# How to write a landscaping and irrigation scope subs will price the same way

1. Define the soil receiving condition before assigning topsoil and fine grading.
2. Separate irrigation supply power from field control wiring and system testing.
3. Give maintenance, acceptance and plant guarantees their own start and finish conditions.
4. Use one common bid basis for unresolved soil treatments and plant allowances.

For a GC estimator issuing a landscape package on a ground-up commercial project at bid-stage CDs, the scope should define **the condition the subcontractor receives, the installed work it delivers, and the obligations that continue after planting**. A plant schedule and an instruction to include irrigation do not establish a common pricing basis.

Write the package around three acceptance points: the soil handoff, the operational irrigation system, and the maintained landscape. Then state what each bidder carries between those points. That is the defensible way to make topsoil import, sleeves, controller wiring and plant guarantees comparable without prescribing every subcontractor's means and methods.

This guide is for a construction bid package or subcontract scope, not a routine grounds-maintenance contract. On design-build irrigation, add an explicit design responsibility and performance basis. Do not quietly turn an installation package into a design obligation.

## Build a document basis, not a list of Division 32 titles

Start with a dated drawing and specification register. Include the landscape plans, planting schedule, planting details, irrigation plans and details, civil grading and utility plans, paving details, electrical power plans, applicable Division 01 requirements and issued addenda. Identify sheet numbers and revisions, not just disciplines.

The useful distinction is between **where a requirement is described** and **which package carries it**. For example, the current public UFGS planting guide links exterior plants to earthwork, irrigation, turf and landscape establishment. Its planting section also contains soil testing, drainage, root barriers, edging and protection requirements. Those are broader than buying and setting plants. See [UFGS 32 93 00, Exterior Plants](https://www.wbdg.org/FFC/DOD/UFGS/UFGS%2032%2093%2000.pdf), sections 1.2, 1.4 and Parts 2 and 3.

Use these section titles as review prompts, then substitute the actual project sections:

- Earthwork, stripping, stockpiling and grading.
- Soil preparation or planting soils.
- Irrigation systems.
- Seeding, sodding or other specified turf installation.
- Exterior plants or planting.
- Landscape establishment and maintenance.
- Existing tree protection and preservation, wherever specified.
- Electrical service and controls affecting irrigation.
- Temporary water, protection, inspections and closeout.

The technical examples here use the publicly available UFGS guides checked on November 24, 2026: Earthwork, August 2023; Exterior Plants, August 2017 with Change 1 of August 2021; Irrigation Sprinkler Systems, August 2011 with Change 1 of May 2017; Sodding, April 2006 with Change 1 of August 2021; and Landscape Establishment, August 2017. These are editable guide specifications, not universal requirements for commercial projects. The issued contract documents control.

Do not copy their bracketed durations, soil properties or equipment options into a scope as though the designer selected them. If the documents leave a choice unresolved, obtain a clarification or state a common pricing basis to all bidders. For the broader package-building process, use the [construction scope generation guide](https://piper-ai.com/resources/construction-scope-generation-guide).

## Define the soil handoff by elevation, material and verification

“Fine grading included; topsoil by others” is incomplete. Fine grading of what material, received at what elevation, with what evidence of suitability?

Write the earthwork-to-landscape handoff as a receiving condition:

1. **Elevation:** identify the receiving surface relative to final soil or turf elevation, allowing for the specified soil profile and surface treatment.
2. **Material:** identify whether landscape receives subgrade, stockpiled topsoil or placed planting soil.
3. **Suitability:** identify who samples, tests, amends and obtains approval of the material.
4. **Quantity:** state who supplies any shortfall and how it is measured.
5. **Correction:** identify who corrects a nonconforming receiving surface before landscape work proceeds.

This combines two separate specification concerns. [UFGS 31 00 00, Earthwork](https://www.wbdg.org/FFC/DOD/UFGS/UFGS%2031%2000%2000.pdf) includes topsoil, stripping, stockpiling and finishing operations. [UFGS 32 92 23, Sodding](https://www.wbdg.org/FFC/DOD/UFGS/UFGS%2032%2092%2023.pdf), sections 2.3 and 3.1, expressly coordinates topsoil with Division 31 and notes that receiving subgrade elevation depends on the additional soil and surface treatment. A scope must resolve both ownership and the physical space for the material.

