title: 'How to do AI site utility takeoff: assisted and agentic, step by step'
url: 'https://piper-ai.com/resources/how-to-do-ai-site-utilities-takeoff'
description: 'Measure storm, sanitary and water networks with AI using run-level tasks, plan-profile checks and a clear handoff from reviewed quantities to the estimate.'
contentTypes: [guide]
publishedAt: '2026-11-29T20:26:12.856Z'
author: 'Ido Gedanken, CEO'
readingTime: 11
---

# How to do AI site utility takeoff: assisted and agentic, step by step

1. Assign measurement tasks by network and run, not just by sheet.
2. Assisted tracing needs candidate review; agentic takeoff needs a network completeness review.
3. Keep pipe length, structure depth and excavation depth on separate bases.
4. Release quantities with their source geometry, measurement convention and open questions.

For a GC estimator reviewing a commercial site package at bid-stage CDs, the useful unit of AI takeoff is **a utility run with named endpoints**, not a sheet total. Prepare the current drawing set, define the measurement basis, then use assisted tools for selected runs and repeated symbols or an agent for a bounded network. Review the resulting geometry against plans, profiles and schedules before releasing quantities.

The distinction matters. Assisted takeoff proposes candidates that you accept or correct as you work. Agentic takeoff starts with a measurement task and returns a set of editable measurements to review. The second workflow delegates more of the search, so your review must establish whether the network is complete, not merely whether the returned lengths look plausible.

This process covers storm, sanitary and water utilities shown on drawings. It does not replace utility design, field verification or a subcontractor's installation plan. At DD or earlier, use it for documented extents and explicit assumptions, not to turn missing profiles into bid-ready excavation quantities.

## 1. Prepare a network package, not a civil-plan folder

Start with a sheet register for each network. Include the proposed utility plans, existing-conditions plans, profiles, structure schedules, trench details, grading sheets, specifications and current addenda. Add the relevant plumbing and fire-service interface sheets rather than assuming all exterior work is on civil drawings.

The source interaction is central to the method. The federal [UFGS stormwater guide specification](https://www.wbdg.org/FFC/DOD/UFGS/UFGS%2033%2040%2000.pdf), in its drawing-preparation notes, calls for new and existing pipelines, service and size, endpoint invert elevations, pipe-class limits, structure details and bedding conditions. These are different inputs to the same run. The guide is a specification template for project editing, not a universal requirement for commercial projects.

For each sheet, record its revision and intended use. Designate which source supplies route geometry, pipe classification, elevations and installation requirements. If two current sources disagree, preserve both references and raise the conflict. Do not establish a blanket precedence rule that the contract does not provide.

### Verify scale before assigning any length task

Calibrate the plotted PDF against a stated dimension or a known station interval, then check a second span away from the calibration location. Record the verification basis. Treat each enlarged plan or detail as a separate scale until checked.

On profiles, verify horizontal and vertical scales separately. For this workflow, read labeled elevations and stations rather than measuring depth from the apparent profile slope. If the PDF cannot pass the scale check, hold its scaled measurements and request a usable source.

### Decode the legend and write the work boundary

Create a short mapping of each utility family to its drawing convention: line pattern, symbol, label and proposed/existing designation. Assign diameter and material from the applicable labels and notes, not an assumed relationship to line weight.

Write the boundary as endpoints and responsibilities. For example: “Include the new sanitary network through the connection at existing MH-E; stop the building service at the stated plumbing interface; report the connection separately.” Do not use “all site utilities” as the whole scope instruction.

The five-foot interface is a convention to verify, not a universal subcontract boundary. The [UFGS water guide's introductory note](https://www.wbdg.org/FFC/DOD/UFGS/UFGS%2033%2011%2000.pdf) describes a system beginning five feet from buildings, with nearby piping typically covered by other divisions. Confirm the actual package split using the project's documents and the review approach in [the plumbing and site-utility boundary guide](https://piper-ai.com/resources/plumbing-underground-scope-boundary).

## 2. Set the quantity basis before choosing the AI mode

Keep three quantities distinct: the length used for estimating installed pipe, the length used for procurement, and the length used for contract payment. Do not silently use one total for all three.

