with new media, structural repairs and an underdrain assessment. It contemplates a new underdrain system if the assessment supports replacement, with completion scheduled for 2029. That is a planning schedule, not proof of completion. Appendix A lists Phase 2 as four filters and Phase 3 separately. Those labels do not establish the package boundaries in a later solicitation.

| Treatment in estimate | Element and source position | Decision before firm carry |
| --- | --- | --- |
| Retain or protect | Filter valves and actuators were replaced in 2024 and connected to plant SCADA, according to the plan | Verify the current equipment and drawings; define protection, isolation and any specified modifications rather than duplicate replacement |
| Remove | Phase 1 includes unused mechanical mixers or paddles; the plan identifies failing mixing-basin baffles for replacement | Obtain demolition limits, access and disposal requirements; distinguish removed equipment from replacement baffles |
| Conditional | Sluice-gate treatment awaits review and design; underdrains require assessment before potential replacement | Obtain disposition and assessment criteria; price an alternate or allowance only if the procurement permits it |
| Future filter phases | The plan describes new media and structural repairs in phased filter rehabilitation | Confirm which filters, quantities and repairs belong to the issued package, not merely the capital plan |

The 2025 plan says Phase 1 construction was anticipated in 2026, while another section lists Phase 1 design among projects planned for 2026. Neither statement establishes that construction started. Resolve the present stage with the owner and current procurement record before using any planned date as a schedule commitment.

## A worked handoff register for the estimator

The register below is an illustrative review tool, not an allocation of contractual responsibility. Assign actual package ownership only after reading the issued documents and subcontractor qualifications.

| Interface | Proposed handoff to resolve | Evidence or pricing consequence |
| --- | --- | --- |
| Mixing basin to demolition | GC asks process and demolition bidders to identify mixer removal limits, lifting route and retained services | Mark each item on the demolition drawing; identify who isolates and makes safe before removal |
| Baffles to concrete | Concrete bidder identifies replacement geometry, connections and repair limits after removal | Carry documented quantities; flag concealed substrate and access assumptions instead of treating every observed defect as defined work |
| Sluice gates to operations | Process mechanical bidder and plant operator establish whether each gate is repaired, replaced or plated off | Obtain gate schedule, isolation method and acceptance test; record unresolved dispositions as RFIs |
| Underdrains to media | Filter specialist identifies assessment, access, media removal and reinstatement; designer decides replacement scope | Keep assessment and replacement separate in the estimate; compare bids on the same stated assumption and identify the cost exposure if assessment changes the design |
| Existing actuators to controls | Electrical and controls bidders identify protection, reconnection and any specified changes to existing equipment | Avoid a duplicate replacement carry; obtain control points, shutdown and testing responsibilities |
| One work area to operating plant | Superintendent and owner operations develop an outage and return-to-service sequence | State permissible outages, temporary measures, sampling or acceptance steps if required by the contract, and the party responsible for each |

For example, suppose a filter specialist excludes underdrain replacement because no assessment has been issued, while another includes a complete new system. Their totals do not price the same scope. Level the proposals to a common documented basis, show the difference as a separate exposure, and ask the designer how the assessment will be authorized and translated into a change or priced option. Do not quietly add replacement to the base if the bid documents do not call for it.

## Plan the live-treatment handoffs

Before a price becomes a schedule promise, ask operations which basins or filters may be unavailable together, for how long, and at what demand or seasonal limits. Determine who provides isolation, verifies leakage through existing gates, manages water and debris, and approves return to service. These are diligence questions, not claims that a particular bypass, disinfection method or outage is specified for this project.

For mixing basins, connect removal and baffle installation to gate disposition and access. A gate that cannot isolate as assumed can change the work sequence. For filters, connect media removal to inspection of exposed walls and underdrains, then to repair decisions, media installation and acceptance. Price the consequences of waiting for an assessment separately from the physical replacement work where the contract structure allows. Record whether temporary equipment, testing, controls reconnection and operator attendance sit with the GC, a trade or the owner.

## Verify the current package before relying on the plan

Obtain the latest drawings, specifications, addenda, gate and equipment schedules, assessment reports, phasing requirements and bid form. Ask which filters and basins are in the package, whether prior work changed the 2025 baseline, and how unknown conditions are to be priced. Reconcile the resulting scope and exclusions against each proposal, then document the decision owner and the source revision for every open item.

The [Albany Water capital-plan decision guide](https://piper-ai.com/resources/albany-water-capital-program-preconstruction-decisions) provides the broader source and stage context. Use the [scope coverage guide](https://piper-ai.com/resources/construction-bid-coverage-guide) to check the resulting trade handoffs against the estimate.
