---
title: 'Manhattan prebid property research: which official sources answer each question?'
url: 'https://piper-ai.com/resources/manhattan-prebid-property-record-research-sources'
description: 'Choose the right NYC property records for a Manhattan bid, reconcile filings, zoning, landmarks and recorded documents, and identify what remains open.'
contentTypes: [guide]
publishedAt: '2026-11-27T05:08:54.063Z'
author: 'Ido Gedanken, CEO'
readingTime: 5
---

# Manhattan prebid property research: which official sources answer each question?

For a Manhattan alteration or infill bid, start with the question the estimate needs answered. Use BIS and DOB NOW for different parts of the filing history, ZoLa and the Zoning Resolution for zoning research, ZAP for land-use applications, Discover NYC Landmarks for designation, and ACRIS for recorded documents. None alone establishes the scope the GC should price.

First reconcile the address, borough-block-lot (BBL) and building identification number (BIN) with the owner and design team, particularly if a site contains multiple lots or buildings. Keep each identifier with the record retrieved. Then compare the evidence with the current issued bid documents and identify the missing decisions. This is a research workflow, not a title opinion, survey or zoning determination.

## Choose the record for the decision

The following routes complement each other. Retain the document or a dated search result where available, together with its identifiers and status. A screen capture records what was displayed on a date; it does not turn an application into an approval.

| Route | Question and search key | Evidence to retain | What it cannot establish alone |
| --- | --- | --- | --- |
| BIS | What older DOB jobs and building history appear? Use address or building identifier. | Property profile, job numbers, status and relevant record references. | Current issued scope or proof that filed work was built. |
| DOB NOW Public Portal | What applications were submitted in DOB NOW? Use address or building identifier. | Application numbers, status, certificates and relevant public records. | Complete historical filing history or the approved drawings themselves. |
| ZoLa | What zoning and mapped layers appear for the parcel? Use address or BBL. | Dated parcel and layer view and zoning references. | A survey, final project entitlement or a ruling on the proposed design. |
| Zoning Resolution and Special Midtown maps | What text and mapped area should the design team assess? Use district, map and parcel location. | Applicable text sections and map version with review date. | A project-specific determination from a map label alone. |
| ZAP | What land-use applications and status may relate to the site? Use address, BBL or known project identifier. | Project record, action status and available supporting decision documents. | That a proposal was approved or that approved work was constructed. |
| Discover NYC Landmarks | Is the property shown as designated or within a historic district? Use address and mapped property. | Building profile, designation type and designation report. | Approval of this project's proposed work. |
| ACRIS | What recorded property documents can be located? Use BBL or address. | Document identifiers, recording dates and relevant images. | A complete title search or a legal conclusion about present rights. |

DOB's [building-data guide](https://home4.nyc.gov/site/buildings/dob/find-building-data.page) says BIS includes pre-DOB-NOW permits and applications, along with jobs, occupancy, complaints, violations and inspections; the [DOB NOW Public Portal](https://www.nyc.gov/site/buildings/industry/dob-now-public-portal.page) contains applications submitted there. Search both, even if one produces an apparently complete history. DOB also provides a record-request route through DOB NOW: BIS Options for folders, plans and microfilm. A notice that material is ready for pickup is not the same as having the drawings in the bid room.

[ZoLa](https://zola.planning.nyc.gov/) is a starting point for mapped zoning and proposals. [NYC311](https://portal.311.nyc.gov/article/?kanumber=KA-02121) recommends having the address and BBL for zoning inquiries and says ZoLa zoning information is updated monthly. For land-use applications, use [ZAP](https://zap.planning.nyc.gov/projects); the city's [planning tools catalogue](https://www.nyc.gov/assets/planning/download/pdf/planning-level/community/catalogue-digital-tools.pdf?r=0820) describes application status and historical project data. Obtain the underlying decision and conditions when an application appears relevant.

[LPC's maps page](https://www.nyc.gov/site/lpc/designations/maps.page) links to Discover NYC Landmarks and designation reports. LPC recommends its interactive map to confirm historic-district inclusion because address ranges on older district PDFs reflect information available when those maps were drawn. [ACRIS](https://www.nyc.gov/site/finance/property/acris.page) provides Manhattan recorded-document images from 1966 onward. The [Department of Finance](https://www.nyc.gov/site/finance/property/property-recording-property-related-documents.page) distinguishes a records review from a title search and points to the Land Records Research Library for earlier documents.