For an example of an official payment convention, [UFGS 33 11 00, paragraphs 1.1.1 and 1.1.2](https://www.wbdg.org/FFC/DOD/UFGS/UFGS%2033%2011%2000.pdf), measures water pipe along centerlines between specified endpoints without deducting valves or fittings. Its payment language includes joints, specials and fittings in the pipe unit price while paying hydrants, valves and valve boxes individually. Apply that language only when incorporated into the project contract.

Your internal takeoff can still identify fittings individually for costing. Mark whether their cost belongs inside a pipe assembly or a separate estimate line. A separate count does not automatically mean a separate payable item.

Set these rules before measurement:

- **Pipe:** LF by network, material, diameter, class where specified, and defined depth band. State whether lengths are center-to-center, laying length or another contract basis.
- **Structures:** each by type, with the depth basis recorded. Keep rim or cover elevation and the relevant invert values available for review.
- **Appurtenances:** fittings, valves, boxes, hydrants, cleanouts and connections, with their parent run or structure identified.
- **Trench:** excavation, bedding and backfill from the applicable cross-section and extent. Record the width source and whether it is an estimating width or payment limit.
- **Acceptance work:** identify the specified testing, inspection and televising basis rather than deriving it from symbols.

For storm structures, [UFGS 33 40 00, paragraph 1.1.3](https://www.wbdg.org/FFC/DOD/UFGS/UFGS%2033%2040%2000.pdf), measures depth from the top of the cover or grating to the outlet-pipe invert, with project-edited provisions for additional depth. That is not an excavation-depth formula. Carry both bases separately if the project uses that structure measurement convention.

## 3. Choose the mode by the work you can define and inspect

The following is a recommended task split, not a claim that any software can execute every row. Confirm the chosen tool's actual outputs before delegating.

| Item group | Best mode for this task | Why | What to review |
| --- | --- | --- | --- |
| Isolated tie-in or congested crossing | Manual | Resolve a small, judgment-heavy extent directly | Endpoint, existing/new status, connection detail and responsibility |
| Clear pipe run between identified structures | Assisted tracing | Propose the route while the estimator controls selection | Full centerline, start and stop points, branches and label assignment |
| Repeated inlets, cleanouts or valve symbols | Assisted matching | Propose locations from a selected symbol example | Actual plan locations, type variants and schedule identity |
| Complete labeled storm or sanitary network | Agentic | Delegate the walk through runs and related sources | Every endpoint, branch, continuation, profile reference and unresolved run |
| LF split by diameter and depth band | Agentic, if supported | Combine reviewed geometry with labeled attributes | Segment boundaries, depth definition and evidence for each classification |
| Trench, bedding and backfill | Reviewed calculations after measurement | These quantities need an approved cross-section basis | Width, bottom elevation, material zones, structure allowances and inclusions |
| Testing, televising and service interruptions | Manual scope review | Define obligations from documents rather than geometry alone | Required extent, test method, acceptance basis and estimate owner |

In assisted work, start with one known run or one known symbol family. Inspect the proposal before applying it, correct the selection, then assign the item. You are directing each selection rather than asking the tool to establish the network's overall coverage.

For agentic work, begin with one bounded network. Require a run list as well as quantities, so the review has a visible record of what the agent searched and what it left unresolved. The broader AI takeoff process explains the cross-trade sequence; here the defining task is reconciling connected utility runs.

## 4. Give the agent endpoints, sources and stop conditions

A useful request specifies the network, the sheets, the measurement convention and the review artifact. It also says what not to infer.

**Illustrative agent task brief, using fictional sheet and structure identifiers:**

\`\`\`text
Task: prepare an editable takeoff of the proposed sanitary network.

Use the current issued plans C-301 and C-302, profiles C-401,
structure schedule C-501, trench detail C-601 and sanitary specs.
Use the verified scale recorded for each plan view.

Boundary: include new runs from MH-S01 through MH-S06 and the
connection to existing MH-E01. Include branches within this boundary.
Stop building services at the documented plumbing package interface.
List existing piping as context, not new pipe quantity.

