---
title: 'Livingston Avenue bridge D900058: separate status, cost and interfaces'
url: 'https://piper-ai.com/resources/livingston-avenue-bridge-d900058-scope-status-guide'
description: 'Read NYSDOT’s current bridge contract and milestones alongside practical rail, movable-span and path handoff questions.'
contentTypes: [guide]
publishedAt: '2026-11-23T07:12:58.067Z'
author: 'Ido Gedanken, CEO'
readingTime: 2
---

# Livingston Avenue bridge D900058: separate status, cost and interfaces

The Livingston Avenue bridge replacement is an under-construction rail project, not a newly advertised construction opportunity on the basis of its status page. For a GC or CM assessing a potential interface, start with the current contract record and then obtain the actual access, testing and handover requirements for the work under consideration.

[NYSDOT identifies](https://piyn.dot.ny.gov/display/projects/livingstonavebridge) project 1SRP01 as contract D900058: a replacement drawbridge with a multi-use path connecting the Albany Skyway to a Rensselaer trail. The page, checked November 17, 2026, lists the project under construction and the contract award on May 17, 2024.

## Compare amounts and dates on their own terms

| Record | NYSDOT figure | Interpretation |
| --- | --- | --- |
| Award and current construction contract cost | $634,760,000 each | Current table shows no approved cost changes at the check date |
| Historical anticipated cost | $550 million | Earlier planning figure, not an additional funding amount |
| Estimated substantial completion | May 30, 2028 | Forecast milestone, not completed work |
| Original contract completion | June 29, 2028 | Original contractual completion date, not the substantial completion forecast |

The historical $550 million line and current award table have different dates and purposes. Do not add them or infer the reason for the difference without the underlying cost basis. NYSDOT defines original contract completion and estimated substantial completion separately on the same page; neither date proves completion.

## Examine four interfaces before a carry

These are analytical questions, not verified contract allocations or scheduled possessions.

- **Railroad operations:** Obtain the applicable access agreement, work windows, protection and approval process. Price constraints only from the governing documents; the status page does not provide possession windows.
- **Movable span:** Request the scope and acceptance sequence for mechanical, electrical and control work, testing and any railroad or agency witnesses. Identify prerequisites and who owns correction and retesting.
- **Path connections:** Trace the limits at both approaches, including grading, barriers, drainage and restoration where drawings require them. Confirm who delivers each tie and the sequence for access.
- **Owner handover:** Compare completion and acceptance requirements, as-built and training obligations, and any retained owner work. Do not equate a forecast substantial-completion date with every closeout obligation.

For an illustrative interface review, if a path contractor stops at a bridge approach, mark the physical termination on both drawings and ask who completes the connection and restores any disturbed work. Record the answer and revision with the carry. The example does not assert that this split exists on D900058.

Before pricing, request the relevant current contract drawings, amendments, schedule, access rules and testing matrix. The public status page does not give quantities, possession windows or trade allocations. [Review bid scope and responsibility gaps](https://piper-ai.com/resources/construction-bid-coverage-guide) when a defined solicitation exists, and [compare Albany project stages and evidence](https://piper-ai.com/resources/albany-public-project-stage-preconstruction-guide) for the distinction between project status and procurement.
