# Inwood Hill Park sports lighting: start with the service and foundations

A lighting-only allowance is an incomplete early review for the proposed Inwood Hill Park ballfield project. The estimator needs a service-to-luminaire boundary and an explicit foundation assumption, with subsurface evidence before a foundation design is priced as settled.

[NYC Parks tracker 1973111](https://data.cityofnewyork.us/resource/4hcv-tc5r.json?$where=trackerid%3D%271973111%27) describes lighting near the Nature Center, including LEDs, drivers, controllers, poles, foundations, panels, enclosures and new Con Edison service, as well as subsurface borings, testing and reporting. Its November 13, 2026 update lists the project as proposed. It is not an issued design or invitation to bid.

## Follow the system from service to field

The matrix is estimator analysis, not an allocation established by Parks.

| Boundary | Question for package review | Information to obtain |
| --- | --- | --- |
| Utility service | Who coordinates utility work and pays any separately assessed charges? | Service application, utility response and point of connection |
| Panels and distribution | Who carries enclosures, feeder routes, terminations and restoration? | One-line diagram, site plan and electrical scope |
| Foundations and poles | Who designs and constructs foundations and supplies anchor details? | Borings, foundation design and pole manufacturer information |
| Lights and controls | Who provides drivers, control wiring, programming and functional tests? | Fixture schedule, controls sequence and acceptance plan |

A pole price alone does not establish a foundation price. Until investigation and design information are available, keep the assumed foundation basis and resulting exposure visible. Do not invent a soil condition, pole count, depth or route.

## Separate similar field projects

The [May 2026 St. Vartan Park agency record](https://data.cityofnewyork.us/resource/fb86-vt7u.json?$where=reporting_period%3D%27202605%27%20AND%20managing_agency%3D%27DPR%27%20AND%20fms_id%3D%27SEED-VRTN%27) separately names service, conduits, cables, a scoreboard and service equipment. It is a pre-design record, not an Inwood specification. The difference is a reason to request each project's own issued scope, not to transfer the scoreboard into this estimate.

## Make the allowance auditable

In an illustrative preliminary carry, list utility coordination, distribution, investigation, foundations, poles, luminaires and controls as separate lines. Mark each included, excluded or unresolved, name the assumed package owner and note which design answer would change it. Confirm field access, surface restoration and testing responsibility before leveling actual proposals.

For the broader package review, use the [electrical bid exclusions](https://piper-ai.com/resources/common-electrical-bid-exclusions-gcs-should-review) and the [estimating from incomplete drawings](https://piper-ai.com/resources/design-intent-estimating-incomplete-drawings).