title: 'Lower Roxbury: trace drainage, curb work and final paving by location'
url: 'https://piper-ai.com/resources/lower-roxbury-drainage-curb-paving-sequence-review'
description: 'Track utility, curb, sidewalk and final paving evidence by intersection across the Lower Roxbury Slow Streets project.'
contentTypes: [guide]
publishedAt: '2026-11-22T04:31:03.786Z'
updatedAt: '2026-11-22T04:31:03.801Z'
author: 'Ido Gedanken, CEO'
readingTime: 2
---

# Lower Roxbury: trace drainage, curb work and final paving by location

For Lower Roxbury Slow Streets, record status by intersection and by construction stage. A finished curb at one location does not establish final paving across the project, and the City's July 2026 handout was a tentative forecast, not proof of current production.

The [July handout](https://www.boston.gov/sites/default/files/file/2026/07/2026-0701%20Lower%20Rox%20Handouts.pdf), page 4, separates utility work, curb excavation and forming, sidewalk pours, and signs followed by paving and markings. It labels the schedule tentative and weather-dependent. The [City project page](https://www.boston.gov/departments/transportation/project/lower-roxbury-slow-streets) says in its August 2026 Harrison/Northampton update that final markings and paving follow completion of all project sidewalks and curbs.

## Location-by-stage evidence register

| Location from July handout | Record separately for each stage | Next evidence to obtain |
| --- | --- | --- |
| Tremont / Northampton | Utility; curb; sidewalk; signs and paving | Dated field or owner update and issued scope |
| Harrison / Northampton | Utility; curb; sidewalk; signs and paving | Reconcile August owner update to current record |
| Shawmut / Kendall and Shawmut / Lenox | Utility; curb; sidewalk; signs and paving | Location-specific status and remaining interfaces |
| Washington / Thorndike and Shawmut / Hammond | Utility; curb; sidewalk; signs and paving | Current sequence and access constraints |
| Washington / East Lenox and Harrison / East Lenox | Utility; curb; sidewalk; signs and paving | Current status and final-work dependency |

For each cell, enter the date, source, status and next decision owner. Leave it unknown until supported. The handout gave tentative durations of one to two weeks per location for utility work, two to three for curb forming and two to three for sidewalk pours, followed by one to two weeks for signs, paving and markings. These historical forecasts are not trade production rates or a contractual schedule. The chart does not establish precise date intervals for each location in this record.

## Use the dependency without inventing progress

If one intersection's drainage or utility work remains open, ask the owner and utility team for its current release and the curb subcontractor for the affected handoff. Compare that answer with the issued schedule and the City's stated project-wide final paving dependency. Record traffic access, restoration and remaining work as questions until supported by the package. Verify the procurement record and [trace its revisions](https://piper-ai.com/resources/construction-addenda-management-for-gc-estimators); an owner update alone does not establish final completion or a trade's contract obligations.