**Illustrative soil reconciliation, not a project result:** Assume the project detail requires 6 inches of placed soil across 18,000 square feet of turf. The geometric placed volume is:

18,000 SF × 0.5 FT ÷ 27 = **333.3 CY**.

Assume 240 CY of approved reusable soil is available on the same placed-volume basis. The import shortfall is **93.3 CY**. At an illustrative $72 per placed CY for import, placement and finishing, that shortfall represents **$6,718**, rounded. This simplified example excludes separate testing, amendments and quantity-conversion factors.

The important decision is not the subtraction. If earthwork delivers the area at final soil elevation rather than 6 inches below it, adding the required profile means removing approximately 333.3 CY first. The correct import quantity does not make the receiving condition correct. The scope needs a grade acceptance check before landscape mobilizes, not merely an import unit price.

For this example, a usable package statement would read:

> Landscape includes placement and fine grading of the specified 6-inch soil profile over the designated turf area. Earthwork delivers the receiving surface at the coordinated elevation below final soil grade. Base pricing assumes 240 CY of approved reusable soil, measured as placed volume, available at the designated stockpile. Landscape includes the remaining import requirement. The parties verify receiving grades and reusable soil suitability before placement; corrections to earthwork's receiving condition remain in the earthwork package.

Replace every quantity and allocation with the project basis. Do not compare stockpile, truck and placed quantities without stating the conversion assumptions.

### Give unknown amendments a common bid basis

A tested soil recommendation and a bid assumption are not the same thing. The planting and sodding guides distinguish application rates determined by laboratory analysis from rates entered specifically for bidding. See UFGS 32 93 00, section 3.3.4, and UFGS 32 92 23, section 3.1.2.

If the final laboratory recommendation is not available, choose a disclosed treatment basis with the design team rather than asking bidders to independently price “all required amendments.” State the assumed material, application rate, treatment area, incorporation depth and adjustment mechanism.

For example, **illustratively**, a common compost basis of 2 CY per 1,000 SF across 18,000 SF gives 36 CY. A later approved rate of 3 CY per 1,000 SF gives 54 CY, a change of 18 CY. At an illustrative installed adjustment rate of $95/CY, the change is $1,710. State whether the amendment is incorporated within the specified soil profile or changes that profile; do not automatically add it to the import volume.

This is a judgment call. On a fully designed hard bid, seek an issued clarification before changing the basis. At DD under CMAR, a stated pricing assumption and adjustment basis may be appropriate for the current estimate, subject to the agreed contract process. Where the design is not settled, preserve that distinction using [design-intent estimating for incomplete drawings](https://piper-ai.com/resources/design-intent-estimating-incomplete-drawings).

## Specify planting quality and the complete installation

Build inclusions by installation assembly, not by plant count alone. The planting guide addresses nursery certifications, plant size and root-ball size, delivery protection, storage, soil mixtures, drainage, mulch, support systems and installation. The sodding guide separately addresses species, soil preparation, handling, placement, rolling, watering and protection. These are useful prompts from [Exterior Plants](https://www.wbdg.org/FFC/DOD/UFGS/UFGS%2032%2093%2000.pdf) and [Sodding](https://www.wbdg.org/FFC/DOD/UFGS/UFGS%2032%2092%2023.pdf), not blanket instructions to include every option.

For the applicable project assemblies, spell out:

- **Plant identity and quality:** botanical name, cultivar, specified size, container or root-ball requirements, nursery selection and approval process.
- **Quantity basis:** landscape locations and schedule, with identified discrepancies resolved rather than silently choosing the cheaper count.
- **Installation:** layout approval, excavation, soil mixture, watering basins, mulch, support and protection accessories shown or specified.
- **Bed construction:** preparation, edging, root barriers, weed-control treatment and drainage where applicable.
- **Turf:** seed or sod type, area, preparation, installation, initial watering, protection and repair of disturbed areas.
- **Procurement:** approval before purchase, delivery timing, storage area and protection until installed.
- **Restoration:** limits of work disturbed by this package and treatment of damage caused by later trades.

Keep plant allowances separate from selected plants. An allowance should say whether it covers purchase only or complete installation, including freight, excavation, accessories, maintenance and the applicable guarantee. Ask for a replacement species or size as a defined alternate, not an unrecorded substitution in the base bid.

