---
title: 'Harper Street Asphalt Plant: define the dewatering treatment and discharge chain'
url: 'https://piper-ai.com/resources/harper-street-asphalt-plant-dewatering-interface'
description: 'Harper Street''s dated rebuild plan links tidal groundwater to treatment and a storm-sewer route, leaving operation and discharge responsibilities to verify.'
contentTypes: [guide]
publishedAt: '2026-11-28T23:01:50.875Z'
author: 'Ido Gedanken, CEO'
readingTime: 2
---

# Harper Street Asphalt Plant: define the dewatering treatment and discharge chain

## Price the whole water path

At NYC DOT’s Harper Street Asphalt Plant in Queens, excavation below tidal groundwater requires a pricing basis beyond pump rental. The [October 22, 2025 revised public participation plan](https://www.nyc.gov/assets/ddc/downloads/contracts/NYSDECPublicParticipationPlan_HWHARPER.pdf) for HWHARPER-3 describes sewer, separator and tank excavation, possible wellpoint or submersible pumping, and treatment before discharge through a NYSDOT storm sewer. It names DDC as applicant and says a contractor had not been awarded at that time.

The plan estimates 135 gallons per minute. That is a planning estimate, not a final permit limit or an as-built flow. Continuous pit pumping and trench work may have different durations and pumping needs; establish the excavation sequence and groundwater basis before using one flow assumption for every task.

## Follow the treatment and discharge chain

| Step | Dated plan or estimating question | Assignment and evidence to resolve |
| --- | --- | --- |
| Excavation | Below-water sewer, separator and tank work | Confirm elevations, sequence and groundwater information |
| Abstraction | Wellpoints or submersible pumps described | Match method and duration to each excavation; identify design and operation owner |
| Treatment | Settling, bag filtration and carbon treatment described | Confirm design basis, equipment, consumables and disposal responsibility |
| Conveyance | Treated water routed to a NYSDOT storm sewer | Confirm connection location, access and receiving-system coordination |
| Discharge and sampling | Follow the applicable authorization and monitoring terms | Identify permit holder, sampler, laboratory and reporting responsibility |
| Continuity | Treatment must match pumping assumptions | Resolve backup power, interruptions and contingency in the issued package |

These assignments are questions, not asserted contractor duties. In particular, identify who pays for sampling, sludge and spent carbon disposal, maintenance and backup power. Check the proposed flow and treatment basis against the excavation schedule before soliciting prices. The [underground scope boundary guide](https://piper-ai.com/resources/plumbing-underground-scope-boundary) helps review the related excavation and discharge interfaces.

## Keep project identities and permit status separate

The plan identifies HWHARPER-1 as demolition, HWHARPER-2 as fence and curb, and HWHARPER-3 as the rebuild. Do not blend nearby administration-building and garage project records into this chain without confirming their scope. The [draft SPDES document](https://www.nyc.gov/assets/ddc/downloads/contracts/NYSDEC_SPDES_DraftPermit_HWHARPER.pdf) has effective and expiration dates marked TBD. It does not establish an issued permit or current limits. Obtain the controlling authorization, connection conditions, issued construction documents and amendments before making a commitment.