Walk the network by structure ID. Assign each run a from/to ID.
Measure one centerline per pipe. Report the plan center-to-center LF
separately from any laying-length adjustment or payment quantity.

For each run, record diameter, material/class, source label, plan LF,
profile station interval, endpoint surface/invert elevations and sources.
Use the approved depth-band definition. Split at band crossings only
where the elevation basis supports the split; retain segment quantities.

Count new structures by type. Record the specified structure-depth basis.
List fittings, cleanouts and connections with their parent run or node.
Identify specified testing and inspection work separately from geometry.

Return editable drawing measurements plus a run register and open questions.
Do not guess missing labels, invert elevations or trench widths.
Flag plan/profile conflicts, numbering gaps and sheet-edge continuations.
Mark each run ready for review or held, with the reason and source reference.
\`\`\`

This is a proposed task, not a report of a completed software test. If the tool cannot return the requested register or attributes, prepare them manually beside the editable measurements. Do not lower the review standard to match an unexplained total.

Use separate requests for water and gravity networks. For water, substitute valve, fitting, hydrant and service endpoints where structure numbering does not define the route. Require the same connection between each quantity and its source evidence.

## 5. Review the returned network on the drawing

Review in three passes: coverage, classification, then quantity basis. This order is a practical choice: checking arithmetic on an incomplete network does not establish coverage.

**Coverage:** walk from the boundary's starting node through every branch to its endpoint. Match each run-register row to drawing geometry. At match lines, use the same endpoint identity on both sheets and assign one measurement owner. Reconcile the node list with the structure schedule and account for every continuation.

**Classification:** open the relevant label, profile or schedule for each run. Verify material, diameter, proposed/existing status and structure type. For a structure with several inverts, identify which one governs the pipe segment and which governs the specified structure depth.

**Quantity basis:** compare measured route length with printed dimensions or profile station intervals where applicable. A station interval is a cross-check only when its alignment and endpoints correspond to the measured route. Investigate a disagreement before choosing either number.

For example, [UFGS 33 30 00, paragraph 3.1.1](https://www.wbdg.org/FFC/DOD/UFGS/UFGS%2033%2030%2000.pdf), calls for installation drawings with plan and side views, layout and elevations. The estimating recommendation here is to keep those horizontal and vertical inputs connected by run ID, rather than reviewing them as unrelated sheet totals.

Mark quantities as accepted, corrected or held. A held classification need not erase a valid measured length: retain the length with an unresolved diameter or depth assignment. Release only the portion whose basis is settled, and give the remaining question an owner.

For automated-selection failure checks beyond this process, use the site-utility AI pitfalls review.

## 6. Derive trench quantities from reviewed runs

Do not convert total pipe LF into excavation before settling the trench section. [UFGS 33 40 00, paragraph 3.1.1](https://www.wbdg.org/FFC/DOD/UFGS/UFGS%2033%2040%2000.pdf), directs trench width to the drawings or specification and refers excavation and backfill to the earthwork section. Use the project's applicable detail, including any separate payment limits.

Define pipe-depth bands explicitly. “Depth” might mean surface to invert for your estimate classification, while excavation extends to the trench bottom and structure pricing uses a different elevation pair. Store the inputs instead of collapsing them into one average depth.

**Illustrative calculation:** a fictional 120 LF run has a constant surface elevation of 100.0 feet and an invert falling linearly from 94.0 to 92.0 feet. Surface-to-invert depth therefore increases from 6.0 to 8.0 feet. If the estimating band boundary is 7.0 feet, the crossing occurs halfway along the run: retain two 60 LF segments, subject to the team's boundary-inclusion rule.

That split is justified only by the stated constant surface and linear invert assumptions. With intermediate grades, vertical changes or missing elevations, subdivide from supported data or hold the allocation.

For a separate **illustrative excavation calculation**, assume the reviewed trench-bottom basis gives an average excavation depth of 7.5 feet and an approved rectangular width of 3 feet. Gross volume is 120 × 3 × 7.5 ÷ 27 = 100 CY. This excludes structure excavations, overbreak and any sloped-side geometry. It is not automatically the backfill or disposal quantity.