Existing tree protection needs its own assignment. UFGS 32 93 00, section 3.3.1, includes protection fencing and access planning around designated features. For the project scope, identify who installs, maintains and removes the protection, when it must be in place, and who controls work inside the protected area. A landscape subcontractor arriving near completion cannot be the sole answer to protection needed during early earthwork.

## Draw irrigation boundaries through the entire system

For irrigation, define the water connection, the controller supply and the field circuits separately. “Electrical by others” should not be allowed to erase all wiring from the landscape price.

[UFGS 32 84 24, Irrigation Sprinkler Systems](https://www.wbdg.org/FFC/DOD/UFGS/UFGS%2032%2084%2024.pdf) treats control wiring and conduit as irrigation components while separately requiring coordination of electrical service to the controller. It also includes pressure and operating tests, adjustment after grading and planting, and controller charts. The pricing boundary should preserve that whole chain.

Use a responsibility schedule like this, edited to the project:

| Interface | Landscape or irrigation package | Named other package and acceptance point |
| --- | --- | --- |
| Soil receiving surface | Verify condition; place assigned soils; fine grade | Earthwork delivers coordinated receiving elevation and material |
| Sleeves at new paving | Provide sleeve layout and assigned materials; verify access before piping | Paving or site utility package installs assigned sleeves before paving and records locations |
| Water supply | Irrigation work downstream of the stated connection; assigned backflow equipment and tests | Plumbing or site utilities delivers the stated connection with specified supply conditions |
| Controller power | Furnish controller; connect field controls; program and demonstrate system | Electrical provides assigned branch circuit, disconnect and supply termination |
| Field wiring | Valve and sensor wiring, splices and assigned conduit | Electrical scope confirms any separately assigned portions rather than excluding all controls |
| Plant establishment | Defined care, inspections and corrective work | GC or owner provides assigned access, water and documented takeover conditions |

This is an allocation example, not a recommended universal trade split. If landscape owns sleeve installation, move that obligation into its package and include the early mobilization. If paving owns it, landscape still needs to provide the coordinated sleeve information before paving begins.

State sleeve locations, sizes, quantities, endpoints, installation timing and verification responsibility. Distinguish sleeves under new paving from bores beneath existing paving; the irrigation guide addresses boring and restoration, which should not be treated as the same construction condition as an open-trench sleeve.

For design-build irrigation, identify the required design deliverables, designer qualifications, water pressure and flow basis, coverage and zoning criteria, approval process and treatment of inadequate supply. The UFGS irrigation guide expressly separates design-build drawing submittals and identifies supply pressure, plant water requirements and hydrozones in its system description. A promise of “complete irrigation” is not a substitute for these inputs.

There is another interface after installation: final head adjustment follows grading and planting in the guide. If another package changes finished grades, retain a return visit and an operational demonstration in the irrigation scope. Mechanical installation alone should not be the package's completion point.

## Put maintenance and guarantee obligations on separate clocks

Write three distinct obligations: care during installation, the defined establishment or maintenance period, and the plant guarantee. Give each a start condition, end condition, responsible party and acceptance evidence.

[UFGS 32 05 33, Landscape Establishment](https://legacy.wbdg.org/FFC/DOD/UFGS/UFGS%2032%2005%2033.pdf) begins maintenance immediately after installation, while its establishment periods commence upon specified inspections. It provides for irrigation inspection, winterization and startup, plant care, inspection reports and corrective work. Separately, UFGS 32 93 00, section 1.7, offers different guarantee arrangements and exceptions that must be selected for the project.

The combined consequence is easy to miss: a stated maintenance duration may not represent the entire service obligation. Installation care can precede the inspection that starts the formal period. Phased planting can also produce different clocks unless the contract establishes a common acceptance arrangement.

**Illustrative service basis:** If the package requires 12 weeks of establishment maintenance after an acceptance inspection, and the bid schedule assumes four weeks of installation care before that inspection, the planned service span is 16 weeks. At an illustrative $450 per weekly service visit, pricing only 12 visits carries $5,400 instead of $7,200, a $1,800 difference. This excludes water charges, replacements and seasonal services; the visit frequency is an example, not a guide-spec requirement.

Do not solve this by guessing a contingency. State the planned planting and inspection sequence, the included service basis, and how a delayed inspection or phased release is addressed under the contract.

The maintenance clause should name tasks and frequencies, irrigation checks, water source and charges, winterization or startup where applicable, access, reports, final inspection and corrective work. The guarantee clause should name its trigger, duration, plant condition criteria, exceptions, replacement work and any renewed obligation for replacement plants. Do not assume that a one-year guarantee includes one year of routine maintenance.

