# North Hawk and Orange Street: reconcile court and stormwater scope

At North Hawk and Orange Street, a court price and a storm-sewer price do not by themselves demonstrate complete coverage. The estimating decision is where the porous playing surface, storage below it, retaining edges and controlled outlet meet, and which proposal carries each transition.

The [Albany Water capital plan](https://www.albanyny.gov/DocumentCenter/View/14038/Albany-Capital-Improvement-Program---CIP---Five-Year-2026-2030-PDF), printed sections 3-6 and 3-8 (physical PDF pages 60 and 62), describes a project at 127 Orange Street combining a separated Orange Street storm sewer, bioretention, regraded porous basketball court, subsurface stormwater management, retaining walls and seating. An actuated outlet valve uses real-time controls. The December 2025 plan anticipated construction beginning in 2026 but said the Water Board awaited an executed grant. That planning statement does not establish that a grant was subsequently executed, construction began, or a bid is open.

## Connect the court surface to the drainage system

The source describes the intended system, not the limits of individual trade contracts. The following is estimating analysis: use it to test proposed package splits once a current issued set exists.

| Boundary | Check against the issued revisions | Question for the carry |
| --- | --- | --- |
| Court elevations and storage | Grading, section and storage details at the same revision | Who owns subgrade preparation and the transition from porous surface to the system below? |
| Storage and sewer | Connection location, invert and any separation limits | Does either civil proposal carry the complete connection and reinstatement? |
| Walls, seating and landscape | Edge details, finished grades and adjacent bioretention | Who carries excavation, foundations and finish where the court meets a wall or seat? |
| Outlet valve and controls | Valve location, power, control sequence and testing requirements | Who supplies, installs, wires, programs and demonstrates each part if required? |
| Bioretention and court | Overflows, edge grades and planting limits | Are surface grading and drainage paths included consistently by both bidders? |

An illustrative mismatch: a court contractor prices the playing surface to the top of prepared base, while the civil contractor excludes final grading beneath the court. A low total may conceal the missing preparation. Request a defined elevation and a written interface before accepting either price as complete. Conversely, do not double-carry the same connection because both trades reference it without stating who performs it.

## Close the funding and design questions separately

Before committing an estimate, request the latest solicitation and addenda, grant and authorization status, civil and landscape sheets, control narrative, and any owner-defined work limits. Compare section cuts to the grading plan, then record the revision and proposed responsible bidder for every unresolved edge. Ask for a clarification where documents leave the outlet control, power or acceptance boundary unclear. These are questions for the current package, not requirements established by the capital plan.

The [Albany project-stage guide](https://piper-ai.com/resources/albany-public-project-stage-preconstruction-guide) helps separate capital planning from bid evidence. Use the [bid coverage guide](https://piper-ai.com/resources/construction-bid-coverage-guide) to compare the actual responses once a package is issued.