Derive bedding and backfill from their specified zones and documented displacement assumptions. Keep excavation, imported material and spoil disposition distinct. For item structure and formula setup, refer to site utility takeoff tips.

## 7. Release an estimate handoff, not just a quantity export

The handoff should let another estimator reopen the run and understand the carry. Deliver:

1. The issued-set and scale basis.
2. Editable measurements and the run register.
3. LF summaries by network, material, diameter and approved depth band.
4. Structures and appurtenances linked to run or node IDs.
5. Trench calculations with the detail, width and depth inputs.
6. Testing, connection and restoration scope with its estimate owner.
7. Accepted corrections, unresolved questions and qualifications.

Read acceptance requirements before deciding what the pipe assembly includes. The [water guide specification](https://www.wbdg.org/FFC/DOD/UFGS/UFGS%2033%2011%2000.pdf) covers flushing, disinfection and several field tests. The [sanitary guide](https://www.wbdg.org/FFC/DOD/UFGS/UFGS%2033%2030%2000.pdf) contains leakage, pressure and deflection testing provisions. These templates illustrate what to search for; the edited project specification establishes the applicable scope. Verify televising separately rather than assuming a uniform requirement across all networks.

Keep field obligations separate from drawing certainty. In US work subject to [OSHA 1926.651(b)](https://www.osha.gov/laws-regs/regulations/standardnumber/1926/1926.651), underground-installation locations must be addressed before excavation, exact locations determined by safe and acceptable means as work approaches them, and installations protected, supported or removed as necessary while the excavation is open. A measured existing line does not establish that those obligations are priced. Assign the locating and protection basis for review without treating the takeoff as field verification.

On a hard bid, unresolved scope belongs in a clarification or explicit carry decision. On a developing GMP, retain the assumption and responsibility for its next confirmation. When an addendum changes a run, use the retained IDs to review affected pipe, structures, trench quantities and acceptance work; [drawing revision cascades](https://piper-ai.com/resources/drawing-revisions-cascade-scope-bids-estimate) explains that handoff beyond takeoff.

## Questions before releasing site utility quantities

### Should I ask an agent to measure the entire site at once?

Start with a bounded network whose endpoints and sources you can verify. Review its run register and drawing measurements before expanding the task. Separate storm, sanitary and water requests make the measurement basis and unresolved questions easier to inspect without accepting a single mixed total.

### Is center-to-center pipe length the quantity I should buy?

Not automatically. Retain the stated estimating or payment convention separately from procurement laying length. Review structure dimensions, fittings and the installation basis before making adjustments. The takeoff handoff should identify which length each total represents rather than allowing procurement to inherit an unlabeled LF number.

### Can the agent assign depth bands when the profiles are missing?

Hold unsupported depth assignments rather than guessing. You can retain a valid plan length while leaving its depth classification unresolved. If precon needs a provisional number, document the assumption separately, name who must confirm it and keep it distinguishable from quantities derived from labeled elevations.

### What is the minimum review for assisted tracing?

Inspect the full proposed route before applying it, then verify endpoints and item assignment. For a utility run, review the centerline, branches, label and extent on the actual source sheet. That candidate-level review is different from establishing completeness of a whole network returned by an agent.

## Keep the reviewed runs connected in Piper

One way to run this process is [Piper's takeoff workflow](https://piper-ai.com/use-cases/takeoff). Piper supports manual, assisted and agentic takeoff from PDF drawings in one editable takeoff file. Measurements remain attached to their source sheets, so the team can inspect scale, geometry and item assignment rather than reviewing only a rolled-up quantity.

Assisted tracing and symbol matching provide candidates to inspect and correct. In agentic takeoff, the estimator describes the measurement task and reviews the editable measurements the agent creates. Neither mode removes the need to check network coverage, source labels or unresolved scope.

Takeoff sits in the same project as drawings, specifications, trade scopes and bid review. That shared project basis matters when a changed utility run affects more than pipe LF. The team still supplies and reviews formulas, pricing and the carry decision. The useful result is a quantity whose extent and assumptions remain inspectable as the project changes.