## Read the Special Midtown map with the text

For a site potentially within Special Midtown, do not stop at a district label or assume that every Midtown parcel has the same requirements. [Zoning Resolution section 81-03](https://zr.planning.nyc.gov/article-viii/chapter-1/81-03) identifies maps for the district and subdistricts, East Midtown subareas, retail and street-wall continuity, and transit improvement areas. Locate the relevant parcel against the applicable maps, then ask the design team which current text provisions, exceptions and project facts govern the proposal.

Save the section and map references and the date checked. A parcel map is an aid to locating the question, not a boundary survey. A dated [City Planning FAQ](https://www.nyc.gov/assets/planning/downloads/pdf/zoning/downloadable-zoning-resources/zoning-faq.pdf) points researchers toward ZAP and ACRIS for certain historic permits and development-right declarations. Its 2021 numerical examples should not be used as current zoning authority or a calculation of this project's rights.

## Work through an illustrative Midtown alteration

Consider a hypothetical occupied building with a proposed facade alteration and rooftop addition. No address or actual parcel is being evaluated here. The team needs to decide whether its bid basis has enough information to price the envelope, temporary protection and rooftop work.

1. **Identify the site.** Obtain the owner's address, BBL, BIN, survey and the list of buildings and lots included in the contract. If identifiers differ across records, ask the owner to reconcile them before treating results as one building's history.
2. **Split the filing history.** Search BIS and DOB NOW, recording job numbers, descriptions and statuses separately. If an old alteration appears relevant to the roof structure, request the associated approved drawings and compare them with the issued design and site information. A filing record alone does not prove what was built; an approved drawing describes an approval, not necessarily current field conditions.
3. **Check mapped zoning and the proposal.** Locate the parcel in ZoLa, check the relevant Special Midtown maps and current text, and record any apparent subarea. Ask the architect to confirm applicability and whether the proposed addition depends on a land-use action. Search ZAP for relevant applications and obtain actual decisions and conditions. A pending or proposed action is not approval.
4. **Check designation and recorded documents.** Use Discover NYC Landmarks for the designation and report, then ask the design team what approval the proposed facade work requires and its status. Review relevant ACRIS documents, including any identified development-right declaration, with the owner and counsel. A record may raise a question about rights without resolving it.
5. **Price the issued basis.** Compare the answers and missing documents with the bid drawings, specifications and addenda. If facade details, roof capacity or approval conditions remain open, assign each question and state the estimate treatment: a defined assumption, allowance or exclusion, subject to the bid instructions and contract. Do not silently price a desired design as an approved one.

For the technical requirements after the evidence is assembled, use the [NYC preconstruction code review](https://piper-ai.com/resources/nyc-building-code-preconstruction-review). If the facade is in scope, the [facade repair scope review](https://piper-ai.com/resources/nyc-local-law-11-facade-construction-scope) separates inspection findings from a repair package. Once access and sequencing are understood, [price the logistics assumptions](https://piper-ai.com/resources/construction-logistics-plan-estimate-review) against the actual site plan.

## Keep an actionable source register

Create one row per consequential finding or unresolved question. A practical entry contains:

- **Identity:** address, BBL, BIN and any associated job, application or document number.
- **Evidence:** source URL, document title or image, record date, date checked and status. Keep the actual decision or drawing when obtained, not only its index entry.
- **Estimate consequence:** affected scope, trade, access constraint and issued drawing or specification revision used for pricing.
- **Open decision:** the question, named owner or design-team contact, required response date and current estimate assumption, allowance or exclusion.

For example, a public application index may point to an approval with conditions that the bid set does not reproduce. Record the application number and status, request the decision and conditions from the owner or design team, and identify which package may change. If the old approved plans are inaccessible, document the request and carry a clearly defined assumption only as the bid permits. Revisit the register when an addendum, revised drawing or determination arrives. Public records help identify what to ask; the current contract documents and responsible professionals establish the basis for the project decision.
