# Massachusetts 521 CMR: review cumulative renovation cost before fixing accessibility scope

A Massachusetts renovation estimate needs a cost and phase history before the design team can decide whether 521 CMR requires accessibility work beyond the immediate alteration. The Massachusetts Architectural Access Board identifies the [2006 edition as in force](https://www.mass.gov/lists/521-cmr-2006-edition). Section [3.3 and 3.5](https://www.mass.gov/files/documents/2018/10/17/521003.pdf) address alteration costs, full and fair cash value and work accumulated over 36 months, with qualifications and exceptions.

At 30% or more of the applicable full and fair cash value, section 3.3.2 can trigger whole-building compliance. Exempted work can still count in the calculation. Public-use status, tenant boundaries, exceptions and valuation need the designer's and, where appropriate, AAB's determination. Do not substitute a tax assessment or a single trade quote for that decision.

## Assemble a cost-history worksheet

| Input | Evidence to request | Open decision |
| --- | --- | --- |
| Public-use and tenant basis | Use, affected spaces and tenant boundaries | Designer determines applicable jurisdiction and exceptions |
| Work history | Costs and permits for work across the relevant 36 months | Designer identifies work included under the regulation |
| Current project | Trade and owner-furnished work, exclusions and phases | Reconcile complete alteration cost rather than just the current package |
| Valuation | Source and date of full and fair cash value evidence | Qualified reviewer establishes appropriate basis |
| Resulting scope | Designer or AAB decision and affected drawings | Carry building-wide work or unresolved allowance as appropriate |

If a fit-out is one of several phases, obtain earlier phase costs before fixing the GMP. List the valuation source and the person responsible for the determination; a missing history is a pricing uncertainty, not a conclusion that the threshold is or is not met. [Confirm the code basis with the design team](https://piper-ai.com/resources/construction-code-requirements-scope-review) and review [other Boston obligations](https://piper-ai.com/resources/boston-preconstruction-obligation-decision-guide).