# Harambee Phase 5A: separate path construction from the wider courts program

At Harambee Park, a Phase 5 label is too broad to define the path package. The City identifies Phase 5A path work as under construction, while its wider capital program describes courts and sewer and drainage work. For preconstruction, place each item against the actual package and issue set before carrying it. A capital-program description does not establish that every element is in the path contract.

The [City project page](https://www.boston.gov/departments/parks-and-recreation/project/harambee-park-improvements) identifies JAM Corp with the Phase 5A path work and describes continued engagement on the wider courts and walkway program. The City's [path connection notice](https://www.boston.gov/bid-listings/16578616) closed on May 21, 2026. It is a dated path procurement, not an invitation to price the whole park today.

## Phase boundary record

| Element | Evidence and boundary | Evidence to place it in a package |
| --- | --- | --- |
| Phase 5A path | City identifies path construction | Issued path plans, limits, specifications and contract revisions |
| Netball court and fencing | Broader Phase 5 capital mission | Approved court design and procurement boundary |
| Tennis court | Broader Phase 5 capital mission | Issued drawings, schedule and actual package identification |
| Sewer and drainage separation | Capital mission refers to separation as required by BWSC | Utility correspondence, approved alignment and issued connection details |

The City's [FY 2027 capital budget project profile](https://www.boston.gov/sites/default/files/file/2026/04/V4-3-Environment%2C%20Energy%20and%20Open%20Space_0.pdf) describes the broader Phase 5 mission. The public documents have different purposes: the capital profile expresses a program; the notice identifies a path procurement. Neither supplies a complete current contract scope here. This review did not inspect the issued path set, utility alignments or quantities.

## Reconcile the edge of the path

Overlay the issued path limits with the most recent court and utility information available to the team. At every crossing or termination, ask whether the path contract includes excavation, temporary restoration and final tie-in, and whether a later package depends on work already installed. Record the source, revision and responsible decision maker. Do not infer an answer from the proximity of a proposed court to the path.

For sewer and drainage, request the utility agency's applicable requirements and the design showing what is separated, where and under which package. Until then, an allowance or qualification should identify its basis and exclusions. That avoids pricing a notional utility alignment as if it were an issued quantity, while keeping a real interface visible for the next estimate.

## Carry the decision into solicitation

Before solicitation or buyout, reconcile the package list, drawings, specifications, schedule and addenda. If a later revision moves a tie-in, update both the path and adjoining package assumptions; [check the actual issued revision](https://piper-ai.com/resources/construction-addenda-management-for-gc-estimators). The [scope generation guide](https://piper-ai.com/resources/construction-scope-generation-guide) provides a way to trace each responsibility to its source. A completion day and a current tender were not established by the cited records.