title: 'I-35 Capital Express drainage tunnels: review shafts, pumping and corridor interfaces'
url: 'https://piper-ai.com/resources/i35-capex-drainage-tunnel-pump-station-scope-guide'
description: 'Review I-35 Capital Express drainage scope across tunnels, access shafts, pumping and controls, with a register for installation access and system turnover.'
contentTypes: [guide]
publishedAt: '2026-11-29T01:42:03.231Z'
author: 'Ido Gedanken, CEO'
readingTime: 2
---

# I-35 Capital Express drainage tunnels: review shafts, pumping and corridor interfaces

TxDOT reports that construction of the I-35 Capital Express Central Drainage Tunnel and Pump Station segment began in mid-2025, with completion anticipated in 2029, weather permitting. The scope includes two drainage tunnels, shafts and a pump station. [TxDOT drainage tunnel segment](https://www.txdot.gov/mymobility35/projects/capex-central/drainage-tunnel-and-pump-station.html) Source status checked November 17, 2026. Price tunnel, shaft and pump work against a single access and turnover sequence. A civil completion date alone does not settle who makes the shaft ready for equipment installation or who tests the system through its discharge.

## Separate tunnel access shafts from pumping interfaces

The following register is estimating analysis, not a statement of the owner’s contract assignments. The owner overview establishes the project context; the current drawings, specifications and package documents determine what a bidder must carry.

| Interface | Review boundary | Decision to resolve |
| --- | --- | --- |
| Tunnel and shafts | Excavation, lining and access interfaces | Who delivers dry, accessible installation areas and closes temporary openings? |
| Pump equipment | Equipment setting and mechanical connections | Who provides lifting, temporary support and final alignment? |
| Power and controls | Feed, instrumentation and control interfaces | Who terminates and tests signals between equipment and site systems? |
| Outfall | Discharge connection and surrounding work | What are the issued discharge limits and test boundaries? |
| Highway access | Work zones, delivery and restoration | Which party provides access, traffic control and final reinstatement? |

TxDOT identifies SAK/Shea JV Construction and Webber Waterworks as contractors. That identification does not establish the division of subcontracts. [TxDOT drainage tunnel segment](https://www.txdot.gov/mymobility35/projects/capex-central/drainage-tunnel-and-pump-station.html)

## Follow the drainage system through its discharge

Use separate tunnel-shaft and pump-station rows. List access periods, installation openings and temporary works at their documented locations. Track each exclusion to a priced scope, a documented allowance or an RFI; the table does not represent the awarded contract split.

The overview establishes two tunnels and maintenance-access shafts; it does not establish that a pump is installed at every shaft. Keep a tunnel-shaft register and a pump-station register separate, linking them only at interfaces supported by the issued drawings. A tunnel contractor's excavation completion is a different milestone from mechanical access and operational acceptance.

## Documents to request before committing

Request shaft-specific access and closure details, pump-station installation openings, equipment and control interfaces, and discharge limits. Assign temporary access and lifting requirements at the actual equipment location. Do not apply a hypothetical pump-trade handoff to every tunnel shaft or assume a public contractor list supplies the subcontract split.

The [logistics estimate review](https://piper-ai.com/resources/construction-logistics-plan-estimate-review) provides a broader method for documenting these boundaries and carrying unresolved assumptions through bid review.