---
title: 'Logan L1465-C1: trace pump monitoring, supplied materials and commissioning'
url: 'https://piper-ai.com/resources/logan-l1465-monitoring-material-commissioning-boundaries'
description: 'Build a site-by-site estimate register for Logan pump monitoring, ALC-supplied communications materials and commissioning support.'
contentTypes: [guide]
publishedAt: '2026-11-22T17:06:34.735Z'
updatedAt: '2026-11-22T17:06:34.771Z'
author: 'Ido Gedanken, CEO'
readingTime: 3
---

# Logan L1465-C1: trace pump monitoring, supplied materials and commissioning

For an estimator reviewing Logan L1465-C1, the useful unit is a **monitoring location with a documented path and responsibility boundary**, not a new pump. Separate the 36 priority locations from the 14 alternate locations, then identify the installation, supplied material and commissioning support at each. Fifty locations do not establish a purchase of 50 new pumps.

The [Massport notice for L1465-C1](https://www.commbuys.com/bso/external/bidDetail.sda?docId=BD-19-1411-CAPPR-LOC1-124963&external=true&parentUrl=bid) advertised remote monitoring at Logan International Airport, with general bids scheduled for February 25, 2026. This is a historical advertised scope checked November 16, 2026, not evidence of an award or current construction. The notice describes on/off status, high water, flow and other data through remote terminal units linked to the Massport MOA network. It describes either a conduit route to a nearby communications room through a provided router cabinet or cellular service for locations away from communications rooms. It does not assign a route to every location.

## Build the location and alternate register

The notice places the locations across landside, airside, utility areas, tunnels, garages and offsite buildings. The notice groups 36 priority locations in the base and three add alternates: one at the tower pump station in Central Parking Garage, five in utility tunnels and eight in Terminal E utility space. The notice calls for a base and alternate pricing workbook; the workbook itself was not examined. [Source: Massport notice](https://www.commbuys.com/bso/external/bidDetail.sda?docId=BD-19-1411-CAPPR-LOC1-124963&external=true&parentUrl=bid).

Use the following as an estimator's register, populated from the actual drawings and workbook rather than as an owner-issued schedule:

| Register field | Record and decision |
| --- | --- |
| Location and bid bucket | Drawing identifier, site area, base or numbered alternate; reconcile counts without assuming an alternate is awarded. |
| Path and access | Indicated route or cellular designation, endpoints and access constraints; leave unknown where the issued documents are silent. |
| Material boundary | Each specified ALC-supplied item, delivery and custody assumptions, installation location and any missing item. |
| Installation boundary | Power, conduit and wiring shown; identify who carries each interface and any unresolved routing or restoration. |
| Commissioning support | Required availability, dependencies and estimated support effort; confirm scope and timing in the contract documents. |
| Evidence and status | Drawing and revision, trade quote, open question, owner response and carry or exclusion. |

For example, an **illustrative** tunnel alternate row should remain separate from a base site even if both need a communications interface. Record the drawing's actual route and the quote's endpoint, then ask whether power and conduit on either side are included. Do not turn an unconfirmed cellular designation into a hardwired quantity, or a missing endpoint into an assumed port assignment.

## Separate ALC supply from installation and support

The notice says the GC carries an ALC allowance, that ALC supplies specific materials, and that the GC installs those materials adjacent to the pump and in the network room, makes power connections and runs conduit and wiring. It does not establish the allowance amount or a complete material list in the excerpt. A material supply line is therefore not a complete installed-scope line: reconcile the supplied item, delivery point and installer with the electrical and communications quotations before carrying the cost. [Source: Massport notice](https://www.commbuys.com/bso/external/bidDetail.sda?docId=BD-19-1411-CAPPR-LOC1-124963&external=true&parentUrl=bid).

Massport says it will subcontract commissioning separately, outside L1465, while the GC is expected to be available to support it. Separately procured commissioning does not establish zero GC effort. Carry support only against the actual package requirements and documented estimate assumptions; seek the required attendance, access, sequencing and responsibility details before fixing the number. The notice does not provide a commissioning protocol, control logic or point list.

## Close the evidence before carrying the number

Obtain the location drawings, pricing workbook, specifications and issued addenda; map each site to its bid bucket and verify the ALC allowance and material schedule. Reconcile access, routes, installation and commissioning support with the affected quotes. Keep unanswered questions visible in the estimate, with their cost treatment and owner response, instead of silently assigning the same scope to all 50 locations.

Use the Boston public construction bid sources guide to verify the issued project scope and [the addenda workflow](https://piper-ai.com/resources/construction-addenda-management-for-gc-estimators) to trace scope changes to the controlling revision. The notice is a starting point, not a substitute for the issued set.
