# Massachusetts prompt payment: carry the review clocks into contract handoff

A Massachusetts private-project payment schedule needs two registers: one for progress applications and another for requests to increase the contract price. Confirm the contract’s coverage under [M.G.L. chapter 149, section 29E](https://malegislature.gov/Laws/GeneralLaws/PartI/TitleXXI/Chapter149/Section29E) before applying its clocks. Its definition includes lien eligibility, an original owner contract price of at least $3 million and an exclusion for projects of one to four dwelling units.

The law limits the periods established for submission, review and payment of progress applications and has a separate review clock for requests for increases in price. A written rejection must state the factual and contractual basis and include a good-faith certification. Conditional payment provisions are generally unenforceable except under the statute’s specified nonperformance and insolvency conditions. Tier and contract facts matter, so counsel should review the actual provisions. [Section 29E](https://malegislature.gov/Laws/GeneralLaws/PartI/TitleXXI/Chapter149/Section29E)

## Put each clock on its own event

For a covered contract, section 29E sets these maximum periods, subject to its conditions:

| Event | Statutory period | Handoff check |
| --- | --- | --- |
| Periodic progress submission | Submission intervals no longer than 30 days, beginning at the end of the first calendar month occurring at least 14 days after performance starts | Preserve commencement and the recurring submission calendar |
| Progress review | 15 days after submission, with seven additional days permitted at each lower tier | Identify recipient and tier |
| Approved progress payment | 45 days after approval, subject only to enforceable statutory payment conditions | Record approval separately from submission |
| Price-increase review | 30 days after the later of the work commencing or the written request being submitted, with seven additional days permitted at each lower tier | Preserve both dates |

Counsel should also review the statute’s deemed-approval provisions and its opportunity for rejection before payment is due. A missed review date does not justify treating every requested dollar as unconditionally payable. [Section 29E(c)–(e)](https://malegislature.gov/Laws/GeneralLaws/PartI/TitleXXI/Chapter149/Section29E)

## Register the receipt and the decision

| Item | Date and owner | Decision to preserve |
| --- | --- | --- |
| Progress application | Recipient records receipt and reviewer | Approval or written rejection, basis and certification |
| Price increase | Change reviewer records separate receipt | Response under the applicable price-increase process |
| Approved amount | Commercial lead records approval | Payment due date measured from approval; review-tier extensions do not add to the 45-day payment period |
| Conditional payment clause | Counsel and finance review at award | Applicability of statutory exceptions and contract language |

A submitted request is not an assurance that every amount will be paid. For example, if a field directive precedes agreement on price, record both the authority to proceed and the separate price request; [separate change authority from agreed price](https://piper-ai.com/resources/construction-change-directive-vs-change-order). Allocate review time and administration in the bid, and have counsel resolve unusual clauses before signature. Retainage has its own closeout sequence, while the [Boston obligation guide](https://piper-ai.com/resources/boston-preconstruction-obligation-decision-guide) screens other project obligations.