# Loudonville reservoir upgrades: separate UV controls from lime-building work

At Loudonville Reservoir, a GC reviewing a future package should start with three boundaries: the completed 2024 UV equipment upgrade, the subsequent lime system and office conversion in the old chlorination building, and the separately planned Basin C inlet and walkway. Shared location does not make them one scope or one acceptance event.

The [December 2025 Albany Water capital plan](https://www.albanyny.gov/DocumentCenter/View/14038/Albany-Capital-Improvement-Program---CIP---Five-Year-2026-2030-PDF) reports the UV upgrade complete in 2024. It describes the old chlorination building conversion as partially completed in 2025 and planned for completion in 2026. That forecast does not establish present completion. The CIP is a planning-level case, not a current procurement notice. The relevant passages are printed pages 2-23 through 2-25 (physical PDF pages 33–35).

## Separate process equipment from the building and controls

The reported UV work included demolition of existing equipment and installation of reactors, lamps, UV transmittance monitors, operator interface terminals, programmable logic controllers, cabinets and SCADA integration. The converted building has an office in one half and the lime-feed system in the other. The plan's different dates and facilities warrant separate closeout records, even if a later contract interfaces with both.

The plan describes a deteriorating Basin C inlet accessible by boat and a planned replacement inlet and walkway, with repairs not scheduled at the time. That is an access and civil scope question, not evidence that inlet work was part of the UV or lime job. The plan also records discussion of relocating other chemical feed equipment. Discussion is not approval to relocate it, so request a specific owner decision before adding it to a scope.

## A boundary and acceptance register

The acceptance evidence below is a proposed diligence list, not a claim that a particular test or submittal was contractually required. The owner and designer should specify actual acceptance requirements.

| Boundary | Dated plan status | Evidence to request for a new package |
| --- | --- | --- |
| UV process and controls | UV equipment and SCADA integration reported complete in 2024 | Obtain UV closeout, equipment inventory, controls as-builts and acceptance records. Identify any interface to be protected or modified. |
| Lime system and converted building | Partial in 2025; completion planned for 2026 | Obtain current punch list and turnover, equipment and building drawings, and owner acceptance. Separate remaining process work from office and building work. |
| Shared controls or utilities | A possible interface to investigate; no new connection implied | Obtain current architecture and issued interface drawings. Define controls contractor, tie-in boundaries, outage authorization and testing responsibility. |
| Basin C inlet and walkway | Planned but unscheduled in 2025 | Obtain current design, access and operations constraints, permits and schedule before assigning civil or marine access work. |
| Other feed relocation | Discussed, not established as approved | Request a written decision and design before carrying relocation or associated building changes. |

For a hypothetical bid, a controls contractor may include a connection to an existing system while the process contractor excludes field wiring. Compare the interface drawings and proposal limits, then assign the missing connection explicitly if the current contract requires it. Do not assume that a UV closeout record accepts later lime-system work, or that a lime-system acceptance closes the inlet project.

## Request the records that decide the carry

Ask the owner for current status and procurement boundaries, the 2024 UV closeout package, lime conversion turnover and outstanding work, current controls drawings, and a Basin C design and access decision. Have operations confirm service constraints and the designer identify any new interface. Until those records are available, mark each interface as an open question instead of implying a treatment setting, an approved relocation or a construction start.

The [Albany Water capital-plan decision guide](https://piper-ai.com/resources/albany-water-capital-program-preconstruction-decisions) helps establish source and stage. Use [estimate scope coverage](https://piper-ai.com/resources/construction-bid-coverage-guide) to reconcile the issued packages and proposal exclusions.