title: 'IAH Taxiways SA and SB dropped the 62-unit guard-light line from the base bid'
url: 'https://piper-ai.com/resources/iah-taxiways-sa-sb-addendum-5-base-alternate'
description: 'Reconcile the airfield bid form, electrical takeoff and phasing assumptions after Houston Airports revised the base and alternate 1.'
contentTypes: [guide]
publishedAt: '2026-11-19T05:21:41.442Z'
updatedAt: '2026-11-19T05:21:41.450Z'
author: 'Ido Gedanken, CEO'
readingTime: 3
---

# IAH Taxiways SA and SB dropped the 62-unit guard-light line from the base bid

At Houston’s George Bush Intercontinental Airport, a revision to the Taxiways SA and SB rehabilitation bid form removed an entire 62-unit guard-light line from the base bid. It also changed the same item in Additive Alternate 1 from 31 to 62. An estimating team pricing the base and alternate together would therefore carry 62 under the revised form, down from 93 in the preceding form. The base bid and the alternate need their own scope reconciliation before electrical quotes go into the estimate.

This historical public-package comparison was prepared with [Piper](https://piper-ai.com/), the AI operating system for preconstruction.

## Carry the revised bid form into the takeoff

Houston Airports’ [Addendum 3](https://assets.ctfassets.net/fwldykjthzos/2rbOwJ1w57WqaZVVjNjf3f/006f6958af2049bd437a0da50d819516/Addendum_20No.3_20HJA_20TXSASB_202024_20020.pdf) lists the old duct bank and guard light quantities in Form 00410B at PDF pages 15–16 and 20. A bidder subsequently asked about overlap between the base bid and Alternate 1, including light fixtures. [Addendum 5](https://assets.ctfassets.net/fwldykjthzos/68Fuz6JijHIO7Xar7oMWMo/70681aa3c9c1653b2ca26a87e0cc6fdb/Addendum_20No.5_20HJA_20TXSASB_202024_20020.pdf) answered by replacing Form 00410 and drawing G01.04. The revised Part B runs through PDF pages 6–18. The Alternate 1 quantities below appear on page 14 and the revised quantity-summary sheet is page 19. [Addendum 6](https://assets.ctfassets.net/fwldykjthzos/6sieiWQY1OwZ14OpnSrGKA/ac23cff5e2a11fed6e0155931c044d3f/Addendum_20No.6_20HJA_20TXSASB_202024_20020.pdf) changed the bid deadline to July 18, 2024. The issuer’s Addendum 6 gives no replacement form.

| Electrical pay item | Addendum 3 | Addendum 5 | Estimate decision |
| --- | --- | --- | --- |
| L-125-5.7 in-pavement runway guard lights | Base 62 EA; Alternate 1 31 EA | Base line removed; Alternate 1 62 EA | Remove the base allowance for this pay item and rebuild the alternate quote at the revised quantity. |
| L-110-5.7 flowable-fill encased 2-way 2-inch duct bank | Base 650 LF; Alternate 1 700 LF | Base line removed; Alternate 1 200 LF | Check the specific assembly, then reconcile the independent base and alternate quotes to the revised sheet and form. |
| P-620-5.1i existing marking removal | Base 1,500 SF | Base 36,320 SF | Requote marking removal against the new base quantity and phase limits. |

The arithmetic for a hypothetical price containing the base and Alternate 1 is 93 to 62 guard lights and 1,350 to 200 LF of that specified duct bank. Those are comparisons of two bid-form versions. Confirm the actual award scope and issued execution documents before treating either comparison as installed work or attributing a dollar amount to it.

## Keep the marking and erosion-control assumptions separate

The 34,820-SF increase in the base marking-removal item follows the bidder’s request to check removal coverage. Compare PDF page 15 in Addendum 3 with page 9 in Addendum 5. In Addendum 5, Question 4 directs bidders to allow time for asphalt curing before painting and points to sheets G03.01–G03.10 for the temporary marking scope. Review the [issued drawings](https://downloads.ctfassets.net/fwldykjthzos/6qns7558M2tlLxtOvjf6SX/7176f6aba507c798f47df59785fa6b08/Drawings_20HJA_20TXSASB_202024_20020_compressed.pdf) along with the [construction safety and phasing plan](https://downloads.ctfassets.net/fwldykjthzos/7gMcWdiz8ogOu2tX5Zd6T/d538390f99ba144f014ca76aee21d70d/Project_20Manual_20Vol_202_20_28CSPP_29_20HJA_20TXSASB_202024_20020.pdf) before carrying reopening and remobilization assumptions. Keep temporary markings, masking and later permanent work visible when lining up the paving, electrical and paint quotes.

Question 7 addresses a different measurement problem. A bidder had measured identical 74-foot filter-dam symbols on the stormwater plans. Houston Airports clarified that the Type II symbol marks placement and points to C09.13, Detail 3. The dam spans the channel toe to toe. Carry the issued pay item with a separate record of the field-measure basis for each applicable location.

## Use the award record for the award question

Houston Airports’ [July 18 bid tab](https://assets.ctfassets.net/fwldykjthzos/DiN2MUTc6v4FpoefSDGtS/14512860fba5ce6653546ead601e4994/Bid_20Tabulation_20HJA_20TXSASB_202024_20020.pdf) records offers from Posillico, Granite and Zachry, subject to validation. The [Houston Airports award record](https://www.fly2houston.com/airport-business/business-partnerships/contracting/solicitations/details/rehabilitation-of-taxiways-sa-sb-at-george-bush-intercontinental-airport-hja-txsasb-2024-020/) records a $55,096,854.80 award to Posillico Civil, Inc. [City Council’s February 5 action](https://pwehelp.houstontx.gov/citysec/agenda/2025/20250204.pdf) lists Ordinance 2025-0065. The public records give no accepted-alternate breakout or explanation for the difference from the provisional tabulation. The estimate review belongs at the pay-item, drawing and trade-quote level.

The [construction specifications and scope review](https://piper-ai.com/resources/construction-specifications-masterformat-scope-review) helps carry that revision into the electrical and civil subcontract exhibits. Preserve the superseded quote alongside the qualified replacement so the preconstruction team can explain the difference before buyout.