# Hudson Tunnel Project: Manhattan Tunnel package 1B contractor scope and package guide

The Hudson Tunnel Project's Manhattan Tunnel package 1B builds the Manhattan-side segment between the river bulkhead and the Hudson Yards concrete casing east of 12th Avenue. It is distinct from the cross-river tunnel package. The Gateway Development Commission's February 3, 2025 [Manhattan Tunnel contract award](https://www.gatewayprogram.org/wp-content/uploads/2025/10/GDC-February-3-2025-Board-Meeting-Press-Release-for-website.pdf) awarded the work to Frontier-Kemper-Tutor-Perini JV and authorized notice to proceed.

## What the award says about the work

The award describes obstruction removal and protection of the bulkhead and sewer lines. GDC's [Manhattan Tunnel project page](https://www.gatewayprogram.org/manhattan-tunnel-project.html) says construction launched in 2025, and its April 2026 [Hudson River Tunnel award](https://www.gatewayprogram.org/wp-content/uploads/2026/04/P1C-Contract-Award-Press-Release.pdf) described the Manhattan Tunnel as under construction. The 2025 award projected substantial completion in 2029; that is a historical forecast, not evidence of current progress or a revised completion date.

## Resolve the shaft and casing interfaces

For an estimate or subcontract review, place the shaft, bulkhead, sewer protection and obstruction removal on a single interface register. Record which drawings define each limit, who supplies temporary protection, the condition at handover and which work must be accepted before the next contractor proceeds. Ask for survey controls and the design's allocation of existing-condition risk in the actual contract.

At the casing end, compare physical termination and tolerance requirements with the Hudson Yards casing section 3. At the river end, check the separately awarded Hudson River Tunnel package 1C. The project boundary does not by itself allocate every temporary or permanent detail.

## Documents to obtain before carrying an interface

Use the issued geotechnical baseline and investigation documents, utility and protection drawings, staging plan, package limits and current changes if applicable. Compare subcontract exclusions with the prime's obligations, especially removal, protection and reinstatement. Record unanswered conditions as RFIs or qualifications, not as assumed scope. The NYC public project directory locates related public work.

## Review the Manhattan tunnel documents

Once a real package and its controlling documents are available, use the [NYC public bid review](https://piper-ai.com/resources/nyc-public-construction-bid-review-checklist) to record eligibility, addenda and unresolved qualifications. [Piper scope generation](https://piper-ai.com/use-cases/scope-generation) is a workflow for reviewing project documents supplied by the contractor. Confirm every scope assignment against the issued documents and trade quotations before carrying it.

The [construction scope review guide](https://piper-ai.com/resources/construction-scope-generation-guide) offers a method for assigning interfaces from the issued documents.

Compare the Manhattan and cross-river package boundaries so tunnel boring and approach work are not treated as the same contract. See the Hudson River Tunnel Section Package 1C guide.