## Reusable landscaping and irrigation scope outline

Use the following as a drafting checklist. Every blank needs a project answer, not “per plans” repeated underneath it.

### A. General and document basis

Identify project, package limits, scope revision, drawing register, applicable specification sections and addenda. State whether irrigation is installation-only or includes design. Identify phasing, access, permitted planting windows, mobilizations, inspections and closeout requirements.

### B. Inclusions

Define soil receiving condition; topsoil reuse, import, testing, placement and fine grading; bid-basis amendments; complete planting and turf assemblies; irrigation piping, equipment, sleeves, controls and restoration; existing-feature protection assigned to the package; testing, demonstrations, records, maintenance and guarantees.

### C. Exclusions

List only affirmative exclusions consistent with the allocation schedule. For each excluded item, identify the package carrying it. Review topsoil import, sleeves, supply power, tree protection, routine maintenance and plant guarantees individually rather than accepting a blanket exclusion group.

### D. Work by others

Identify the named package, exact deliverable, location, receiving condition, required timing and verification. Include rough grades, reusable soil stockpile, water service, controller supply power and any sleeves installed by another package.

### E. Clarifications and bid assumptions

Record soil availability and suitability, amendment rates, plant quantity discrepancies, procurement substitutions, water supply basis, design inputs, planned acceptance sequence and maintenance service basis. Identify unresolved matters and the contractual route to resolve them.

### F. Alternates and allowances

State each alternate's complete affected assembly. Identify which planting, irrigation, soil, maintenance and guarantee costs change with it. Define plant allowances by quantity, size and covered cost components; keep them visible outside the selected-plant base.

### G. Unit prices

Request units that can actually be verified: placed CY of additional approved soil, installed quantity of a specified amendment, complete installed plant by species and size, sleeve by defined size and construction condition, or maintenance service under a defined task schedule. State inclusions, measurement, authorization, add and deduct treatment, and applicable minimum mobilization charges.

### H. Bidder response and buyout record

Require acknowledgment of the document basis, allocations, assumptions, alternates and exceptions. Reconcile exceptions before carry and preserve the agreed scope at buyout through the bid scope sheet and subcontract exhibit.

For unresolved assignments, keep the owner, source, decision deadline and pricing treatment in a scope gap register; for the separate task of identifying missing coverage, see landscaping and irrigation scope gaps.

## Keep the landscape package connected to its source decisions

The enduring record is not just the issued scope. It is the relationship between the soil profile, receiving grade, connection points, acceptance sequence and the packages carrying them.

[Piper's Scope Generation workflow](https://piper-ai.com/use-cases/scope-generation) brings drawings, specifications, addenda and company requirements together into trade-specific scopes with source references. It surfaces uncertain ownership and coordination items for review, and affected scope can be surfaced when upstream information changes.

For this package, the preconstruction team still decides the soil handoff, irrigation allocation and service obligations. The system's job is to keep those decisions connected to the project information behind them, not to replace the estimator's judgment with a confident assignment.

### What should a landscaping scope of work include?

Include the document basis, soil receiving condition, complete planting and turf assemblies, irrigation connections and controls, assigned protection, testing, maintenance and guarantees. Separate inclusions, exclusions, work by others, assumptions, alternates, allowances and unit prices so bidders can respond to the same basis rather than invent their own boundaries.

### Should landscaping include topsoil import and fine grading?

Only according to the project's explicit allocation. Identify who supplies, tests, places and amends the soil and who delivers the receiving grade. An exclusion of import does not define whether landscape receives bare subgrade, a stockpile or a completed soil profile, so spell out that physical handoff.

### Who should install irrigation sleeves and controller wiring?

Assign sleeves and wiring by deliverable, not by a blanket trade label. Sleeves may be installed by landscape or another site package, but layout and verification still need owners. Separate electrical supply to the controller from irrigation valve and sensor wiring, then retain the required operational testing in the scope.

### Is the plant guarantee the same as landscape maintenance?

No. Maintenance defines care and service obligations; the guarantee defines specified plant performance and replacement obligations. Record separate triggers and durations, including care before formal acceptance, treatment of phased planting and any conditions for replacements. Use the issued contract's terms rather than assuming a universal one-year arrangement.