title: 'Mildred C. Hailey: separate preservation work from phased redevelopment'
url: 'https://piper-ai.com/resources/mildred-hailey-preservation-redevelopment-boundaries'
description: 'Keep retained-building modernization, completed housing, and future redevelopment boundaries distinct when reviewing the Mildred C. Hailey program.'
contentTypes: [guide]
publishedAt: '2026-11-21T15:01:55.437Z'
updatedAt: '2026-11-21T15:01:55.453Z'
author: 'Ido Gedanken, CEO'
readingTime: 2
---

# Mildred C. Hailey: separate preservation work from phased redevelopment

Do not build a Mildred C. Hailey estimate from a masterplan label alone. First identify the buildings, authority and phase covered by the actual package. Retained-building modernization and new-building redevelopment can involve overlapping systems and resident access needs, but a description of one does not assign work in the other.

The [designated developer's FAQ](https://haileyapartments.com/faq/) identifies Centre Street Partners and distinguishes BHA modernization outside the redevelopment area from the redevelopment program. It describes modernization topics including accessibility, kitchens and baths, plumbing, ventilation, heating and cooling, envelope, elevators, life safety and landscape. It also identifies subsequent construction locations. Separately, a [June 24, 2026 BHA release](https://www.bostonhousing.org/en/News/Mayor-Michelle-Wu-celebrates-Mildred-C-Hailey-Pha.aspx) celebrates completed homes at 2 and 6 Lamartine and a community center. A completed first phase is not evidence that a later package is available or that an individual unit can be accessed.

## Keep a boundary register by building and instruction

Use the following to prepare questions for the responsible owner and designer. It is not a claim that the work is assigned to a particular contractor.

| Program boundary | Question for the estimate | Authority and evidence to request |
| --- | --- | --- |
| Retained kitchens and baths | Which units and finishes are included, and what access sequence applies? | Building and unit schedule, scope and resident-access plan from the issuing authority |
| Existing envelope and MEP | What is retained, replaced or connected? | Current surveys, design documents and shutdown requirements |
| Elevators and life safety | What temporary operation and testing are required? | Issued phasing, protection and acceptance requirements |
| Demolition and relocation | Which buildings and preparatory work belong to this package? | Demolition limits and owner-approved relocation sequence |
| New streets and buildings | Where do new utilities and public routes connect to retained property? | Site plans, agency requirements and interface responsibilities |
| Occupied access | Who gives notice, coordinates entry and restores service? | Current resident coordination and logistics instructions |

For an illustrative interface, a new site utility may meet an existing building connection. The estimator should ask for the physical limit, shutdown window, temporary service and restoration owner. Keep the answer attached to the building and document revision; do not assume that a masterplan's description is a subcontract scope.

## Verify phase names before pricing

Obtain the current issuing authority's package, building schedule, logistics requirements and addenda. A capital-budget phase label and a developer's construction subphase need not describe the same scope. If the issue set leaves a boundary unresolved, state the assumption and request direction before bids are leveled. [Check the actual issued revision](https://piper-ai.com/resources/construction-addenda-management-for-gc-estimators) and do not infer an open solicitation from the public FAQ.

Before leveling proposals, compare the building and unit schedule with each bidder’s access, shutdown and restoration assumptions. Keep preservation and redevelopment answers in separate package records, then connect the approved boundaries through the [project scope review](https://piper-ai.com/resources/construction-scope-generation-guide). A building’s inclusion in the wider program does not establish that it belongs in this contract.