title: 'Hutchinson River Parkway District 10 Headquarters Construction: project status and contractor scope review'
url: 'https://piper-ai.com/resources/hutchinson-river-parkway-district-10-headquarters-construction-parks-10442-contractor-guide'
description: 'Hutchinson River Parkway District 10 Headquarters has a separate trailer reference. Verify its relationship to the building package and current procurement.'
contentTypes: [guide]
publishedAt: '2026-11-19T15:02:16.276Z'
updatedAt: '2026-11-19T15:02:16.293Z'
author: 'Ido Gedanken, CEO'
readingTime: 2
---

# Hutchinson River Parkway District 10 Headquarters Construction: project status and contractor scope review

This project will construct a headquarters for Bronx M&O District 10 at Hutchinson River Parkway. The [NYC Parks tracker record](https://data.cityofnewyork.us/resource/4hcv-tc5r.json?trackerid=10442) identifies tracker **10442**, FMS **846 P-110HRMO**, at Hutchinson River Parkway East, Continental Avenue and East 197th Street, Bronx. The recorded phase is **procurement**. The dataset row was last updated November 13, 2026 and this research was checked November 15, 2026. The practical decision is whether the issued scope and current procurement documents justify a pursuit, not whether the tracker phase implies a live bid.

## Recorded project status

The tracker reports design 100% complete, procurement 5% complete and construction 0% complete. These percentages describe separate phases. Project funding is **between $3 million and $5 million**, with source listed as Mayoral; this is funding, not a bid price or award.

The row records design start: June 1, 2024; original projected design completion: September 1, 2025; adjusted design completion: April 1, 2026; actual design completion: April 1, 2026; procurement start: October 1, 2026; projected procurement completion: October 1, 2027. Projected and adjusted dates are forecasts, not evidence that a milestone occurred. Any construction start shown in a procurement-phase record is a scheduled field, not confirmation that work began. A past forecast is not a current deadline or proof of completion; where it has elapsed, the current schedule is unknown. The [dataset and data dictionary](https://data.cityofnewyork.us/Recreation/Capital-Project-Tracker/4hcv-tc5r) provide the context for the tracker fields.

## Headquarters and trailer boundaries

The tracker identifies a new district headquarters but does not describe its building systems or site work. A [2026 City Record design agenda](https://a856-cityrecord.nyc.gov/RequestDetail/20260511029) separately identifies two prefabricated office trailers at the same headquarters. Confirm whether those trailers belong to this tracker package, and which foundations, connections and site work the issued set assigns to it. The agenda alone does not establish the package boundary.

## Check the current procurement documents

Use the tracker to identify the project, then obtain the controlling solicitation, drawings, specifications and addenda from the agency. Verify the current status, eligibility and deadlines before assigning bid resources. The tracker does not itself establish an open solicitation or a contractor award. The [NYC public bid review](https://piper-ai.com/resources/nyc-public-construction-bid-review-checklist) helps record those decisions, and the project directory places this guide among other named projects.

## Review the headquarters package

With the actual documents in hand, Piper's [scope-generation workflow](https://piper-ai.com/use-cases/scope-generation) supports a document-based review. See also the [construction scope review guide](https://piper-ai.com/resources/construction-scope-generation-guide). This is independent Piper analysis, not an NYC Parks notice or affiliation. Research checked November 15, 2026.