# Geotechnical baseline vs. data reports: read the contractual reliance before pricing

A borehole log is an observation at a location and time. A contractual baseline can be a different statement used to allocate risk. Before pricing excavation, identify which documents are incorporated, what the baseline actually says, and which clauses qualify reliance and notice. Neither the report title nor a subcontractor's assumption resolves those questions.

## Separate data, baseline and reference status

In the [WSDOT December 2020 design-build guidance](https://wsdot.wa.gov/publications/manuals/fulltext/M46-03/Chapter22.pdf), both the factual geotechnical data report (GDR) and the geotechnical baseline report (GBR) are contract documents in the described model. The GBR supplies the primary contractual interpretation and risk allocation, while separately identified reference documents are informational. This is a Washington agency example, not a hierarchy for another contract. Read the actual incorporation, precedence and qualifying clauses with counsel and the geotechnical team.

The historical [FHWA geotechnical guidance](https://highways.dot.gov/federal-lands/pddm/Chapter_06.pdf) also distinguishes factual investigation data from interpretation. Identify whether a report is preliminary or final and what it does not investigate. Factual does not mean noncontractual, and a contractual baseline is not automatically a final design value.

## Crosswalk the documents to the carry

| Item | Evidence to record | Estimating consequence |
| --- | --- | --- |
| Status and precedence | Contract list, revisions and order-of-precedence clause | Escalate conflicting documents before choosing a basis |
| Baseline | Exact location, units, duration and stated condition | Link the method and quantity to that statement |
| Qualifiers | Reliance, investigation and differing-condition provisions | Ask counsel what qualifications govern the bid |
| Method | Subcontractor assumptions and exclusions | Price the same stated condition across comparable bids |
| Notice and evidence | Contract procedure, recipients, time and records | Plan field measurement and a responsible notice owner |

In a fictional excavation, a borehole records a water level on the day drilled, while a GBR states an assumed inflow rate for the excavation under stated conditions. Those are different measurements. If a pumping quote uses a lower flow than the stated baseline, normalize its equipment and operating assumptions or obtain a priced qualification. If the baseline is ambiguous about duration or location, submit [clarification questions](https://piper-ai.com/resources/construction-rfi-prebid-scope-review); do not silently substitute the borehole reading.

## Preserve the basis through award

Attach the exact report pages and revisions to the estimate, identify the geotechnical reviewer and record the method, duration and contingency treatment. Compare [bid assumptions and qualifications](https://piper-ai.com/resources/review-subcontractor-exclusions-and-qualifications) against the contract baseline, not merely against one another. If actual conditions differ, document observations and route notice under the actual contract. A discrepancy alone does not establish entitlement or recovery.